HomeMy WebLinkAboutCOM2005-00073 Retaining Wall - COM Permit / Conditions - 11/16/2005 MASON COUNTY DEPT. OF COMMUNITY DEVELOPMENT Inspection Line( 60)427-7262
IrfMason County Bldg. 3 426 W. Cedar P.O. Box 186 Phone: (360)427 670,ext. 352
Shelton, WA 98584
lo COMMERCIAL BUILDING PERMIT COM2005-0 073
OWNER: JOHN STRAATMAN RECEIVED: /21/2005
CONTRACTOR: ASHBY HOMES LICENSE: ASHBYH1036RW EXP: 4/10/2006 ISSUED: 1/16/200E
SITE ADDRESS: 28611 N U S HIGHWAY 101 LILLIWAUP EXPIRES: /16/2006
PARCEL NUMBER: 323305156013
LEGAL DESCRIPTION: LILLIWAUP BLK: 56 & LOT:13-18&T.L.& 1/2 VAC CABLE BLK: 26 LOT: 4 & WILY 1/2 VAC CABLE
PROJECT DESCRIPTION: DIRECTIONS TO SITE:
Retaining Wall 101 North to Lilliwaup, site is on left before Lilliwaup Motel and Store.
I
General Information Construction &Occupancy Information
No.of Units: Type of Constr.: Retaining Wall
Type of Use: Insp.Area: No.of Bathrooms: Occ. Group: U
Type of Work: ACC Fire Dist.: 17 No. of Stories: Occ. Load:
Valuation: $ 15,000.00
Building Height:
Pre-Manufactured Unit Information Square Footage Information
Make: Length: Lot Size: Retaining wall: 240
Model: Width: Building:
Year: Serial No.: Basement: Parking Spaces:
Setback Information
Shoreline&Planning Information
Front: Ft. Shoreline: Ft.
Rear: Ft. Slope: Ft. Water Body:Hood Canal Shoreline Desig.: Urban
Side 1: Ft. SEPA?:Yes Comp.Plan Desig.: Rural
Side 2: Ft.
Fire Protection System Information
Auto Fire Alarm System?: Emergency Key Box?: Standpipe?:
Auto Fire Sprinkler System?: Access Road?: Fire Extinguishers?:
Fixed Fire Suppression System?: Fire Hydrants?: Fire Lanes?:
COM2005-00073 Please refer to the following pages for conditions of this permit. 1 of 4
7) All building permits shall have a final inspection performed and approved by the Mason County Building Department prior to permit expiration The
failure to request a final inspection or to obtain approval will be documented in the legal property records on file with Mason County as being
non-compliant with Mason County ordinances and building regulations.
X
8) Water quality is not to be degraded to the detriment of the aquatic environment as a result of this project.
X
9) Prior to final approval, all upland areas disturbed or newly created by construction activities shall be seeded, vegetated or given an equivaleni type
of erosion protection (silt fencing or straw matting). X
10) The proposed project must be consistent with all applicable policies and other provisions of the Shoreline Management Act, its rules, and the
Mason County Shoreline Master Program.X
11) �:�emporary erosion control measures must be implemented to prevent water quality degradation of adjacent waters or wetlands. Silt fencing nust
be installed and maintained until upland vegetation has become established. X
12) pproved per dimensions and setbacks on submitted site plan. Setbacks are measured from the furthest projection of the structure.
X
13) All other necessary permits from Mason County, Washington State and/or Federal Agencies that are required for this proposed development and
construction must be obtained PRIOR TO SAME DEVELOPMENT AND CONSTRUCTION. X
14 The approval of this project is subject to the recommendations and specifications outlined in the attached geotechnical report or assessment.
Structures and /or land modifications (grading, cuts, fills, etc.) required in the geotechnical report/assessment, may require a seperate perrr it.
The geotechincal report/assessment shall remain attached to the approved building plans. X
15 roject work shall be consistent with conditions of Mason Environmental Permit No. MEP2004-00088. X
This permit becomes null and void if work or construction authorized is not commenced within 180 days,or if construction or work is suspended for a period of 180 days at any time after work is
commenced. Evidence of continuation of work is a progress inspection within the 180 day period. Final inspection must be approved before building can be occupied. Proof of c ntinuation of
work is by means of a progress inspection.The owneror the agent on the owners behalf,represents that the information provided is accurate and grants employees of Mason County access to
the above described property d structureJor r view and inspe ion. /
OWNER OR AGENT: \ DATE:
COM2005-00073 3 o 4
Plumbing Fixtures Mechanical Fixtures FEES
Type Qty. Type Qty. Type By Date Amount Receipt
Building Permit Fee KKK R/9119no �Q 1n A99onrnn
Plan Check Fee KKK aolignnr, C�,1Rl'A1 99nnrnn
Building State Fee NAR(: r;i99ignn,, �a Fn ??nnFnn
Building Permit Fee NARr" F19919nnF 09d9 1F . o9nnFnn
Total $419.06
CASE NOTES FOR
COM2005-00073
CONDITIONS FOR
COM2005-00073
1)� NOTE: Inspection is required during costruction of the retaining wall. Call Mason County Community Development for an inspection.
f
X
2) ; ` The approved site plan is required to be on-site for inspection purposes. If inspection is called for and the site plan is not on site, Approval W LL
NOT be granted. In addition, a reinspection fee, based on the current fee schedule, minimum one-hour will be charged and collected by the Mason
County Building Department prior to any further inspections being performed or approvals granted.
X
3 Any changes in construction shall be reviewed by engineer of record and submitted in writing to the Mason County Building Department prior o
construction. All engineering documents are a part of the approved set of plans and must remain attached thereto. If engineering documentS are
removed, approval will not be granted. In addition, a reinspection fee, based on the current fee schedule, minimum one-hour will be charged and
collected by the Mason County Building Department prior to any further inspections being performed or approvals granted.
X
4) Changes to approved building plans that affect compliance to the current Washington State Energy Code (WSEC), ventilation and Indoor Air
Quality Code (VIAQ), Building/Plumbing/Mechanical Codes and/or Mason County Regulations shall be approved prior to construction.
X
5) ONSTRUCTION PROCESS TO BE FIELD CORRECTED AS REQUIRED PER MASON COUNTY BUILDING DEPARTMENT AND THE
ADOPTED BUILDING CODE.
The construction of the permitted project is subject to inspections by the Mason County Building Department. All construction must be in
conformance with the international codes as amended and adopted by Mason County. Any corrections, changes or alterations required by a
Mason County Building Inspector shall be made prior to requesting additional inspectio s.
X
6) All property lines shall be clearly identified at the time of foundation inspection. X
i
COM2005-00073 2 o 4
a
• 1
t
MARLEY L. YOUNG, CONSULTING ENGINEER
P.O. BOX 1343, SHELTON, WA 98584-0959
r Civil Engineering (360)426-7475- (360)490-0939 - Fax (360)426-5789
Stormwater Site Plans Marley L. Young, P.E., P.L.S.
Sewer Extensions Civil Engineer& Land Surveyor
O
ram--
o IIII II I_
LILLIWAUP
Post Office
5-08-05
CIVIL ENGINEER'S DESIGN OF A GRAVITY ROCK WALL - 3 FEET HEIGHT
ONE TO THREE MAN ROCK - 3 FEET HIGH
The soil material on site is assumed to be loose till, and will be used as backfill
behind the wall, plus chinking rock for drainrock.
One Cross Section used for design
Proposed- 3' Tall Retaining wall — of large rock (2,and 3 man rock at the base)
The proposed rock retaining wall is being reviewed for sliding resistance,
overturning resistance, and bearing capacity
The finished slope of the fill behind the wall
is expected to be 2' horizontal to 1'vertical.
Therefore the slope of the surface equals=2:1
Soil Type A = Surface slope 26.4
Cos = 0.895712
Sin 0 = 0.444635
t ft = Wall depth at top 1
d ft = Wall depth at base 1
H ft = Wall height 3
Batter ft = front face degrees 18,43495
sp gr 3 Man Rock Void Ratio Batter front face tangent 0.333333
62.2 186.6 0.7 Yw = Wall Density pcf = 130.62
Ys = Soil Density pcf = 130
Ystwet = Wet Soil Density pcf 130
0 = Angle of Intemal Friction 32
Cos = 0.348048
Sin 0.529919
Ow= Factored friction Angle .40o 12.8
Qs= 4000
i= Slope above wall 26.4
Surcharge None
B= Wall angle at back side 71.56505
Tan(90-B) 0.333333
J
r
SLIDING RESISTANCE Page 2 of 3
KA = Active pressure coefficient
Z
csc(B) *Sin (B - �)
KA =
[Sin (B+pfw) .5 + (Sin (¢+ Ow) Sin (�- i) A.5)
C
Sin (B +
0.671408 Z-
0.997581 + 0.263496
KA = 0.283459
FA = Active force on wall = .5 (Ys) * (KA) * H A 2 = 165.8236
W = Total weight of Wall =(Yw*H*t)+(((Yw*H*(d-t))/2) = 391.86
Wr= Weight of rock wall 'triangle' = (Yw*H*(d/2) 195.93
Wt = Weight of rock wall 'triangle' = (Yw*H*(t/2) 195.93
Fv = Vertical force on wall from retained soils
= FA* (Sin(ow) = 36.73797
Fh = Horizontal forces on wall from retained soil
= FA (Cosin(ow) = ) 161.7028
Fr= Force resisting sliding = (W+ Fv) Tano = 267.8177
Safety factor against sliding: SFS = Fr/Fh 1.656235 > 1.5 OK
Note: safety factor is greater than 1.5 - Design is O.K.
---------------------------------------------------------------------
---------------------------------------------------------------------
OVERTURNING RESISTANCE
Mo = Overturning Moment= Fh(.33)H 161.6866
Mr= Moment resisting overturning =
Wr* Moment arm. Wr*2/3b 130.62
Wt*Moment arm. Wt * (b + (1/3t)) 261.24
Fv * Moment arm. Fv * ((b+(H/3)*Tan90-B) 48.98395
Mr= 440.844
Safety factor against overturning: SFO = Mr/Mo = 2.726534 >2.0 OK
Note: safety factor is greater than 2 Design O.K.
---------------------------------------------------------------------
---------------------------------------------------------------------
BEARING CAPACITY
Qw= Pressure exerted on soil below base block= (W+Fv)/d = 428.598
as = 4000
Safety factor against bearing failure FSB = Qs/Qw= 9.332755 >2.0 OK
Note: safety factor is greater than 2 Design O.K.
---------------------------------------------------------------------
---------------------------------------------------------------------
Page 3 of 3
ANALYSIS:
Our Analysis is based on a review of the internal and external stability of the wall and
DOES NOT INCLUDE either global or seismic analysis
CONTRACTOR RESPONSIBILITY:
The contractor is expected to use due care in properly setting and installing the rocks.
Also the contractor is expected to properly install drainage rock and drainage pipes
according to acceptable standards.
CHANGED CONDITIONS:
The conclusions and recommendations in these engineering calculations are based on
the interpretation of information received from the client. In the event that the scope of
the project, surface/subsurface or contractal conditions differ from those relied on in these
calculations, the civil engineer and the soils engineer should be advised immediately.
A review of the changed conditions will be conducted and alternative or remedial
recomendations given at that time.
ENGINEER'S CERTIFICATE:
With the assurance that the above recommendations are adhered to, the 3'wall is stable,
no further analysis required. This wall configuration is stable and well within safety factors
if the rock wall is three feet high or less.
I hereby certify that the engineering shown in this
document was performed by me or under my direction.
Marley L. Young, P.E., P.L.S.,
Consulting Civil Engineer
��PPo F P.O. Box 1343
Shelton, WA 98584
r 360 426-7475
�® 14144 444 Project No. 2005-22
DIAL h file: Retanwal.wbl; tab AK; A440-J577
Quattro Pro
EXPIRES 3/5 6/ G
J
MARLEY L. YOUNG, CONSULTING ENGINEER
P.O. BOX 1343, SHELTON, WA 98584-0959
';Civil Engineering (360) 426-7475 - (360) 490-0939 - Fax (360) 426-5789
Stormnrater Site Plans Marley L. Young, P.E., P.L.S.
Sewer Extensions Civil Engineer& Land Surveyor
o I II III
LILLIWAUP
Post Office
5-08-05
CIVIL ENGINEER'S DESIGN OF A GRAVITY ROCK WALL - 6 FT. HIGH
ONE TO THREE MAN ROCK - 6 FEET HIGH
The soil material on site is assumed to be loose till, and will be used as backfill
behind the wall, plus chinking rock for drainrock.
One Cross Section used for design
Proposed - 6' Tall Retaining wall -- of large rock (2,and 3 man rock at the base)
The proposed rock retaining wall is being reviewed for sliding resistance,
overtuming resistance, and bearing capacity
The finished slope of the fill behind the wall
is expected to be 2' horizontal to V vertical.
Therefore the slope of the surface equals =2:1
Soil Type A = Surface slope 26.4
Cos(ii = 0.895712
Sin 0 = 0.444635
t ft = Wall depth at top 1.87
d ft = Wall depth at base 1.87
H ft = Wall height 6
Batter ft = front face degrees 17.31052
sp gr 3 Man Rock void Ratio Batter front face tangent 0.311667
62.2 186.6 0.7 Yw = Wall Density pcf = 130.62
Ys = Soil Density pcf = 130
Ys/wet = Wet Soil Density pcf 130
4= Angle of Internal Friction 32
Cos 0 = 0,848048
Sin 4 0.529919
ow= Factored friction Angle .40o 12.8
Qs= 4000
i = Slope above wall 26.4
Surcharge None
B = Wall angle at back side 72.68948
Tan(90-B) 0.311667
---------------------------------------------------------------------
---------------------------------------------------------------------
SLIMING RESISTANCE Page 2 of 3
KA= Active pressure coefficient
2
csc(B) *Sin (B- �)
KA =
(Sin (B + w .5 + (Sin (g + ow) Sin (0-)A.5
Sin (B + i)
Z
0.68289
[-0998-45 + 0.263884
KA = 0.292653
FA = Active force on wall = .5 (Ys) * (KA) *H A 2 = 684.8077
W = Total weight of Wall =(Yw*H*t)+(((Yw*H*(d-t))/2) = 1465.56
Wr= Weight of rock wall 'triangle' _ (Yw*H*(d/2) 732.7782
Wt= Weight of rock wall 'triangle' _ (Yw*H*(t/2) 732.7782
Fv = Vertical force on wall from retained soils
= FA*(Sin(ow) = 151.7181
Fh = Horizontal forces on wall from retained soil
= FA(Cosin(ow) _) 667.7898
Fr= Force resisting sliding = (W+ Fv) Tano = 1010.585
Safety factor against sliding: SFS = Fr/Fh 1.513328 > 1.5 OK
Note: safety factor is greater than 1.5 - Design is O.K.
OVERTURNING RESISTANCE
Mo= Overturning Moment= Fh(.33)H 1335.446
Mr= Moment resisting overturning =
Wr*Moment arm. Wr*2/3b 913.5302
Wt* Moment arm. Wt* (b+ (1/3t)) 1827.06
Fv * Moment arm. Fv *((b+(H/3)*Tan90-B) 378.2839
Mr= 3118.874
Safety factor against overturning: SFO = Mr/Mo = 2.335455 >2.0 OK
Note: safety factor is greater than 2 Design O.K.
---------------------------------------------------------------------
---------------------------------------------------------------------
BEARING CAPACITY
Qw= Pressure exerted on soil below base block= (W+Fv)/d = 864.8527
Qs = 4000
Safety factor against bearing failure FSB= Qs/Qw= 4.625065 >2.0 OK
Note: safety factor is greater than 2 Design O.K.
---------------------------------------------------------------------
---------------------------------------------------------------------
Page 3 of 3
ANALYSIS:
Our Analysis is based on a review of the internal and external stability of the wall and
DOES NOT INCLUDE either global or seismic analysis
CONTRACTOR RESPONSIBILITY:
The contractor is expected to use due care in properly setting and installing the rocks.
Also the contractor is expected to properly install drainage rock and drainage pipes
according to acceptable standards.
CHANGED CONDITIONS:
The conclusions and recommendations in these engineering calculations are based on
the interpretation of information received from the client. In the event that the scope of
the project, surface/subsurface or contractal conditions differ from those relied on in these
calculations, the civil engineer and the soils engineer should be advised immediately.
A review of the changed conditions will be conducted and alternative or remedial
recomendations given at that time.
ENGINEER'S CERTIFICATE:
With the assurance that the above recommendations are adhered to, the 6'wall is stable,
no further analysis required. This wall configuration is stable and well within safety factors
if the rock wall is six feet high or less.
I hereby certify that the engineering shown in this
document was performed by me or under my direction.
Marley L. Young, P.E., P.L.S.,
Consulting Civil Engineer
Y L. P.O. Box 1343
Shelton, WA 98584
360 426-7475
14144 Project No. 2005-22
ISTE
NpLeE v ^ file: Retanwal.wbl; tab AK; A300-J437
Quattro Pro
t fXPin S 315J04
MARLEY L. YOUNG, CONSULTING ENGINEER
P.O. BOX 1343, SHELTON, WA 98584-0959
Civil Engineering (360) 426-7475 - (360) 490-0939 - Fax (360) 426-5789
Marley L. Young, P.E., P.L.S.
Stormurater Site Plans y g+
Sewer Extensions Civil Engineer & Land Surveyor
O
o (II
LILLIWAUP
Post Office
5-08-05
CIVIL ENGINEER'S DESIGN OF A GRAVITY ROCK WALL - 9 FT. HIGH
ONE TO THREE MAN ROCK - 9 FEET HIGH
The soil material on site is assumed to be loose till, and will be used as backfill
behind the wall, plus chinking rock for drainrock.
One Cross Section used for design
Proposed - 9' Tall Retaining wall -- of large rock (2,and 3 man rock at the base)
The proposed rock retaining wall is being reviewed for sliding resistance,
overturning resistance, and bearing capacity
The finished slope of the fill behind the wall
is expected to be 2' horizontal to 1'vertical.
Therefore the slope of the surface equals =2:1
Soil Type A 0 = Surface slope 26.4
Cos 0 = 0.895712
Sin 0 = 0.444635
t ft = Wall depth at top 2.81
d ft = Wall depth at base 2.81
H ft = Wall height 9
Batter ft = front face degrees 17.33952
sp gr 3 Man Rock Void Ratio Batter front face tangent 0.312222
62.2 186.6 0.7 Yw = Wall Density pcf = 130.62
Ys = Soil Density pcf = 130
Ys/wet = Wet Soil Density pcf 130
0 = Angle of Internal Friction 32
Cos¢ = 0.848048
Sin ¢ 0.529919
Ow= Factored friction Angle .40o 12.8
Qs= 4000
i = Slope above wall 26.4
Surcharge None
B= Wall angle at back side 72.66048
Tan(90-13) 0.312222
---------------------------------------------------------------------
---------------------------------------------------------------------
SLIDING RESISTANCE Page 2 of 3
KA=Active pressure coefficient
z
csc(B) *Sin (B - �)
KA =
Sin (B + 0w)`.5� + (Sin (p + ¢w) Sin
// Sin (B + i)
0.682596 Z
(0
KA = 0.292415
FA = Active force on wall = .5 (Ys) * (KA) * H^2 = 1539.564
W = Total weight of Wall =(Yw*H*t)+(((Yw*H*(d-t))/2) = 3303.38
Wr= Weight of rock wall 'triangle' _ (Yw*H*(d/2) 1651.69
Wt= Weight of rock wall 'triangle' _ (Yw*H*(t/2) 1651.69
Fv = Vertical force on wall from retained soils
= FA* (Sin(ow) = 341.0881
Fh = Horizontal forces on wall from retained soil
= FA(Cosin(ow) _ ) 1501.305
Fr= Force resisting sliding = (W+ Fv) Tano = 2277.316
Safety factor against sliding: SFS = Fr/Fh 1.516891 > 1.5 OK
Note: safety factor is greater than 1.5 - Design is O.K.
OVERTURNING RESISTANCE
Mo = Overturning Moment= Fh(.33)H 4503.464
Mr= Moment resisting overturning =
Wr*Moment arm. Wr*2/3b 3094.166
Wt* Moment arm. Wt* (b+ (1/3t)) 6188.331
Fv *Moment arm. Fv * ((b+(H/3)*Tan90-B) 1277.943
-------------------
Mr= 10560.44
Safety factor against overturning: SFO = Mr/Mo= 2.344959 >2.0 OK
Note: safety factor is greater than 2 Design O.K.
BEARING CAPACITY
Qw= Pressure exerted on soil below base block= (W+Fv)/d = 1296.964
Qs= 4000
Safety factor against bearing failure FSB= Qs/Qw= 3.084126 >2.0 OK
Note: safety factor is greater than 2 Design O.K.
Page 3 of 3
ANALYSIS:
Our Analysis is based on a review of the internal and external stability of the wall and
DOES NOT INCLUDE either global or seismic analysis
CONTRACTOR RESPONSIBILITY:
The contractor is expected to use due care in properly setting and installing the rocks.
Also the contractor is expected to properly install drainage rock and drainage pipes
according to acceptable standards.
CHANGED CONDITIONS:
The conclusions and recommendations in these engineering calculations are based on
the interpretation of information received from the client. In the event that the scope of
the project, surface/subsurface or contractal conditions differ from those relied on in these
calculations, the civil engineer and the soils engineer should be advised immediately.
A review of the changed conditions will be conducted and alternative or remedial
recomendations given at that time.
ENGINEER'S CERTIFICATE.
With the assurance that the above recommendations are adhered to, the 9'wall is stable,
no further analysis required. This wall configuration is stable and well within safety factors
if the rock wall is nine feet high or less.
I hereby certify that the engineering shown in this
document was performed by me or under my direction.
Marley L. Young, P.E., P.L.S.,
Consulting Civil Engineer
P.O. Box 1343
Shelton, WA 98584
360 426-7475
� o�
®,"F��PF IST Project No. 2005-22
NAL F �uh, file: Retanwal.wbl; tab AK; Al50-J290
Quattro Pro
DCPiRcS "s/5/0(p
MARLEY L. YOUNG, CONSULTING ENGINEER
P.O. BOX 1343, SHELTON, WA 98584-0959
Civil Engineering (360) 426-7475 - (360)490-0939 - Fax (360) 426-5789
Stornvmter Site Plans Marley L. Young, P.E., P.L.S.
Sewer Extensions Civil Engineer & Land Surveyor
O
o
LILLIWAUP
Post Office
5-08-05
CIVIL ENGINEER'S DESIGN OF A GRAVITY ROCK WALL- 12 FEET HIGH
ONE TO THREE MAN ROCK - 12 FEET HIGH
The soil material on site is assumed to be loose till, and will be used as backfill
behind the wall, plus chinking rock for drainrock.
One Cross Section used for design
Proposed - 12'Tall Retaining wall -- of large rock(2,and 3 man rock at the base)
The proposed rock retaining wall is being reviewed for sliding resistance,
overturning resistance, and bearing capacity
The finished slope of the fill behind the wall
is expected to be 2' horizontal to 1'vertical.
Therefore the slope of the surface equals =2:1
Soil Type A fil = Surface slope 26.4
Cos = 0.895712
Sin 0.444635
t ft = Wall depth at top 3.75
d ft = Wall depth at base 3.75
H ft = Wall height 12
Batter ft = front face degrees 17.35402
sp gr 3 Man Rock void Ratio Batter front face tangent 0.3125
62.2 186.6 0.7 Yw = Wall Density pcf = 130.62
Ys = Soil Density pcf = 130
Ys/wet = Wet Soil Density pcf 130
= Angle of Internal Friction 32
Cos = 0.848048
Sin {l 0.529919
Ow= Factored friction Angle .40o 12.8
Qs = 4000
i = Slope above wall 26.4
Surcharge None
B = Wall angle at back side 72.64598
Tan(90-13) 0.3125
---------------------------------------------------------------------
---------------------------------------------------------------------
I
SLIDING RESISTANCE Page 2 of 3
KA= Active pressure coefficient
csc(B) *Sin (B- o)
KA =
Sin (B + ow)^.5 + (Sin (o + ow) Sin (o - i) A.5)
Sin (B + i)
0.671408
0.997581 + 0.263496
KA = 0.283459
FA = Active force on wall = .5 (Ys) *(KA) * HA2 = 165.8236
W = Total weight of Wall =(Yw*H*t)+(((Yw*H*(d-t))/2) = 391.86
Wr= Weight of rock wall 'triangle' = (Yw*H*(d/2) 195.93
Wt= Weight of rock wall 'triangle' = (Yw*H*(t/2) 195.93
Fv = Vertical force on wall from retained soils
= FA*(Sin(ow) = 36.73797
Fh = Horizontal forces on wall from retained soil
= FA (Cosin(ow) = ) 161.7028
Fr= Force resisting sliding = (W+ Fv) Tano = 267.8177
Safety factor against sliding: SFS = Fr/Fh 1.656235 > 1.5 OK
Note: safety factor is greater than 1.5- Design is O.K.
OVERTURNING RESISTANCE
Mo = Overturning Moment= Fh(.33)H 161.6866
Mr= Moment resisting overturning =
Wr*Moment arm. Wr*2/3b 130.62
Wt* Moment arm. Wt* (b+ (1/3t)) 261.24
Fv *Moment arm. Fv *((b+(H/3)*Tan90-B) 48.98395
-------------------
Mr= 440.844
Safety factor against overturning: SFO = Mr/Mo = 2.726534 >2.0 OK
Note: safety factor is greater than 2 Design O.K.
---------------------------------------------------------------------
---------------------------------------------------------------------
BEARING CAPACITY
Qw= Pressure exerted on soil below base block= (W+Fv)/d = 428.598
Qs= 4000
Safety factor against bearing failure FSB = Qs/Qw= 9.332755 >2.0 OK
Note: safety factor is greater than 2 Design O.K.
Page 3 of 3
ANALYSIS:
Our Analysis is based on a review of the internal and external stability of the wall and
DOES NOT INCLUDE either global or seismic analysis
CONTRACTOR RESPONSIBILITY.
The contractor is expected to use due care in properly setting and installing the rocks.
Also the contractor is expected to properly install drainage rock and drainage pipes
according to acceptable standards.
CHANGED CONDITIONS:
The conclusions and recommendations in these engineering calculations are based on
the interpretation of information received from the client. In the event that the scope of
the project, surface/subsurface or contractal conditions differ from those relied on in these
calculations, the civil engineer and the soils engineer should be advised immediately.
A review of the changed conditions will be conducted and alternative or remedial
recomendations given at that time.
ENGINEER'S CERTIFICATE:
With the assurance that the above recommendations are adhered to, the 12'wall is stable,
no further analysis required. This wall configuration is stable and well within safety factors
if the rock wall is less than 12 feet high or less.
I hereby certify that the engineering shown in this
document was performed by me or under my direction.
Marley L. Young, P.E., P.L.S.,
Consulting Civil Engineer
P.O. Box 1343
��oF wA ti Shelton, WA 98584
e 360 426-7475
rt p�ors e k9 �►�'�a�� Project No. 2005-22
N -L G�� file: Retanwal.wbl; tab AK; A1-J144
Quattro Pro
C?incS 3/5/0lo
I
WCLLLP MASON COUNTY PERMIT NO. QW DLW 4�
` BUILDING PERMIT APPLICATION
426 W. Cedar• P.O. Box 186, Shelton, WA 98584 Ur�
CU,�"u" �'� 1-11 Shelton (360) 427-9670 • Belfair (360) 275-4467 • Elma (360) 482-5269
!' r On the web www.co.mason.wa.us
APPLICANT INFO�MATI N CONTRACTOR INFORMATION
Owner 'j -1 ' Cy-ryj I r) Company Name
Mailing Address P. 0. C Mailing Address
City!--�� 11-W State W A6 Zip Code '78SSS City State Zip Code
Phone 220• -71- =199 Other Ph. Phone Other Ph.
Lien/Title Holder Contractor Reg. # Exp.
E mail address E Mail Address
Drivers Lic.# DOB Drivers Lic.# DOB
SEPTIC /WATER SYSTEM INFORMATION - Connect to New Septic Existing Septic
Connect to Water System Name of Water System
Well Sewer System Name of Sewer System
PARCEL INFORMATION - 12 Digit Parcel No. - Fire District 20
Legal Description ... 1�
Site Address (Please include street name, street number and city) '9 i I Oi L; 1 1; U�
Directions t0 site _i k. i=' t_">, i":': L.� !.�'z_��► `ii�� I I e h i�� YC 111 iWr �a i}" , i
Will timber be cut and sold in parcel preparation?Yes kNo
Is property within 200'of Saltwater Lake River/Creek Pond
Wetland Seasonal Runoff Stream Slopes or Bluffer 15%
Is this permit submittal the result of a Stop Work Notice,Correction Notice or other enforcement action?Yes/No.
TYPE OF JOB - New "Add—Alt Repair Other PRIMARY RESIDENCE ❑ SEASONAL ❑
Use of Building Describe WorkNo. of Bedrooms No. of Bathrooms Square Footage- 1st Floor 2nd Floor
3rd Floor Basement Deck Covered Deck Other L-k- t Ltt Sq. ft.
Garage Attached Detached Carport Attached Detached
MANUFACTURED HOME INFORMATION - Make Model Year
Length Width Serial No. No. of Bedrooms No. of Bathrooms
Type of Heat Purchase Price$ Replacement Unit? Yes/ No
Installer Name Certification No.
OWNER/BUILDER Acknowledges submission of inaccurate information may result in a stop work order or permit revocation.
Acknowledgement of such is by signature below. I declare that I am the owner,owners legal representative, or the contractor. I further declare
that I am entitled to receive this permit and to do the work as proposed in the application. I declare that I have obtained the permission from all
the necessary parties. If permission is required from any easement holder or any other party in interest regarding this application or the work
proposed in the application, I have obtained permission from them to apply for this permit and conduct the work proposed. The owner or
agent on owners behalf, represents that the information provided is accurate and grants employees of Mason County access to the above
described property and structure for review and inspection. This permit/application becomes null & void if work or authorized construction is
not commenced within 180 days or if construction work is suspended for a period of 180 days. PROOF OF CONTINUATION OF WORK IS BY
MEANS OFAPROGRESS INSPECTION.INACTIVITY OF THIS PERMIT APPLICATION OF 180 DAYS WILL INVALIDATE THE APPLICATION.
X e�-�t 11'e" Date: �117 J0�
Owner 10w6ers p'resentative Contractor (indicate which one)
FOR OFFICIAL USE BEYOND THIS POINT Accepted by: Date
DEPARTMENTAL REVIEW A VE ENIED NOTES
Building Department
Planning Department
Environmental Health Department
Fire Marshal
FEES
Building Permit Fee Site Ins ection
Plan Review Fee EH Review Fee
Plumbing & Base Fee Planninq Review Fee
Mechanical & Base fee Other
Wood/Gas/ Pellet Stove Fee State Fee
Viol 'on Fee Pre-Paid at Submittal
Valuation $ TOTAL FEES