HomeMy WebLinkAboutDept. of Commerce - Amendment # 1 Amendment
Contract Number: 24-63610-139
Amendment: 1
Local Government Division
Growth Management Services
2023-2025 Climate Planning Grant
1. Contractor 2. Contractor Doing Business As (optional)
Mason County
615 W. Alder St
Shelton, WA 98584
N/A
3. Contractor Representative (only if updated) 4. COMMERCE Representative (only if updated)
Marissa Watson
Senior Planner
(360) 427-9670 ext. 367
mwatson@masoncountywa.gov
Noelle Madera
Climate Operations Team Lead
(509) 818-1040
noelle.madera@commerce.wa.gov
PO Box 42525
1011 Plum St SE
Olympia, WA 98504-
2525
5. Original Contract Amount
(and any previous
amendments)
6. Amendment Amount 7. New Contract Amount
$125,000 No Change $125,000
8. Amendment Funding Source 9. Amendment Start Date 10. Amendment End
Date
Federal: State: X Other: N/A: Date of Execution June 30, 2025
11. Federal Funds (as applicable):
N/A
Federal Agency:
N/A
ALN:
N/A
12. Amendment Purpose:
The purpose of this amendment is to modify the scope of work and redistribute the budget among tasks.
COMMERCE, defined as the Department of Commerce, and the Contractor, as defined above, acknowledge and
accept the terms of this Contract As Amended and attachments and have executed this Contract Amendment on the
date below to start as of the date and year referenced above. The rights and obligations of both parties to this Contract
As Amended are governed by this Contract Amendment and the following other documents incorporated by reference:
Contractor Terms and Conditions including Attachment “A-1” – Scope of Work, Attachment “B-1” – Budget. A copy of
this Contract Amendment shall be attached to and made a part of the original Contract between COMMERCE and the
Contractor. Any reference in the original Contract to the “Contract” shall mean the “Contract as Amended”.
FOR CONTRACTOR FOR COMMERCE
Sharon Trask, Commission Chair
Mason County
Date
Mark K. Barkley, Assistant Director
Local Government Division
Date
APPROVED AS TO FORM ONLY
Sandra Adix
Assistant Attorney General
3/20/2014
Date
Docusign Envelope ID: B820869A-8A17-4ADD-9F85-E02F3324021B
3/11/2025 | 8:37 AM PDT 3/11/2025 | 9:52 AM PDT
Amendment
2
This Contract is amended as follows:
Attachment A Scope of Work is hereby replaced in its entirety by Attachment A-1
Scope of Work.
Attachment B Budget is hereby replaced in its entirety by Attachment B-1 Budget.
ALL OTHER TERMS AND CONDITIONS OF THIS CONTRACT REMAIN IN FULL FORCE
AND EFFECT.
Docusign Envelope ID: B820869A-8A17-4ADD-9F85-E02F3324021B
Amendment
3
Attachment A-1: Scope of Work
Mason County
Scope of Work for Climate Planning—Climate Resilience Sub-Element
Section Steps,
Tasks, and
Deliverables
Description End Date
Section 2: Climate
Policy Creation
Initiate Project 11/2023 – 01/2025
Task 2.1 Form Climate Policy Advisory Team
Task 2.2 Establish engagement strategy that supports
environmental justice.
Review Comprehensive Plan PPP and revise
as needed.
Deliverable 1 In-Progress Climate Element Workbook
Sections 2.1, 2.2 completed
01/31/2025
Resilience Sub-
Element
Sec. 3, Step 1
Explore Climate Impacts 12/2024 – 03/2025
Task 3.1.1 Identify community assets
Use existing Mason County Critical Facilities
& Critical Infrastructure Map and other
sources.
Task 3.1.2 Explore hazards and changes in the climate
Use existing Mason County earthquake,
flood, fire, landslide hazard, and liquefaction
maps; UW’s Climate Mapping for a Resilient
Washington webtool; NOAA’s Climate
Resilience Toolkit and Climate Mapping for
Resilience and Adaptation tool; and WA
DOC’s climate website resources.
Docusign Envelope ID: B820869A-8A17-4ADD-9F85-E02F3324021B
Amendment
4
Task 3.1.3 Pair assets and hazards and describe
exposure and consequences.
Use existing Mason County Risk
Assessment.
Task 3.1.4 Identify priority climate hazards
Deliverable 2 In-Progress Climate Element Workbook
Sections S3 Task 1.1, S3 Task 1.2, S3 Task
1.3, and S3 Task 1.4 completed
03/15/2025
Resilience Sub-
Element
Sec. 3, Step 2
Audit Plans & Policies 02/2025 – 04/2025
Task 3.2.1 Review existing plans for climate gaps and
opportunities.
Review Comprehensive Plan and Hazard
Mitigation Plan.
Task 3.2.2 Determine next step; for each climate hazard
identified in Task 3.1.4, complete Climate
Workbook questionnaire.
Deliverable 3 In-Progress Climate Element Workbook
Sections S3 Task 2.1 and S3 Task 2.2
completed.
04/15/2025
Resilience Sub-
Element
Sec. 3, Step 3
Assess Vulnerability & Risk 04/2025 – 05/2025
Task 3.3.1 Assess sensitivity of community assets.
Select appropriate indicators and develop
assessment rules, including composites for
multiple indicators.
Task 3.3.2 Assess adaptive capacity of community
assets.
Select appropriate indicators and develop
assessment rules, including composites for
multiple indicators.
Docusign Envelope ID: B820869A-8A17-4ADD-9F85-E02F3324021B
Amendment
5
Task 3.3.3 Characterize vulnerability of community
assets.
Establish composite, qualitative rating using
sensitivity and adaptive capacity ratings.
Task 3.3.4 Characterize risk of community assets.
For medium/high vulnerability assets.
Task 3.3.5 Decide course of action.
Meet with partners, stakeholders, and
decision makers to accept risk or take action.
Deliverable 4 In-Progress Climate Element Workbook
Sections S3 Tasks 3.1-3.3 and S3 Tasks 3.4-
3.5 completed; documentation of applicable
indicators/rules explained clearly.
05/15/2025
Resilience Sub-
Element
Sec. 3, Step 4
Pursue Pathways 05/2025 – 06/2025
Task 3.4.1 Adapt/expand existing goals where possible
and develop new goals where needed.
Task 3.4.2 Adapt/expand existing policies where
possible and develop new policies where
needed.
Task 3.4.3 Identify policy co-benefits
Deliverable 5 In-Progress Climate Element Workbook
Section S3 Tasks 4.1-4.3 completed
06/15/2025
Resilience Sub-
Element
Sec. 3, Step 5
Integrate Goals & Policies 05/2025 – 06/2025
Task 3.5.1 Review and finalize resilience goals and
policies.
Task 3.5.2 Consult with partners and stakeholders.
Docusign Envelope ID: B820869A-8A17-4ADD-9F85-E02F3324021B
Amendment
6
Deliverable 6 Completed Climate Element Workbook
Section S3 Step 5 completed
06/15/2025
Task 5 Planning Commission and City Council
Meetings
04/2025 – 06/2025
Final Deliverable
Deliverable 7
Draft Climate Element with Resilience
goals and policies
06/30/2025
Docusign Envelope ID: B820869A-8A17-4ADD-9F85-E02F3324021B
Amendment
7
Attachment B-1: Budget
Deliverables Commerce
Grant Funds
1 In -Progress Climate Element Workbook
Sections 2.1, 2.1 completed
$5,982.29
2 In -Progress Climate Element Workbook
Sections S3 Task 1.1, S3 Task 1.2, S3 Task 1.3, and S3
Task 1.4 completed
$25,000
3 In -Progress Climate Element Workbook
Sections S3 Task 2.1 and S3 Task 2.2 completed
$25,000
4 In -Progress Climate Element Workbook
Sections S3 Tasks 3.1-3.3 and S3 Tasks 3.4-3.5
completed
$20,000
5 In -Progress Climate Element Workbook
Section S3 Tasks 4.1-4.3 completed
$20,000
6 Completed Climate Element Workbook
Section S3 Step 5 completed
$10,000
7 Draft Climate Element with Resilience
Goals & Policies
$19,017.71
Contract Total
$125,000
Docusign Envelope ID: B820869A-8A17-4ADD-9F85-E02F3324021B