Washington State Olympic Region
Department Of Transportation Environmental and Hydraulic Services Office
150 Israel Road SW, FI 4,Tumwater
Paula J. Hammond, P.E. PO Box 47417
Secretary of Transportation Olympia,WA 98504-7417
360-570-6700/Fax 360-570-6697
TTY: 1-800-833-
March 9, 2011 www.wsdot.wa.go/fE CEWZ D
MAR 1 W1 i
Department of Ecology
Environmental Review Section MASON CO. PLANNING DEPL
PO Box 47703
Olympia, WA 98504-7703
RE: SEPA Register
Dear SEPA Reviewer:
Attached is a copy of the Environmental Checklist and Determination of Non-
Significance(DNS) for your information and publication in the SEPA Register, in
accordance with WAC 197-11-340(2).
Project: US Highway 101/South of Beacon Point—Major Drainage
Mile Post 316.06 to Mile Post 316.26
If you have any questions,please contact Phil Ambrosino at(360) 570-6731 or Dave
Evans at (360) 570-6738.
Sincerely
Jeff Sawyer
Environmental &Hydraulics Manager
Olympic Region
JBS:paa:par
Enclosures: DNS
Environmental Checklist
Vicinity Map &Plan Sheets
cc: W. Ron Allen,Jamestown S'Klallam Tribe w/enclosures
Kathleen Duncan,Jamestown S'Klallam Tribe w/enclosures
Annette Nesse, Jamestown S'Klallam Tribe w/enclosures
Francis Charles, Lower Elwha Klallam Tribe w/enclosures
William S. White, Lower Elwha Klallam Tribe w/enclosures
Carol Brown, Lower Elwha Klallam Tribe w/enclosures
Jeromy Sullivan, Port Gamble S'Klallam Tribe w/enclosures
Department of Ecology
March 9, 2011
Page 2 of 2
Josh Wisniewski, Port Gamble S'Klallam Tribe w/enclosures
Joe Sparr, Port Gamble S,Klallam Tribe w/enclosures
Charles `Guy' Miller, Skokomish Tribe w/enclosures
Kris Miller, Skokomish Tribe w/enclosures
Lennea Magnus, Skokomish Tribe w/enclosures
Leonard Forsman, Suquamish Tribe w/enclosures
Dennis Lewarch, Suquamish Tribe w/enclosures
Alison O'Sullivan, Suquamish Tribe w/enclosures
Penny Kelley, WDOE w/enclosures
Margie Schirato,WDFW w/enclosures
Allan Borden, Mason County Community Development w/enclosures
Jerry Moore w/enclosures
Project File w/enclosures
SF03092011(5975)
SEPA Contact List
MASON COUNTY DCD
Sent X-f fA�T Oj�i�PJ`W.1 to(check all that apply)on I )
Skokomish Tribal Nation, Nat. Res. Dept. WA Department of Ecology
ATTN: Randy Lumper Environmental Review Section
N 541 Tribal Center Rd., Skokomish Nation,98584 PO BOX 47703, Olympia,98504-7703
rlumper@skokomish.org separegister@ecy.wa.gov
Skokomish Tribal Historic Preservation Officer WA Department of Commerce
ATTN: Kris Miller reviewteam@commerce.wa.gov
80 N Tribal Center Rd, Skokomish Nation, 98584
shlanayl@skokomish.org Ep U.S.Army Corps of Engineers
SEPA Reviewer-Darren Habel
r7 Quinault Indian Nation PO Box C-3755, Seattle, 98124
ATTN: Mark Mobbs darren.habel@usace.army.mil
PO Box 189,Tahola, 98587
mmobbs@quinault.org WA Dept.of Fish and Wildlife
hpapplications@dfw.wa.go\
Squaxin Tribal Nation, Natural Res. Dept.
2952 SE Old Olympic HWY,Shelton 98584 WA Dept.of Fish and Wildlife
jdickison@squaxin.u: ATTN: Margie Bigelow
(Habitat Biologist-S Puget Sound Watershed)
The Confederated Tribe of the Chehalis 2391 W Deegan Rd.,Shelton,98574
ATTN:SEPA Reviewer-Glen Connelly margaret.bigelow@dfw.wa.gov
420 Howanut Rd.,Oakville,98568
goonnelly@chehalistribe.org WA Dept.of Fish&Wildlife
ATTN: Leonard Machut
r7 WA DNR, South Puget Sound Region (Habitat Biologist-Hood Canal Watershed)
950 Farman Avenue N, Enumclaw,98022-9282 48 Devonshire Rd, Montesano,98563-9618
southpuget.region@dnr.wa.gov leonard.machut@dfw.wa.gov
IDWA DNR,Aquatic Resources WA Dept. of Transportation
PO BOX 47027,Olympia, 98504-7027 Ait.'aw-d�i/ 5
and@dnr.wa.gov P.O. Box 47440,Olympia 98504-7440 II
WA DNR, SEPA Center GtRtv1S W5U WQ q�✓
ATTN: External Coordinator City of Shelton ��fJ
0
PO BOX 47015, Olympia,98504-7015 ATTN:Jason Dose
se acenter dnr.wa. ov 525 West Cota St.
P @ 9 ,Shelton 98584
jasond@ci.shelton.wa.us
Olympic Region Clean Air Agency
ATTN:Aaron Manley Port of Shelton
2940-B Limited Ln. NW,Olympia. 98502 ATTN: Brandon Palmer
aaron.manley@orcaa.org 21 West Sanderson Way, Shelton 98584
BrandonP@portofshelton.com
Mason County Transit
ATTN: Mike Oliver Office of Archaeology&Historic Preservation
PO Box 1880, Shelton,98584 ATTN: Lance Wollwage
moliver@masontransit.org P.O. Box 48343, Olympia, 98504-8343
Lance.Wollwage@dahp.wa.gov
Mason County PUD#1
ATTN: Jocelyn Gray Tacoma Public Utilities-Real Property Services
N 21971 Hwy 101,Shelton, 98584 ATTN: Dave Letterman
jocelyneg@mason-pudl.org 3628 S 35th St,Tacoma, 98409-3192
dletterm@cityoftacoma.org
Mason Cty P.W.ATTN:
Other:
Mason Cty E.H.ATTN: School District:
Agent:
Mason Cty Bldg ATTN:
Applicant:
�I
MC DCD last updated on 1 1/20120 1 4
RECEIVED.
JUN 2 7 Nil
426 W. CEDAR ST
Adolk State Environmental Policy Act
MWashington State
Department of Transportation DETERMINATION OF NONSIGNIFICANCE
Description of proposal: US Highway 101/South of Beacon Point—1Major Drainage
The purpose of this major drainage project is to replace an existing 36-inch diameter
culvert that provides conveyance for an unnamed creek, a non-fish bearing stream, that
drains into Hood Canal. The existing culvert is located in a deep roadway fill. The culvert
is failing due to joint separation and collapsing of the pipe. Failure of the embankment
would cause the closure of US 101. Therefore repair requires installation a new 90-foot,
36-inch diameter culvert. A trenchless method will be used to jack the new culvert
through the roadway fill from the west side of the highway in the summer of 2011.
Project work includes "jacking" the replacement culvert pipe through the roadway fill,
slope work, plug and fill the existing culvert pipe, minor stream re-alignment and
guardrail installation on both sides of the roadway
Proponent: Washington State Department of Transportation
Location of proposal: The project is located on US Highway 101, Mile Post 316.06 to Mile
Post 316.26 in Section 12,Township 24 North, Range 3 West, W.M. in Mason County.
Lead Agency: Washington State Department of Transportation
The lead agency for this proposal has detennined that it does not have a probable significant
adverse impact on the environment. An environmental impact statement (EIS)is not required
under RCW 43.21 C.030(2) (c). This decision was made after review of a completed
environmental checklist and other information on file with the lead agency. This information is
available to the public on request.
X This DNS is issued under WAC 197-11-340(2); the lead
agency will not act on this proposal for 14 days
from the date of signature below. Comments must be
Submitted by: April 1, 2011
Responsible Official: JEFF SAWYER
Position/Title: Environmental & Hydraulics Manager
Olympic Region
Phone: 360-570-6701
Address: PO Box 47417
Olympia, WA 98504-7417
p�
Date: � Signature:
X4,0MIQ
Addbk
•:� ' MoDepartment
Washington State
of Transportation
• ?�' R+
•J f
State Environmental Policy Act • Environmental Checklist
The State Environmental Policy Act (SEPA), Chapter 43.21 C RCW, requires all governmental agencies
to consider the environmental impacts of a proposal before making decisions. The purpose of this
checklist is to provide information about the proposal to interested parties, to help identify impacts of the
proposal (and to avoid or reduce impacts from the proposal, if possible) and to help the lead agency
decide whether an Environmental Impact Statement is required. The checklist questions apply to all parts
of the proposal, even if they are planned over a period of time. Attached is additional information that
will help describe the proposal or its environmental effects.
A. BACKGROUND
1. Name of proposed project, if applicable:
US Highway 101, South of Beacon Point—Major Drainage
2. Name of applicant and lead agency:
Washington State Department of Transportation
Olympic Region
Attention: Mr. Jeff Sawyer, Environmental and Hydraulic Services Office
3. Address and phone number of applicant and contact person:
Mr.Jerry Moore Jeff Sawyer
Project Engineer Region Environmental Manager
P.O. Box 47440 PO Box 47417
Olympia,WA 98504-7440 Olympia,WA 98504-7417
Telephone: (360) 565-0622 Telephone: (360) 570-6701
Fax: (360) 565-0678 Fax: (360) 570-6697
4. Date checklist prepared:
March 2011
5. Proposed timing or schedule (including phasing, if applicable):
Anticipated project advertisement date is August 8,2011, with work scheduled
for 45 working days between mid-September and mid-October 2011.
6. Are there any plans for future additions, expansions, or further activity related to or
connected with this proposal?Ifyes, explain.
No
7. List any environmental information you know about that has been prepared, or will
be prepared, directly related to this proposal.
National Environmental Policy Act—Documented Categorical Exclusion
State Environmental Policy Act—Determination of Non-Significance
A Biological Assessment for U.S. Fish and Wildlife Service
• A Biological Assessment for National Marine Fisheries Service
Wetland Biology Report
Cultural Resources Report
Documentation of formal consultation and Section 106 Concurrence with State
Historical Preservation Officier,Jamestown S'Klallam, Lower Elwha Klallam,
Port Gamble S'Klallam, Skokomish and Suquamish Tribes for compliance with
the National Historic Preservation Act.
8. Do you know whether applications are pending for governmental approvals of other
proposals directly affecting the property covered by the proposal? If yes, explain.
No
9. List any government approvals or permits that will be needed for the proposal, if
known.
Critical Area Ordinance Review by Mason County
Army Corps of Engineers 404 Nationwide Permit
Coastal Zone Management Consistency Determination
Section 401 Water Quality Certification by Ecology
Hydraulic Project Approval by Washington Department of Fish and Wildlife
Forest Practices Approval(to be acquired by contractor)
10. Give brief, complete description of the project including(but not limited to) its size,
general design elements, and other factors that will give an accurate understanding
of its scope and nature. There are several questions in this checklist that ask you to
describe certain aspects of the proposal. You do not need to repeat those answers on
this page.
This Major Drainage project will utilize a pipe"jacking" method to install a new
culvert under US Highway 101. The existing cross culvert, located in a deep
roadway fill, is failing.Work will include "jacking a 90 linear foot,36 inch
culvert pipe through the roadway fill, slope work,plug and filling the existing
culvert pipe, minor stream re-alignment, and guardrail installation on both sides
PPS g �
of the roadway.
11. Location of the proposal. Give sufficient information for a person to understand the
precise location of the proposed project, including a street address, if any, and
section, township, and range, if known. If a proposal would occur over a range of
area,provide the range or boundaries of the site(s). Provide a legal description, site
plan, vicinity map, and topographic map, if reasonably available.
This project is located on US Highway 101 between Mile Post 316.06 and Mile
Post 316.26 in Mason County, Township 24 North, Range 3 West,West 1/ of
Section 12,Willamette Meridian. This project lies adjacent to the Hood Canal
between the communities of Brinnon (5.8 miles North) and Lilliwaup (10.9 miles
South).
-2-
B. ENVIRONMENTAL ELEMENTS
1. EARTH
a. General description of the site (underline one):Flat, rolling, hilly, steep slopes,
mountainous, other:
Rural, forested area,with a rolling and curved highway.
b. What is the steepest slope on the site (approximate percent slope)?
Steepest slope on the site is 67%.
c. What general types of soils are found on the site (for example, clay, sand, gravel,
peat, muck)? If you know the classification of agricultural soils, specify them and
note any prime farmland.
Project is located within the Hoodsport stony sandy loam. There is no prime
farmland.
d. Are there surface indications of history of unstable soils in the immediate
vicinity? If so, describe.
A site visit was conducted in January 2011. No evidence of recent instability
was found.
e. Describe the purpose, type, and approximate quantities of any filling or grading
proposed. Indicate source of fill.
Upslope side: Fill will be utilized to redirect the unnamed stream to the new
culvert inlet. Type of fill will be both native and select borrow supplied by
the contractor from a WSDOT approved source. Approximate quantity will
be 130 cubic yards.
Downslope side: Grading will be performed to provide an access road to the
culvert outlet area. Fill will be utilized at the culvert outlet to give the
roadway slope extra integrity for the"jacking" operation.Type of fill will be
rip rap and granular material supplied by the contractor from a WSDOT
approved source. Approximate quantity will be 160 cubic yards (90 cubic
yards of rip rap and 70 cubic yards of granular material).
f. Could erosion occur as a result of clearing, construction, or use? If so, generally
describe.
Some erosion may occur during construction,which will be minimized using
Best Management Practices (BMP's).
g. About what percent of the site will be covered with impervious surfaces after
project construction (for example, asphalt or buildings)?
No added impervious surfaces for this culvert replacement project.
h. Proposed measures to reduce or control erosion, or other impacts to the earth, if
any:
-3-
Erosion will be controlled by preparation and implementation of a
Temporary Erosion and Sedimentation Control(TESC) Plan utilizing Best
Management Practices. The existing culvert will be utilized to maintain
stream flow during construction of the new culvert. The stream will be
redirected to the new culvert at the completion of construction.
2. AIR
a. What types of emissions to the air would result from the proposal(for example:
dust, automobile, odors, industrial wood smoke) during construction and when
the project is completed? If any, generally describe and give approximate
quantities if known.
There will be hydrocarbon exhaust emissions from excavators, dump trucks,
loaders, compaction equipment, sweepers,pickup trucks, delivery trucks,
and pipe jacking equipment during construction activities. Air quality is
expected to return to normal after construction
b. Are there any off-site sources of emissions or odor that may affect your proposal?
If so, generally describe.
No
c. Proposed measures to reduce or-control emissions or other impacts to air, if any:
Water or other BMP's will be used to control dust if necessary.
3. WATER
a. Surface:
1) Is there any surface water body on, or in, the immediate vicinity of the site
(including year-round and seasonal streams, saltwater, lakes,ponds, ,
wetlands)? If yes, describe type and provide names. If appropriate, state
what stream or river it flows into.
There is a perennial, unnamed stream that flows through the project site
and empties into Hood Canal.
2) Will the project require any work over, in, or adjacent to (within 200 feet) the
described waters? If yes,please describe and attach available plans.
Project work will require constructing a"jacking pit" adjacent to the
unnamed stream for the equipment needed to install the new culvert
under US Highway 101 and for the stream realignment.
3) Estimate the amount of fill and dredge material that would be placed in or
removed from surface water or wetlands and indicate the area of the site that
would be affected. Indicate the source offill material.
Excavation of the "jacking" pit will require removal of 55 cubic yards of
material from surface waters over an area of 300 square feet and 2 cubic
yards of material from the wetland over an area of 130 square feet.
-4-
Fill will be utilized to redirect the unnamed stream to the new culvert inlet.
Approximate quantity of fill that will be placed into surface waters will be
130 cubic yards over an area of 400 square feet and 10 cubic yards over an
area of 50 square feet. This will be done during the in-water work window
and appropriate Best Management Practices will be utilized to minimize
turbidity and maintain water quality standards.
4) Will the proposal require surface water withdrawals or diversions? Give
general description,purpose, and approximate quantities if known.
The project work will not withdraw water. The existing culvert will convey
the unnamed stream while the new culvert is "jacked"through the roadway
fill.The new culvert inlet will be offset 25 feet from the existing culvert inlet.
The new culvert will have an outlet directly above the existing culvert and
use the same streambed at the discharge point. Once the new culvert is
installed,the unnamed stream will be redirected to the new pipe inlet.
S) Does the proposal lie within a 100 year floodplain? If so, note location on
the site plan.
No
6) Does the proposal involve any discharges of waste materials to surface
waters? If so, describe the type of waste and anticipated volume of discharge.
This project will not discharge waste materials into surface waters.
b. Ground:
1) Will ground water be withdrawn, or will water be discharged to ground
water? Give general description,purpose, and approximate quantities if
known.
No
2) Describe waste material that will be discharged into the ground from septic
tanks or other sources, if any (for example:Domestic sewage; industrial,
containing the following chemicals; agricultural; etc). Describe the general
size of the system, the number of such systems, the number of houses to be
served(if applicable), or the number of animals or humans the system(s) are
expected to serve.
This project will not discharge Nv istc material into the ground.
c. Water Runoff (including storm water):
1) Describe the source of runoff(including stormwater) and method of collection
and disposal, if any (include quantities, if known). Where will this water
flow? Will this water flow into other waters? If so, describe.
The unnamed stream is spring water fed. Stormwater will enter the
unnamed streambed from roadside ditches and the steep ravine sides.
This water will flow eastward under US Highway 101 to Hood Canal.
-5 -
2) Could waste materials enter ground or surface waters? If so, generally
describe.
Petroleum products will be on the project site during construction.
However, a spill prevention control and countermeasures plan will be
developed and BMP's will be developed for spill prevention and control
during construction.
d. Proposed measures to reduce or control surface, ground and runoff water
impacts, if any:
All runoff will be treated in accordance with the WSDOT Highway Runoff
Manual and Best Management Practices.
4. PLANTS
a. Underline types of vegetation found on the site:
DECIDUOUS TREE: alder, big leaf maple, aspen, Vine maple, cottonwood,
willow, other:
EVERGREEN TREE: fir, western red cedar, pine, hemlock, other:
SHRUBS: Elderberry, Salmonberry, Scotch Broom, Red Huckleberry, Mahonia,
Salal, Spirea, other: Indian Plum
Grass
Pasture
Crop or grain
WET SOIL PLANTS: cattail,buttercup,bullrush, Skunk cabbage, other:
WATER PLANTS: water lily, eelgrass,milfoil, other:
Other types of vegetation:
b. What kind and amount of vegetation will be removed or altered?
Approximately 5000 square feet of trees, bushes, shrubs, grass and other low
level plants will be removed.
c. List threatened or endangered species known to be on or near the site.
None
d. Proposed landscaping, use of native plants, or other measures to preserve or
enhance vegetation on the site, if any:
At project completion all disturbed areas will be replanted and seeded.
5. ANIMALS
a. Underline any birds and animals which have been observed on or near the site or
are known to be on or near the site:
BIRDS: hawk, heron, eagle, songbirds, other:
MAMMALS: deer, bear, elk,beaver, other:
-6-
FISH: bass, salmon,trout,herring, shellfish, other:
b. List any threatened or endangered species known to be on or near the site.
Puget Sound bull trout, marbled murrelet, northern spotted owl, Chinook
salmon, chum salmon and steelhead. These species are present in Hood
Canal, outside of the project area. The unnamed stream is non-fish bearing.
c. Is the site part of a migration route? If so, explain.
Yes,Western Washington is part of the Pacific Flyway for Migratory
Waterfowl.
d. Proposed measures to preserve or enhance wildlife, if any:
Proper use of Best Management Practices will insure that no pollutants or
sediment will enter fish bearing waters of the state (Hood Canal).
6. ' ENERGY AND NATURAL RESOURCES
a. What kinds of energy (electric, natural gas, oil, wood stove, solar) will be used to
meet the completed project's energy needs? Describe whether it will be used for
heating, manufacturing, etc.
None—Not Applicable
b. Would the project affect the potential use of solar energy by adjacent properties?
If so, generally describe.
No
c. What kinds of energy conservation features are included in the plans of this
proposal? List other proposed measures to reduce or control energy impacts, if
any:
None— Not Applicable
7. ENVIRONMENTAL HEALTH
a. Are there any environmental health hazards, including exposure to toxic
chemicals, risk of fire and explosion, spill, or hazardous waste that would occur
as a result of this proposal? If so, describe:
There exists the risk of spills,fires, etc. associated with traffic accidents.
1) Describe special emergency services that might be required.
Fire, Police, Emergency Medical Service Ambulance
2) Proposed measures to reduce or control environmental health hazards, if any:
-7-
Standard construction safety practices will be in effect during
construction.
b. Noise
1) What types of noise exist in the area which may affect the project(for
example: traffic, equipment, operation, other)?
Traffic noise from US Highway 101 exists in this area, but will not affect
the project.
2) What types and levels of noise would be created by or associated with the
project on a short-term or a long-term basis (for example: traffic,
construction, operation, other)? Indicate what hours noise would come from
the site.
Noise levels may rise slightly during the daylight hours during
construction. Levels should return to normal after completion of the
project.
3) Proposed measures to reduce or control noise impacts, if any:
All work will be done during daytime(10 hour work shifts, 0700 to 1700
hours).
8. LAND AND SHORELINE USE
a. What is the current use of the site and adjacent properties?
Transportation corridor and adjacent properties are used for recreation.
b. Has the site been used for agriculture? If so, describe.
No
c. Describe any structures on the site.
None
d. Will any structures be demolished? If so, what?
No—Not Applicable
e. What is the current zoning classification of the site?
Rural Tourist
f. What is the current comprehensive plan designation of the site?
Shoreline of Statewide Significance for Hood Canal
g. If applicable, what is the current shoreline master program designation of the
site?
-8-
Conservancy
h. Has any part of the site been classified as an "environmentally sensitive"area? If
so, specify.
No
i. Approximately how many people would reside or work in the completed project?
None
j. Approximately how many people would the completed project displace?
None
k. Proposed measures to avoid or reduce displacement impacts, if any:
None—Not Applicable
1. Proposed measures to ensure the proposal is compatible with existing and
projected land uses and plans, if any:
All roadside impacted by project work shall be restored in kind. For
example, replace disturbed native.vegetation with native vegetation.
9. HOUSING
a. Approximately how many units would be provided, if any? Indicate whether high,
middle, or low-income housing.
None—N/A
b. Approximately how many units, if any, would be eliminated? Indicate whether
high, middle, or low-income housing.
None
c. Proposed measures to reduce or control housing impacts, if any:
None—N/A
10. AESTHETICS
a. What is the tallest height of any proposed structure(s), not including antennas;
what is the principal exterior building material(s)proposed?
There are no proposed structures within the project limits.
b. What views in the immediate vicinity would be altered or obstructed?
Approximately 24 trees ranging from 12 inch (diameter breast height) to 36
inch (diameter breast height) will be removed on the east side of US 101 to
provide access for placing rip rap and granular material at the culvert outlet.
-9-
I
c. Proposed measures to reduce or control aesthetic impacts, if any:
All roadside impacted by construction shall be restored in kind. For example,
replace native vegetation with native vegetation.
11. LIGHT AND GLARE
a. What type of light or glare will the proposal produce? What time of day would it
mainly occur?
None
b. Could light or glare from the finished project be a safety hazard or interfere with
views?
No, there is no added permanent lighting planned for this project site.
c. What existing off-site sources of light or glare may affect your proposal?
None—Not Applicable
d. Proposed measures to reduce or control light and glare impacts, if any:
None—Not Applicable.
12. RECREATION
a. What designated and informal recreational opportunities are in the immediate
vicinity?
Fishing, camping,hunting and hiking.
b. Would the.proposed project displace any existing recreational uses? If so,
describe.
No
c. Proposed measures to reduce or control impacts on recreation, including
recreation opportunities to be provided by the project, if any:
None,
13. HISTORIC AND CULTURAL PRESERVATION
a. Are there any places or objects listed on, or proposed for, national, state, or local
preservation registers known to be on or next to the site? If so, generally
describe.
Buildings (eligible for the National Register of Historic Places) associated
with the Robbinswold Girl Scout Camp.are located to the east of the project
limits.
b. Generally describe any landmarks or evidence of historic, archaeological,
scientific, or cultural importance known to be on or next to the site.
- 10-
Buildings (eligible for the National Register of Historic Places) associated
with the Robbinswold Girl Scout Camp are located to the east of the project
limits.As the current project involves in-kind replacement of a failing
culvert,none of these buildings will be affected by the project, directly or
indirectly. Reference: Historic context statement of Mason County, and
reconnaissance-level survey of historic buildings along US Highway 101
corridor through Mason County completed in 2009 (Andrews 2009) Also
reference Cultural Resources Program Short Report No. 11-03 by Roger
Kiers (Jan. 21, 2011).
c. Proposed measures to reduce or control impacts, if any:
None
14. TRANSPORTATION
a. Identify public streets and highways serving the site, and describe proposed
access to the existingstreet system. Show on site plans, i an :
Y P .f Y
US Highway 101 travels through the project site.There is no existing street
system to access.
b. Is site currently served by public transit? If not, what is the approximate distance
to the nearest transit stop?
No,Nearest Mason County Transit stops are approximately 2.5 miles (Twin
Totems to the south and Hoodsport to the north).
c. How many parking spaces would the completed project have? How many would
the project eliminate?
None
d. Will the proposal require any new roads or streets, or improvements to existing
roads or streets, not including driveways? If so, generally describe (indicate
whether public or private).
No
e. Will the project use (or occur in the immediate vicinity oJ) water, rail, or air
transportation? If so, generally describe.
No
f. How many vehicular trips per day would be generated by the completed project.
If known, indicate when peak volumes would occur.
None
g. Proposed measures to reduce or control transportation impacts, if any:
- 11 -
Two way traffic will be maintained throughout construction. One-way
flagger controlled traffic with minor delays will occur periodically to
reposition equipment or materials.
15. PUBLIC SERVICE
a. Would the project result in an increased need for public services (for example:
fire protection,police protection, health care, schools, other)? If so, generally
describe.
No
b. Proposed measures to reduce or control direct impacts on public services, if any.
One-way flagger controlled traffic with minor delays. Emergency responders
will always be given priority.
16. UTILITIES
a. Underline the utilities currently available at the site: electricity, water, natural
gas, refuse service, telephone, sanitary sewer, septic system, other.
Power, telephone and fiber optic lines are aerial within the project limits.
b. Describe the utilities that are proposed for the project, the utility providing the
service, and the general construction activities on the site or in the immediate
vicinity which might be needed.
No utilities will be required to be re-located during the construction of this
project.
C. SIGNATURE
The above answers are true and complete to the best of my knowledge.
Signature:
Jeffegawyer
Olympic Region Environmental Manager