HomeMy WebLinkAboutHPA-Expedited Bridge Removal - PLN General - 5/14/2008 l
a11 Washington HYDRAULIC PROJECT APPROVAL Coastal
IJU Department of 48 Devonshire Road
IFFISH and RCW 77.55.021(10)&(11)-Appeal Pursuant to Chapter Montesano,WA 98563
WILDLIFE (360)249-4628
Issue Date: May 14,2008 Control Number: 112510-1
Project Expiration Date:June 15,2008 FPA/Public Notice#: N/A
PERMITTEE AUTHORIZED AGENT OR CONTRACTOR
Neyhart Farms
ATTENTION: Douglas Neyhart
2297 Tahuya River Road
Tahuya,WA 98588
Fax:206-623-5110
Project Name: Expedited Neyhart Bridge Removal and Installation
Project Description: Replace bridge that was washed away in the December 2007 flood with a 89
foot full span bridge. The failed ecology blocks, left and right bank cement
abutments and old bridge shall be removed from the river. To remove the
old right bank cement wall, the wall may be cut no greater than 18 inches
above the spread footing. Both cement abutments and the bridge shall be
placed landward of the right bank out of the flood way. Any bank or bridge
protection work shall applied for and receive a separate Hydraulic Project
Approval.
PROVISIONS
1. TIMING LIMITATIONS: The project may begin May 14, 2008 and shall be completed by June
15, 2008.
2. Work shall be accomplished per plans and specifications submitted to the Washington
Department of Fish and Wildlife (WDFW) as well as two emails from Doug Neyhart to WDFW dated
April 9, 2008, except as modified by this Hydraulic Project Approval. A copy of these plans shall be
available on site during construction. No bank or bridge protection work is authorized under this
Hydraulic Project Approval. Any bank or bridge protection work shall be applied for and receive a
separate Hydraulic Project Approval.
EQUIPMENT
3. Equipment used for this project shall operate stationed on the bank.
4. Equipment used for this project shall be free of external petroleum-based products while working
around the stream. Equipment shall be checked daily for leaks and any necessary repairs shall be
completed prior to commencing work activities along the stream.
5. Equipment crossings of the stream are not authorized by this HPA.
REMOVAL OF ABUTMENTS, ECOLOGY BLOCKS AND OLD BRIDGE
6. Removal of the existing structures shall be accomplished so the structure and associated
material does not enter the stream. The failed ecology blocks, left and right bank cement
Page 1 of 5
V. Washington HYDRAULIC PROJECT APPROVAL Coastal
Department of 48 Devonshire Road
FISH and RCW 77.55.021(10)&(11)-Appeal Pursuant to Chapter Montesano,WA 98563
WILDLIFE (360)249-4628
Issue Date: May 14,2008 Control Number: 112510-1
Project Expiration Date:June 15,2008 FPA/Public Notice#: N/A
abutments and old bridge shall be removed from the river. The old right bank cement wall shall be
cut as low as possible and not to exceed greater than 18 inches above the spread footing. Both
cement abutments and the bridge shall be placed landward of the right bank out of the flood way.
7. The bridge deck shall be cleaned of aggregate or earth materials prior to bridge removal. This
material shall be disposed of so it will not enter the stream.
8. The abutments, ecology blocks and old bridge shall be fully suspended so no portion can
damage the streambed and banks.
9. Removal shall be accomplished by mechanical means. This Hydraulic Project Approval does
not authorize blasting.
BRIDGE INSTALLATION
10. The bridge structure shall be fully suspended to minimize damage to the streambed and banks.
11. The bridge shall be constructed to pass the 100-year peak flow with consideration of debris
likely to be encountered.
12. Abutments, piers, piling, sills, approach fills, etc., shall not constrict the flow and cause any
appreciable increase (not to exceed 0.2 feet) in backwater elevation (calculated at the 100-year
flood) or channel-wide scour, and shall be aligned to cause the least effect on the hydraulics of the
stream.
13. Approach material shall be structurally stable and shall be composed of material that if eroded
into the water shall not be detrimental to fish life.
WATER QUALITY
14. Wooden components shall not contain creosote or pentachlorophenol. This shall include
pilings, beams, structural supports, and decking.These components shall remain free of these toxic
substances for the duration of their functional lives.
15. If at any time, as a result of project activities, fish are observed in distress, a fish kill occurs, or
water quality problems develop (including equipment leaks or spills), immediate notification shall be
made to the Washington Military Department's Emergency Management Division at 1-800-258-
5990, and to the Area Habitat Biologist listed below.
16. Erosion control methods shall be used to prevent silt-laden water from entering the stream.
These may include, but are not limited to, straw bales, filter fabric, temporary sediment ponds,
check dams of pea gravel-filled burlap bags or other material, and/or immediate mulching of
exposed areas.
Page 2 of 5
Washington HYDRAULIC PROJECT APPROVAL Coastal
Department of 48 Devonshire Road
FISH and RCW 77.55.021(10)&(11)-Appeal Pursuant to Chapter Montesano,WA 98563
WILDLIFE (360)249-4628
Issue Date: May 14,2008 Control Number: 112510-1
Project Expiration Date:June 15,2008 FPA/Public Notice#: N/A
17. All waste material, including the damaged bridge, both concrete abutments, construction
debris, silt, excess dirt or overburden resulting from this project shall be deposited above the limits
of flood water. The ecology blocks may be stored landward of the left bank.
18. If high flow conditions that may cause siltation are encountered during this project, work shall
stop until the flow subsides.
19. Extreme care shall be taken to ensure that no petroleum products, hydraulic fluid, fresh
cement, sediments, sediment-laden water, chemicals, or any other toxic or deleterious materials
are allowed to enter or leach into the stream.
20. Alteration or disturbance of the bank and bank vegetation shall be limited to that necessary to
construct the project. Within seven calendar days of project completion, all disturbed areas shall be
protected from erosion using vegetation or other means. Within one year of project completion, the
banks shall be revegetated with native or other approved woody species. Vegetative cuttings shall
be planted at a maximum interval of three feet (on center) and maintained as necessary for three
years to ensure 80 percent survival.
PROJECT LOCATIONS
Location #1 Neyhart Farms
WORK START: May 14, 2008 IWORK END: June 15, 2008
WRIA: Waterbody: Tributary to:
15.0446 Tahuya River Hood Canal
1/4 SEC: Section: Township: Range: Latitude: Longitude: County:
SW 1/4 13 22 N 03 W N 47.39418 W 123.01427 Mason
Location#1 Driving Directions
From Belfair(Highway 3),go SW on Highway 300/North Shore Road 15 miles,cross bridge,take first right to
Tahuya/Belfair Road,go 1 mile,turn right on Tahuya River Road,2 miles,turn right on the driveway right next to an
old kid's bus shelter(now with garbage cans),go approx. 100'and take first driveway to the right. Go to the end of
road driveway.
APPLY TO ALL HYDRAULIC PROJECT APPROVALS
This Hydraulic Project Approval pertains only to those requirements of the Washington State Hydraulic Code,
specifically Chapter 77.55 RCW(formerly RCW 77.20). Additional authorization from other public agencies may be
necessary for this project. The person(s)to whom this Hydraulic Project Approval is issued is responsible for applying
for and obtaining any additional authorization from other public agencies(local,state and/or federal)that may be
necessary for this project.
Page 3 of 5
i Washington HYDRAULIC PROJECT APPROVAL Coastal
Department of 48 Devonshire Road
FISH and RCW 77.55.021(10)&(11)-Appeal Pursuant to Chapter Montesano,WA 98563
WILDLIFE (360)249-4628
Issue Date: May 14, 2008 Control Number: 112510-1
Project Expiration Date:June 15,2008 FPA/Public Notice#: N/A
This Hydraulic Project Approval shall be available on the job site at all times and all its provisions followed by the
person(s)to whom this Hydraulic Project Approval is issued and operator(s)performing the work.
This Hydraulic Project Approval does not authorize trespass.
The person(s)to whom this Hydraulic Project Approval is issued and operator(s)performing the work may be held
liable for any loss or damage to fish life or fish habitat that results from failure to comply with the provisions of this
Hydraulic Project Approval.
Failure to comply with the provisions of this Hydraulic Project Approval could result in a civil penalty of up to one
hundred dollars per day and/or a gross misdemeanor charge, possibly punishable by fine and/or imprisonment.
All Hydraulic Project Approvals issued pursuant to RCW 77.55.021 (EXCEPT agricultural irrigation, stock watering or
bank stabilization projects)or 77.55.141 are subject to additional restrictions,conditions or revocation if the Department
of Fish and Wildlife determines that new biological or physical information indicates the need for such action. The
person(s)to whom this Hydraulic Project Approval is issued has the right pursuant to Chapter 34.04 RCW to appeal
such decisions. All agricultural irrigation,stock watering or bank stabilization Hydraulic Project Approvals issued
pursuant to RCW 77.55.021 may be modified by the Department of Fish and Wildlife due to changed conditions after
consultation with the person(s)to whom this Hydraulic Project Approval is issued: PROVIDED HOWEVER,that such
modifications shall be subject to appeal to the Hydraulic Appeals Board established in RCW 77.55.301.
APPEALS INFORMATION
If you wish to appeal the issuance or denial of,or conditions provided in a Hydraulic Project Approval,there are
informal and formal appeal processes available.
A. INFORMAL APPEALS(WAC 220-110-340)OF DEPARTMENT ACTIONS TAKEN PURSUANT TO RCW 77.55.021,
77.55.141, 77.55.181,and 77.55.291: A person who is aggrieved or adversely affected by the following Department
actions may request an informal review of:
(A)The denial or issuance of a Hydraulic Project Approval,or the conditions or provisions made part of a Hydraulic
Project Approval;or
(B)An order imposing civil penalties. A request for an INFORMAL REVIEW shall be in WRITING to the Department
of Fish and Wildlife HPA Appeals Coordinator,600 Capitol Way North, Olympia,Washington 98501-1091 and shall be
RECEIVED by the Department within 30 days of the denial or issuance of a Hydraulic Project Approval or receipt of an
order imposing civil penalties. If agreed to by the aggrieved party,and the aggrieved party is the Hydraulic Project
Approval applicant,resolution of the concerns will be facilitated through discussions with the Area Habitat Biologist and
his/her supervisor. If resolution is not reached,or the aggrieved party is not the Hydraulic Project Approval applicant,
the Habitat Technical Services Division Manager or his/her designee shall conduct a review and recommend a decision
to the Director or his/her designee. If you are not satisfied with the results of this informal appeal, a formal appeal may
be filed.
B. FORMAL APPEALS (WAC 220-110-350)OF DEPARTMENT ACTIONS TAKEN PURSUANT TO RCW 77.55.021
(EXCEPT agricultural irrigation,stock watering or bank stabilization projects)or 77.55.291:
A person who is aggrieved or adversely affected by the following Department actions may request a formal review of:
(A)The denial or issuance of a Hydraulic Project Approval,or the conditions or provisions made part of a Hydraulic
Project Approval;
(B)An order imposing civil penalties;or
(C)Any other'agency action'for which an adjudicative proceeding is required under the Administrative Procedure
Act,Chapter 34.05 RCW.
A request for a FORMAL APPEAL shall be in WRITING to the Department of Fish and Wildlife HPA Appeals
Coordinator,shall be plainly labeled as'REQUEST FOR FORMAL APPEAL'and shall be RECEIVED DURING
OFFICE HOURS by the Department at 600 Capitol Way North, Olympia,Washington 98501-1091,within 30-days of
the Department action that is being challenged. The time period for requesting a formal appeal is suspended during
Page 4 of 5
Washington HYDRAULIC PROJECT APPROVAL Coastal
Department of 48 Devonshire Road
FISH and RCW 77.55.021(10)&(11)-Appeal Pursuant to Chapter Montesano,WA 98563
WILDLIFE (360)249-4628
Issue Date: May 14, 2008 Control Number: 112510-1
Project Expiration Date:June 15, 2008 FPA/Public Notice#: N/A
consideration of a timely informal appeal. If there has been an informal appeal,the deadline for requesting a formal
appeal shall be within 30-days of the date of the Department's written decision in response to the informal appeal.
C. FORMAL APPEALS OF DEPARTMENT ACTIONS TAKEN PURSUANT TO RCW 77.55.021 (agricultural irrigation,
stock watering or bank stabilization only), 77.55.141, 77.55.181,or 77.55.241: A person who is aggrieved or adversely
affected by the denial or issuance of a Hydraulic Project Approval,or the conditions or provisions made part of a
Hydraulic Project Approval may request a formal appeal. The request for FORMAL APPEAL shall be in WRITING to
the Hydraulic Appeals Board per WAC 259-04 at Environmental Hearings Office,4224 Sixth Avenue SE, Building Two-
Rowe Six, Lacey,Washington 98504;telephone 360/459-6327.
D. FORMAL APPEALS OF DEPARTMENT ACTIONS TAKEN PURSUANT TO CHAPTER 43.21 L RCW: A person
who is aggrieved or adversely affected by the denial or issuance of a Hydraulic Project Approval,or the conditions or
provisions made part of a Hydraulic Project Approval may request a formal appeal. The FORMAL APPEAL shall be in
accordance with the provisions of Chapter 43.21 L RCW and Chapter 199-08 WAC. The request for FORMAL APPEAL
shall be in WRITING to the Environmental and Land Use Hearings Board at Environmental Hearings Office,
Environmental and Land Use Hearings Board,4224 Sixth Avenue SE, Building Two-Rowe Six, P.O. Box 40903,
Lacey,Washington 98504;telephone 360/459-6327.
E. FAILURE TO APPEAL WITHIN THE REQUIRED TIME PERIODS results in forfeiture of all appeal rights. If there is
no timely request for an appeal,the department action shall be final and unappealable.
ENFORCEMENT: Sergeant Jackson (29) P1
Habitat Biologist �DrDi�ctor
Gloria Rogers 360-249-4628
CC: Mason County Department of Community Development (emailed)
Ryan Crater and Pam Bennett-Cumming
Post Office Box 279
Shelton, WA 98584
Page 5 of 5
n )
sTar,ofi
a �n
a x
ws �_
�yd 1889 any
State of Washington
DEPARTMENT OF FISH AND WILDLIFE
48 Devonshire Road,Montesano,Washington 98563-9618(360)249-4628,TDD(360)902-2207,Fax(360)664-0689
July 24, 2008
Neyhart Tahuya Farms LLC
Douglas Neyhart
2297 Tahuya River Rd
Tahuya, WA 98588
Dear Mr. Neyhart:
SUBJECT: Incomplete Hydraulic Project Application Package;Bank Protection;Tahuya River,
Tributary to Hood Canal; SW 1/4, Section 13,Township 22 North,Range 03 West,
Mason County, WRIA 15.0446, WDFW Log No. 114047-01
The Department of Fish and Wildlife (WDFW) received your application for a Hydraulic Project
Approval (HPA) on July 23, 2008. To complete your application, please submit the following
information to me at the above address.
Written notice of compliance with the State Environmental Policy Act (SEPA), including
exemption or type of determination, date of exemption or final determination date, and the
lead agency is required before a HPA may be issued.
Incomplete plans were submitted with the application.
Once the above-referenced information has been received, your application will be complete and
evaluation of your HPA application will begin. The 45-day review period for evaluating applications
for HPA per RCW 77.55.021 will not start until this information is received.
I hope this information helps and please call (360)249-4628 X 249 if I can assist you through this
process.
Sincerely,
6 111�09e_r�
Gloria Rogers
Area Habitat Biologist
Cc: WRIA 15 File, Olympia(emailed)
Ryan Crater, Mason County Department of Community Development(emailed)