HomeMy WebLinkAboutBLD2026-00032 Storage - BLD Inspections - 4/20/2026 Department of Community Development
0MASON COUNTY 615 W.Alder St.Bldg 8,Shelton,WA 98584
COMMUNITY DEVELOPMENT 360-427-9670 ext.352
Permit Assistance tenter,Building,Planning www.MasonCountyWA.gov
INSPECTION CARD AND CERTIFICATE OF OCCUPANCY**
To schedule an inspection call or visit
https://masoncountywa.gov/departments/community_development/building/inspections/index.php
Permit Number BLD2026-00032 Date Issued 02/05/2026 Issued By
Project To store tools,miscellaneous items,and goat house.
Site Address 100 E COON DR NORTH
Applicant Greg Barich
Contractor
Contractor Phone
Primary Code 2021 IBC,IRC,IFC,IEC,IMC,& Type
Permit Type GARAGE/STORAGE Occupancy
-APPROVED PLANS MUST BE ONSITE FOR ALL INSPECTIONS.
-DO NOT PROCEED BEYOND EACH STAGE OR COVER WORK UNTIL APPROVAL IS GRANTED.
-THIS CARD MUST BE POSTED IN A CONSPICUOUS LOCATION,FRONT OF THE PREMISES IS BEST FOR MAKING ENTRY.
-ALL PERMITS EXPIRE 180 DAYS AFTER THE PERMIT IS ISSUED OR 180 DAYS AFTER DATE OF LAST INSPECTION.
-OWNER/AGENT IS RESPONSIBLE FOR REQUESTING ALL INSPECTIONS THROUGH FINAL INSPECTION.
**THIS STRUCTURE MAY NOT BE USED OR OCCUPIED UNTIL ALL APPROVALS ARE GRANTED.**
PRIOR TO CALLING FOR FINAL INSPECTION,ALL CONDITIONS OF THE PERMIT MUST BE MET
Public Works Access/Driveway Other
Health Septic Well
Deptartment
Planning Site Inspection
Department
Fire Marshall Fire Apparatus Access Fire Sprinkler
Auto Fire Alarm Hood and Duct
Other Final
Building Building Official: Community Services Designee
Department
Concrete Setbacks Slab
Footing Perimeter I I Point load Footing
Footing Interior teWte Footing Decks/Porches
Foundation Stem Walls Other
Rough-In Groundwork Plumbing Framing
Groundwork Mechanical Plumbing
Groundwork Gas Pipe Mechanical
Gas Piping Shear Wall Nailing '-Z.?'-2 pC
Underfloor
Other
Insulation Slab Ceiling
Floor Vaulted Ceiling
Walls Vapor Barrier
Other
Wallboard Interior Wall Brace Panels Fire Walls
Nailing
Other
Final Building .�
Manufactured Setbacks Setup
Home
Concrete Foot/Runners Final
Other
S j fro . - f
A
MASON COUNTY INSPECTION RESULTS Pagel 4
Department of Community Development
COMMUNITY DEVELOPMENT 615 W Alder St, Shelton, WA 98584
Permit Assistance Center,Building,Planning (360)427-9670 ext. 352
Application# BLD2026-00032 Application Type GARAGE/STORAGE Owner BARICH GREG A
Parcel# 222247590042 Site Address 100 E COON DR NORTH BELFAIR, WA
98528
Inspector Inspection Type Date Status Comments
2-9-26 DED
Dave Dobson SETBACK INSPECTION 02/09/2026 FAIL Plans and permit to be onsite and available for inspections. (No response at RV door
11:20am)
No inspection performed. Please reschedule. Do not pour
INSPECTION RESULTS Pagel
MASON COUNTY Department of Community Development
COMMUNITY DEVELOPMENT 615 W Alder St, Shelton, WA 98584
Permit Assistance Centel,Budding,Planning (360) 427-9670 ext. 352
Application # BLD2026-00032 Application Type GARAGE/ STORAGE Owner BARICH GREG A
100 E COON DR NORTH BELFAIR, WA
Parcel# 222247590042 Site Address
98528
Inspector Inspection Type Date Status Comments
2-11-26 DEC
FOOTING, WALL AND INTERIOR POINT LOADS DO NOT MATCH PLANS. FOOT
PRINT OF CONSTRUCTED FOUNDATION ADDS SQUARE FOOTAGE.
Drew Carlson FOOTING INSPECTION 02/11/2026 FAIL CONTACT ENGINEER OF RECORD TO PROVIDE A REVISION OR CONSTRUCT
FOOTING AND FOUNDATION PER ENGINEERED PLANS.
IF PLANS ARE REVISED SUBMIT PLANS AND NEW ENGINEERING TO MASON
COUNTY FOR APPROVAL.
Mason County
Mason County - Division of Community Development
615 W. Alder St.
QN C Building 8
Shelton, WA 98584
360-427-9670 ext 352
www.masoncountywa.gov
FBLD202'6-00032 GARAGE/ STORAGE
DESCRIPTION: TO STORE TOOLS, MISCELLANEOUS ISSUED: 02/05/2026
D GOAT HOUSE.
ESS: 100 E COON DR NORTH BELFAIR EXPIRES: 08/04/2026
PARCEL: 222247590042
APPLICANT: Greg Barich OWNER: BARICH GREG A
Po Box 1685 PO BOX 1828
Sumner, WA BELFAIR,WA 98528
3607312244
VALUATIONS: FEES: Paid Due
U VB Utility, miscellaneous 672.00 $44,674.56 State Fee-Residential $6.50 $0.00
Plan Check Fee $416.95 $0.00
Technology Surcharge $21.17 $0.00
Building Permit Fee $641.46 $0.00
Planning Residential Review $275.00 $0.00
Fee
Total: $44,674.56 Totals : $1,361.08 $0.00
REQUIRED INSPECTIONS
Setback Inspection Rough- Plumbing Inspection
Footing Inspection Mechanical Inspection
Foundation Wall-Pre-Pour Inspection Insulation Inspection
............. ........... .................•---• — — — — — — — —
Shearwall Inspection BLD-Final Inspection
Framing Inspection
CONDITIONS
All surface water and potential runoff must be controlled on site and shall not adversely affect any adjacent properties nor
increase the velocity flow entering or abutting to any state or county culverting/ditching system or road way.
------------------------------ --------------- ---
Printed by:Anna Schaffran on:02/05/2026 0343 PM
Page 1 of 4
Mason County
Mason County - Division of Community Development
615 W. Alder St.
C Building 8
Shelton, WA 98584
360-427-9670 ext 352
www.masoncountywa.gov
GARAGE/ STORAGE BLD2026-00032
By definition, propane tanks and heatpumps are structures, which must meet setback conditions. Please check your
"Approved Site Plan"to ensure these structures meet the setback conditions listed.
- - . . . . . . . ._ . . - -
* Landings and stairs must meet the same setback conditions as any permitted structure; and, must be shown on your site
plan. Please check your"Approved Site Plan"to ensure these structures are shown and meet the setback conditions listed.
* The international code requires a fire apparatus access road for every facility, building, or portion of a building that is more
than 150'from an approved access road. Roads are required to meet the minimum Mason County Fire Marshal standards
for Fire Apparatus Access Roads up to the point where such roads connect with a county maintained public road or to
another fire apparatus access road which connects to a county maintained public road.
* All construction must meet or exceed all local and state ordinances in addition to the International Codes requirements as
adopted and amended by Mason County and the State of Washington. Occupancy is limited to the approved and permitted
classification. Any non-approved change of use or occupancy would result in permit revocation.
* Concrete used for basement walls, foundation walls, exterior walls, porches, carport slabs, steps exposed to the weather,
garage floor slabs and other vertical concrete work exposed to the weather shall have a minimum compressive strength of
3000 psi (IRC Table R402.2).
* All other necessary permits from Mason County, Washington State, Federal Agencies, and/or other agencies/groups that
are required for this proposed development and construction must be obtained PRIOR TO DEVELOPMENT AND
CONSTRUCTION.
* The stamped approved site plan is required to be on-site for inspection purposes. If an inspection is requested and the
approved site plan is not on site, approval will not be granted. In addition, a re-inspection fee (refer to current fee schedule,
minimum 1 hour)will be charged and shall be collected by the Building Department prior to any further inspections being
performed or approvals granted.
* When parcel development requires direct access to county road(s), a Road Access Permit or Approval must be granted by
the Mason County Department of Public Works. For any construction which is proposed to be located within 25'of a Mason
County road right of way, it is suggested to contact that office to review future planned work which may affect your project.
For more information contact Public Works, at(360)427-9670, ext. 450 or 100 W Public Works Dr. Shelton. The building
permit will not be finaled until the permit holder can show proof that the access permit from Public Works has been finaled
and approved.
------ -- - ----------- - -
* REQUIREMENTS FOR ROOF COVERINGS. Roof coverings shall be applied in accordance with the applicable
provisions of the current code and the manufacturer's installation instructions.
A drip edge shall be provided at eaves and gables of shingle roofs.
--------------------------- _------------------......------....--------------___--------
* Retaining walls needed to support a surcharge such as structures, roads, or to support slopes, shall require a separate
building permit and approval prior to construction of the retaining wall.
* A Mason County Stormwater Management Worksheet was completed and signed as part of this building permit
application. Design, sizing, placement, inspection and maintenance of stormwater management systems shall be the
responsibility of the owner/agent of the developed parcel. It is the owner/agent/contractor's responsibility to ensure that
Mason County Department of Public Works has approved the stormwater site plan for this parcel prior to the commencement
of any development activities. *NOTE if Stormwater Management option "A" was selected on the Small Parcel Stormwater
Management Application/Worksheet the document entitled "Managing Storm Drainage on Small Lots, The Small Parcel
Stormwater Site Plan" constitutes an approved plan based on the criteria listed on the application/worksheet. If the
development has, or will have, a septic/drainfield system you are responsible for contacting Mason County Division of
Environmental Health to ensure that the stormwater system will not adversely affect the septic system of this, or any other,
parcel. You may also wish to consult with the septic design professional involved with the project. By calling for a final
inspection of the building permit the owner/agent/contractor is acknowledging that all components of the stormwater
management system have been installed as approved on the stormwater site plan. Under the requirements of Mason County
Stormwater Ordinance, either private ditches and drains will meet requirements of the stormwater ordinance or prior
approval will be granted to use an existing utility and drainage easement dedicated for that specific purpose.
Printed by:Anna Schaffran on:02/05/2026 03:43 PM
Page 2 of 4
t M
Mason County
Mason County - Division of Community Development
615 W. Alder St.
Building 8
Shelton, WA 98584
360-427-9670 ext 352
www.masoncountywa.gov
GARAGE/ STORAGE BLD2026-00032
* The use, handling and storage of hazardous materials or flammable and combustible liquids is not allowed without the
approval of the Mason County Fire Marshal.
* Provisions for surface/subsurface drainage control must be implemented with new construction or development on site and
MUST NOT adversely impact adjacent parcels. Under the requirements of Mason County Stormwater Ordinance, either
private ditches and drains will meet requirements of the stormwater ordinance or prior approval will be granted to use an
existing utility and drainage easement dedicated for that specific purpose. For further information regarding this ordinance
contact the Mason County Public Works Department prior to construction at Ext 450
.............................................
* All permits expire 180 days after permit issuance, or 180 days after the last inspection activity is performed.The Building
Official may grant one or more extension of 180 days, upon the receipt of a written extension request prior to permit
expiration. Letter must indicate that circumstances beyond the control of the permit holder prevented action from being
taken.
--- - ------ ----- -------- --- ---- --- - -- --------- ---- --- -. - - - ---- -------------....-
* WIND LOADS-Roof coverings shall be designed and tested to withstand the maximum basic wind speed.The basic wind
speed for Mason County is 85 mph with 110 mph gust factor.
-----------------•-- --------.......----.._-----------._--....--.---..-------•------.--..._.__..--.----•-----
* Concrete encased grounding electrodes must be installed and used at each new building or structure that is built upon a
permanent concrete foundation. In Mason County the electrical code is regulated by Washington State Department of Labor
& Industries(L&I).
For more information contact L&I for additional information. In Olympia call(360)902-6350 and in Bremerton call (360)415-
4000.
-------------•--_----- -----•------------------------•--•------------------------------------------------ ---._.
* Pressure treated wood manufactured after January 1,2004 may contain high concentrations of copper which could quickly
corrode metal fasteners, connectors, and flashing. Install metal connectors approved for contact with the new types of
pressure treated material.
* All property lines shall be clearly identified at the time of foundation inspection.
* All changes to"approved"building plans that effect compliance with the international codes as amended and adopted, or
any other Mason County ordinance or regulation, must be reviewed and approved by Mason County prior to construction.
--------- - ------ --------------------•--......-•-....------, ---------------•-.-------•-•----•---....._._..
* The foundation/footing must be placed on undisturbed,firm-native soil. Proper frost depth,minimum 12 inches,shall be
observed below grade in undisturbed soils.
------------------------- -------------------------------------------------------------------------------------.
* Approved per dimensions and setbacks on submitted site plan. Setbacks are measured from the farthest projection of the
structure. Front setbacks are measured from the front lot line or road easement boundary,whichever is closer.
----------- ---- ------------ -- ---- --------- -------- --------- - -- --------
* All RED stamped approved plans are required to be on-site for inspection purposes. If an inspection is called for and
plans are not available on site,then approval will not be granted. In addition,a re-inspection fee(refer to current fee
schedule, minimum 1 hour)will be charged and must be collected by the Building Department prior to any further inspections
being performed or approvals granted.
* Disclaimer: Mason County does not require a survey to obtain a building permit.As a result,site plans may not reflect
accurate data. It is the applicant's responsibility to comply with setback requirements.
* When parcel development requires direct access to state road(s),a-Road Access Permit or Approval must be granted and
approved by the Washington State Department of Transportation. For more information contact Washington State
Department of Transportation,at(206)357-2620, ext.630.
* Owner/Agent is responsible to post the assigned address and/or purchase and post private road signs in accordance
with Mason County Code 14.28 and 14.17.
* Contractor registration laws are governed under RCW 18.27 and enforced by the WA State Dept of Labor and Industries,
Contractor Compliance Division. There are potential risks and monetary liabilities to the homeowner for using an
unregistered contractor. Further information can be obtained at 1-800-647-0982.The person signing this condition is either
the homeowner,agent for the owner or a registered contractor according to WA state law.
- ------ ----------------------------------------------------------------------- ---------
Printed by:Anna Schaffran on:02/05/2026 03:43 PM
Page 3 of 4
0 Mason County
Mason County - Division of Community Development
615 W. Alder St.
Building 8
Shelton, WA 98584
360-427-9670 ext 352
www.masoncountywa.gov
GARAGE/ STORAGE BLD2026-00032
* OWNER/ BUILDER acknowledges submission of inaccurate information may result in a stop work order or permit
revocation. Acknowledgement of such is by signature below. I declare that I am the owner, owners legal representative, or
contractor. I further declare that I am entitled to receive this permit and to do the work as proposed. I have obtained
permission from all the necessary parties, including any easement holder or parties of interest regarding this project. The
owner or authorized agent represents that the information provided is accurate and grants employees of Mason County
access to the above described property and structure(s)for review and inspection. This permit/application becomes null &
void if work or authorized construction is not commenced within 180 days or if construction work is suspended for a period of
180 days. PROOF OF CONTINUATION OF WORK IS BY MEANS OF INSPECTION. INACTIVITY OF THIS PERMIT
APPLICATION OF 180 DAYS WILL INVALIDATE THE APPLICATION UNLESS OTHERWISE APPROVED.
* CONSTRUCTION PROCESS TO BE FIELD CORRECTED AS REQUIRED PER MASON COUNTY BUILDING
DEPARTMENT AND THE ADOPTED BUILDING CODE.
The construction of the permitted project is subject to inspections by the Mason County Building Department. All
construction must be in conformance with the international codes as amended and adopted by Mason County. Any
corrections, changes or alterations required by a Mason County Building Inspector shall be made prior to requesting
additional inspections.
* All building permits shall have a final inspection performed and approved by Mason County Building Department prior to
permit expiration.The failure to request a final inspection or to obtain approval will be documented in the legal property
records on file with Mason County as being non-compliant with Mason County ordinances and building regulations.
* The plan review check list and corrections are part of the approved plans and must remain attached. It is the responsibility
of the applicant, owner or contractor to make the required corrections indicated on the plans. Once the plans are marked
"APPROVED", they shall not be changed or altered without authorization from the Building Official. The permit holder is
responsible to retain the complete approved set of plans on site for the duration of the project. Failure to comply and/or
removal of approved documents will result in failure of required building inspections.
I hereby certify that I have read and examined this application and know the same to be true and correct.
All provisions of Laws and Ordinances governing this type of work will be complied with whether
specified herein or not. The granting of a permit does not presume to give authority to violate or cancel
the provisions f any other a/local law regulating construction or the performance of construction.
Issued By:
Contractor or Authorized Agent: Date: 2.. 5
Printed by:Anna Schaffran on:02/05/2026 03:43 PM
Page 4 of 4