HomeMy WebLinkAboutCOM2019-00116 Lodge, Kitchen, Bathrooms - COM Inspections - 9/26/2024 t r7l t,
615 W.Alder St.Bldg 8,SHELTON,WA 98584
MASON COUNTY SHELTON: 360-427-9670, EXT 352
COMMUNITY SERVICES
BELFAIR:360-275-4467, EXT 352
Building,Planning,[nvlronmental Health,Community Health ELMA: 360-482-5269, EXT 352
- www.co.mason.wa.us
INSPECTION CARD AND CERTIFICATE OF OCCUPANCY**
To schedule an inspection call or visit http://www.co.mason.wa.us/community-services/bid-inspection.php
Permit Number COM2019-00116 Date Issued 07/16/2020 Issued By
Project LODGE WITH MEETING ROOM, KITCHEN 8r 4 BATHROOMS ^
Site Address 580 SE Fireweed Rd
Applicant CAMP SLUYS-IMPACT NORTHWEST
Contractor El KRISTYN&SON CONST INC
Contractor Phone 360.432.3147
Primary Code UPC IBC, IRC, IFC, IEC,IMC,& Type
Permit Type NEW COMMERCIAL PERMIT Occupancy
-APPROVED PLANS MUST BE ONSITE FOR ALL INSPECTIONS.
-DO NOT PROCEED BEYOND EACH STAGE OR COVER WORK UNTIL APPROVAL IS GRANTED.
-THIS CARD MUST BE POSTED IN A CONSPICUOUS LOCATION, FRONT OF THE PREMISES IS BEST FOR MAKING ENTRY.
-ALL PERMITS EXPIRE 180 DAYS AFTER THE PERMIT IS ISSUED OR 180 DAYS AFTER DATE OF LAST INSPECTION.
-OWNER/AGENT IS RESPONSIBLE FOR REQUESTING ALL INSPECTIONS THROUGH FINAL INSPECTION.
**THIS STRUCTURE MAY NOT BE USED OR OCCUPIED UNTIL ALL APPROVALS ARE GRANTED.**
PRIOR TO CALLING FOR FINAL INSPECTION,ALL CONDITIONS OF THE PERMIT MUST BE MET
Public Works Access/Driveway Other
Health Septic Well
Deptartment
Planning Site Inspection
Department
Fire Marshall Fire Apparatus Access Fire Sprinkler
Auto Fire Alarm Hood and Duct
Other Final
Building Building Official: Community Services Designee
Department
Concrete Setbacks 3o p)AEL Slab
Footing Perimeter Point load Footing
Footing Interior Footing Decks/Porches
Foundation Stem Walls I5 2O 1DEc Other
Rough-In Groundwork Plumbing Framing 27-23—z b
Groundwork Mechanical Plumbing 2_LA12\ C`m
Groundwork Gas Pipe Mechanical 2Iy I2\ C,LYY\
Gas Piping Shear Wall Nailing
Underfloor �O 20 ip C /o 1r5 kf j't 3 L3- J7Z
Other �0,.04ws• JZ-
Insulation Slab ZZ f7k Ceiling
Floor Vaulted Ceiling
Walls 2-23—Z DCL Vapor Barrier
Other
Wallboard Interior Wall Brace Panels Fire Walls
Nailing
Other
Final Building - 2 —2 DC� L
Manufactured Setbacks Setup
Home
Concrete Foot/Runners Final
Other
�* CAS V\9\1vl(� `ASS \\I n�20 OtC,
11
Joshua Luck
From: Joshua Luck
Sent: Tuesday, October 3, 2023 10:47 AM
To: 'EILEEN BAILEY'
Subject: Inspection Comments COM201 9-001 1 6
Good Morning,
Please see inspection comments below. If you have any questions, please feel free to contact me. All water system or
septic questions should be direct to Environmental Health (EH). 6�*Vtp I3iiss.-fj
Approval of water system required prior to occupancy, contact EH. (Review permit conditions) C/orj-'J
- Food establishment permit required, please contact Public Health @ (360)427-9670 x279 (Review permit
conditions)
- .deform water as-builts and final approval letter/report from Engineer required. (Review permit conditions)
- Grease interceptor required per the 2015 UPC and permit conditions, please address
- Fire Marshal final required (alarm) &1,0VJ
.� L&I final inspection/approval required
Install Knox box and have key properly secured (contact local fire department and/or the Fire Marshal)
Install vertical ADA grab bar in bathroom
Install boots/pads/insulation at pipes under bathroom sinks.
Paint exterior gas line
Seal exterior penetrations
/ Fix/adjust attic insulation at attic access
Post address on structure
Thank you
Joshua Luck I Deputy Building Official
Mason County Community Development
0: (360)427-9670 ext. 726
C: (360)490-4077
www.masoncountywa.goVA
V `
V
1
INSPECTION RESULTS Page
MASON COUNTY Department of Community Development
COMMUNITY DEVELOPMENT 615 W Alder St, Shelton, WA 98584
Permit Assistance Center,Building,Planning (360) 427-9670 ext. 352
Application# COM2019-00116 Application Type NEW COMMERCIAL PERMIT Owner CAMP SLUYS — IMPACT
NORTHWEST
Parcel# 320351200000 Site Address 580 SE Fireweed Rd Shelton, WA 98584
Inspector Inspection Type Date Status Comments
9-24-24-DEC
WELL PERMIT FOR CLASS B SYSTEM HAS NOT BEEN CLOSED. PLEASE
CONTACT E&H.
SWG SEPTIC PERMIT HAS BEEN CLOSED
CALL DREW WHEN WELL PERMIT HAS BEEN CLOSED 360 490 0570
10/3/23
- Approval of water system required prior to occupancy, contact EH. (Review
permit conditions)
-Storm water as-builts and final approval letter/report from Engineer required. (Review
Drew Carlson BLD-FINAL INSPECTION 09/24/2024 FAIL permit conditions)
-Grease interceptor required per the 2015 UPC and permit conditions, please address
-Fire Marshal final required (alarm)
-L&I final inspection/approval required
-Install Knox box and have key properly secured (contact local fire department and/or
the Fire Marshal)
-Install vertical ADA grab bar in bathroom
-Install boots/pads/insulation at pipes under bathroom sinks.
-Paint exterior gas line
-Seal exterior penetrations
-Fix/adjust attic insulation at attic access
-Post address on structure
r
i
�wvirotecl� �►�,g�weer�wg �L�c
ceotechvl�cal Ewv�vowwLewtal pva%wage Roadway
August 22,2024
EI Kristyn&Son
Attn:Tim Bailey
101 SE Rosewood Court
Shelton,Washington 98584
Re: Camp Sluys Drainage Plan and Report Inspection, located at 580 SE Fireweed Road,Parcel
32035-12-00000,Shelton,Washington.
Dear Mr. Bailey,
The following stormwater items have been inspected on-site and reviewed by Envirotech Engineering.
1. The driveway is slightly sloped to the west,and stormwater will sheetflow to the west.There is
over 100 feet of native vegetation on the property that allows for Full Dispersion,BMP T5.30.
2. The Dispersion Trench was moved to the southwest portion of the parking area.This is
acceptable.The trench is 21 feet long,but due to the length of natural vegetated flowpath,
approximately 150',it has been determined that Full Dispersion will accommodate all extra flow
from smaller trenches.
Please call Michael Staten at 360-689-6045 if you have any questions or require additional
information.
Sincerely,
Envirotech Engineering, PLLC
PAL CLYpF ST
%NV:A
?� ,p 43045 0 :�
Gc EGISTERF
1 A L IG` 8/22/24
Michael Staten,P.E.
Project Director
PO gox984
getfatr, washtin,gtow98528
cel,t: 360-689-6045
ewvtvotech@geotechv�.tcattw fo.cow�.
CERTIFICATE OF OCCUPANCY
Mason County, WA
OWNERS NAME: IMPACT NORTHWEST
OWNER'S ADDRESS: 3711 S SR 27 HWY F104 SPOKANE WA, 99206
SITE ADDRESS: 580 SE FIREWEED RD, SHELTON WA, 98584
BUILDING PERMIT NUMBER: COM2019-00116
DESCRIPTION: LODGE WITH MEETING ROOM, KITCHEN & 4 BATHROOMS
BUILDING OFFICIAL: KELL ROWEN TELEPHONE NUMBER: (360) 427-9670 ext. 352
CODE/EDITTION: 2015 IBC USE OF STRUCTURE: CAMP LODGE **
OCCUPANCY: A-3 OCCUPANT LOAD: 79
TYPE OF CONSTRUCTION: v B SPRINKLER SYSTEM REQUIRED: NO
This structure has been inspected for compliance with the requirements of this code for occupancy and
the use for which the proposed occupancy is classified.
CONDITIONS OR STIPULATIONS:
MUST MAINTAIN ALL STORM WATER SYSTEMS, FIRE PROTECTION SYSTEMS AND PERMIT
CONDITIONS.
**CAMP LODGE W/COMERCIAL KITCHEN
Mason County
Mason County - Division of Community Development
�r 615 W. Alder St. Bldg.8
Shelton, WA 98584
360-427-9670 ext 352
www.co.mason.wa.us
E
019-00116 NEW COMMERCIAL PERMIT
T DESCRIPTION: LODGE WITH MEETING ROOM, KITCHEN & ISSUED: 07/16/2020
OOMSDRESS: 580 SE FIREWEED RD SHELTON EXPIRES: 08/03/2021
PARCEL: 320351200000
APPLICANT: CAMP SLUYS - IMPACT NORTHWEST OWNER: CAMP SLUYS - IMPACT NORTHWEST
3711 SOUTH STATE ROUTE27 F-104 3711 SOUTH STATE ROUTE27 F-104
SPOKANE,WA99206 SPOKANE, WA 99206
1.360.432.3147
GENERAL CONTRACTOR'S LICENSE: El KRISTYN &SON CONST INC License: EIKRIKS950QD
101 ROSEWOOD CT Expires: 11/04/2021
SHELTON,WA98584
360.432.3147
VALUATIONS: FEES: Paid Due
A-3 VB Assembly, general, 2000.00 $257,560.00 Planning Commercial Review $380.00 $0.00
community halls, libraries, Fee
museums IFC Plan Check Fee $701.61 $0.00
Covered Deck/Carport 720.00 $15,840.00 Pre-application meeting - Major $220.00 $0.00
EH Plan Review
Building Permit Fee $2,158.80 $0.00
State Fee-Commercial $25.00 $0.00
Plan Check Fee $1,403.22 $0.00
Planning Stormwater Review $300.00 $0.00
Mechanical Base Fee $30.00 $0.00
Plumbing Fees $136.00 $0.00
Mechanical Fees $268.00 $0.00
Plumbing Base Fee $25.00 $0.00
Technology Surcharge $80.42 $0.00
Building Plan Review Revisions $80.00 $0.00
Total: $273,400.00 Totals : $5,808.05 $0.00
FIXTURES
Printed by:Corey Bennett on:02/22/2021 04:11 PM
Page 1 of 8
1
Mason County
Mason County - Division of Community Development
615 W. Alder St. Bldg.8
�• , % Shelton, WA 98584
360-427-9670 ext 352
www.co.mason.wa.us
NEW COMMERCIAL PERMIT COM2019-00116
Cat Mechanical Fixtures Qty Plumbing Fixtures
1.0000 For each air-handling unit to and including 10,000 1.0000 Number of Dishwashers
cubic feet per minute (cfm) (4719L/s), including 1.0000 DRINKING FOUNTAIN
attached ducts.
1.0000 For each air-handling unit over 10,000 cfm
1.0000 SINK-3 WITH DRAIN
(4719L/s) 1.0000 Number of Water Heaters and or Vent
1.0000 Propane Tank(s) 4.0000 Number of Hose Bibs
1.0000 Wood/Gas/Pellet Stove(s) 4.0000 Bathroom Sink
3.0000 Gas Outlet(s) (1-5) 4.0000 URINAL
5.0000 Spot Vent Fan(s)
REQUIRED INSPECTIONS
Setback Inspection Insulation Inspection
Footing Inspection Fire Marshal Final
Foundation Wall-Pre-Pour Inspection BLD-Final Inspection
Framing Inspection SLAB INSPECTION
Rough- Plumbing Inspection Underfloor- Plumbing
Mechanical Inspection Gas Piping Inspection
CONDITIONS
Carbon monoxide alarms, listed as complying with UL 2075 shall be installed in accordance with manufacturer
specifications and in accordance with IRC Section R315.
Alarms shall be installed outside of each separate sleeping area in the immediate vicinity of the bedrooms and on each level
of the dwelling.
EXISTING DWELLINGS shall be equipped with carbon monoxide alarms when alterations (including addition or alteration of
fuel burning appliances), repairs, or additions requiring a permit occur, or when one or more sleeping rooms are added or
created.
All surface water and potential runoff must be controlled on site and shall not adversely affect any adjacent properties nor
increase the velocity flow entering or abutting to any state or county culverting/ditching system or road way.
" Owner/Agent is responsible to post the assigned address and/or purchase and post private road signs in accordance
with Mason County Title 14.28 and 14.17.
x The plan review check list and corrections are part of the approved plans and must remain attached. It is the responsibility
of the applicant, owner or contractor to make the required corrections indicated on the plans. Once the plans are marked
"APPROVED", they shall not be changed or altered without authorization from the Building Official. The permit holder is
responsible to retain the complete approved set of plans on site for the duration of the project. Failure to comply and/or
removal of approved documents will result in failure of required building inspections.
Printed by:Corey Bennett on:02/22/2021 04:11 PM
Page 2 of 8
Mason County
Mason County - Division of Community Development
� 615 W. Alder St. Bldg.8
z� Shelton, WA 98584
360-427-9670 ext 352
www.co.mason.wa.us
NEW COMMERCIAL PERMIT COM2019-00116
By definition, propane tanks and heatpumps are structures, which must meet setback conditions. Please check your
"Approved Site Plan" to ensure these structures meet the setback conditions listed.
* WIND LOADS - Roof coverings shall be designed and tested to withstand the maximum basic wind speed. The basic wind
speed for Mason County is 85 MPH.
* All permits expire 180 days after permit issuance, or 180 days after the last inspection activity is performed. The Building
Official may grant a one time extention of 180 days, upon the receipt of a written extension request prior to permit expiration.
Letter must indicating that circumstances beyond the control of the permit holder preventing action from being taken. No
more than one extension may be granted.
* Concrete encased grounding electrodes must be installed and used at each new building or structure that is built upon a
permanent concrete foundation. In Mason County the electrical code is regulated by Washington State Department of Labor
& Industries (L&I).
For more information contact L&I for additional information. In Olympia call (360)902-6350 and in Bremerton call (360)415-
4000.
* Approved per dimensions and setbacks on submitted site plan. Setbacks are measured from the furthest projection of the
structure.
The foundation/footing must be placed on undisturbed, firm-native soil. Min of 12" below grade.
* The international code requires a fire apparatus access road for every facility, building, or portion of a building that is more
than 150'from an approved access road. Roads are required to meet the minimum Mason County Fire Marshal standards
for Fire Apparatus Access Roads up to the point where such roads connect with a county maintained public road or to
another fire apparatus access road which connects to a county maintained public road.
* CONSTRUCTION PROCESS TO BE FIELD CORRECTED AS REQUIRED PER MASON COUNTY BUILDING
DEPARTMENT AND THE ADOPTED BUILDING CODE.
The construction of the permitted project is subject to inspections by the Mason County Building Department. All
construction must be in conformance with the international codes as amended and adopted by Mason County. Any
corrections, changes or alterations required by a Mason County Building Inspector shall be made prior to requesting
additional inspections.
* When parcel development requires direct access to county road(s), a Road Access Permit or Approval must be granted by
the Mason County Department of Public Works. For more information contact Public Works, at (360) 427-9670, ext. 450 or
100 W Public Works Dr. Shelton. The building permit will not be finaled until the permit holder can show proof that the
access permit from Public Works has been finaled and approved.
* Pressure treated wood manufactured after January 1, 2004 may contain high concentrations of copper which could quickly
corrode metal fasteners, connectors, and flashing. Install metal connectors approved for contact with the new types of
pressure treated material.
* The stamped approved site plan is required to be on-site for inspection purposes. If an inspection is requested and the
approved site plan is not on site, approval will not be granted. In addition, a re-inspection fee (refer to current fee schedule,
minimum 1 hour)will be charged and shall be collected by the Building Department prior to any further inspections being
performed or approvals granted.
* Provisions for surface/subsurface drainage control must be implemented with new construction or development on site and
MUST NOT adversely impact adjacent parcels. Under the requirements of Mason County Stormwater Ordinance, either
private ditches and drains will meet requirements of the stormwater ordinance or prior approval will be granted to use an
existing utility and drainage easement dedicated for that specific purpose. For further information regarding this ordinance
and the REQUIREMENT to obtain an ACCESS PERMIT for the installation/construction of a driveway or access connecting
from a Mason County Road, Contact the Mason County Public Works Department prior to construction at Ext 450. For any
construction which is proposed to be located within 25' of a Mason County road right of way, it is suggested to contact that
office to review future planned work which may affect your project.
Printed by:Corey Bennett on:02/22/2021 04:11 PM
Page 3 of 8
Mason County
w<r , Mason County - Division of Community Development
615 W. Alder St. Bldg.8
Shelton, WA 98584
360-427-9670 ext 352
www.co.mason.wa.us
NEW COMMERCIAL PERMIT COM2019-00116
All building permits shall have a final inspection performed and approved by Mason County Building Department prior to
permit expiration. The failure to request a final inspection or to obtain approval will be documented in the legal property
records on file with Mason County as being non-compliant with Mason County ordinances and building regulations.
Contractor registration laws are governed under RCW 18.27 and enforced by the WA State Dept of Labor and Industries,
Contractor Compliance Division. There are potential risks and monetary liabilities to the homeowner for using an
unregistered contractor. Further information can be obtained at 1-800-647-0982. The person signing this condition is either
the homeowner, agent for the owner or a registered contractor according to WA state law.
A Mason County Stormwater Management Worksheet was completed and signed as part of this building permit
application. Design, sizing, placement, inspection and maintenance of stormwater management systems shall be the
responsibility of the owner/agent of the developed parcel. It is the owner/agent/contractor's responsibility to ensure that
Mason County Department of Public Works has approved the stormwater site plan for this parcel prior to the commencement
of any development activities. "NOTE if Stormwater Management option "A" was selected on the Small Parcel Stormwater
Management Application/Worksheet the document entitled"Managing Storm Drainage on Small Lots, The Small Parcel
Stormwater Site Plan" constitutes an approved plan based on the criteria listed on the application/worksheet. If the
development has, or will have, a septic/drainfield system you are responsible for contacting Mason County Division of
Environmental Health to ensure that the stormwater system will not adversely affect the septic system of this, or any other,
parcel. You may also wish to consult with the septic design professional involved with the project. By calling for a final
inspection of the building permit the owner/agent/contractor is acknowledging that all components of the stormwater
management system have been installed as approved on the stormwater site plan.
Provisions for surface/subsurface drainage control must be implemented with new construction or development on site and
MUST NOT adversely impact adjacent parcels. Under the requirements of Mason County Stormwater Ordinance, either
private ditches and drains will meet requirements of the stormwater ordinance or prior approval will be granted to use an
existing utility and drainage easement dedicated for that specific purpose. For further information regarding this ordinance
and the REQUIREMENT to obtain an ACCESS PERMIT for the installation/construction of a driveway or access connecting
from a Mason County Road, Contact the Mason County Public Works Department prior to construction at Ext 450. For any
construction which is proposed to be located within 25' of a Mason County road right of way, it is suggested to contact that
office to review future planned work which may affect your project.
* All construction must meet or exceed all local and state ordinances in addition to the International Codes requirements as
adopted and amended by Mason County and the State of Washington. Occupancy is limited to the approved and permitted
classification. Any non-approved change of use or occupancy would result in permit revocation.
All RED stamped approved plans are required to be on-site for inspection purposes. If an inspection is called for and
plans are not available on site, then approval will not be granted. In addition, a re-inspection fee (refer to current fee
schedule, minimum 1 hour)will be charged and must be collected by the Building Department prior to any further inspections
being performed or approvals granted.
' All changes to "approved" building plans that effect compliance with the international codes as amended and adopted, or
any other Mason County ordinance or regulation, must be reviewed and approved by Mason County prior to construction.
• All property lines shall be clearly identified at the time of foundation inspection.
• REQUIREMENTS FOR ROOF COVERINGS. Roof coverings shall be applied in accordance with the applicable
provisions of the current code and the manufacturer's installation instructions.
A drip edge shall be provided at eaves and gables of shingle roofs.
Printed by:Corey Bennett on:02/22/2021 04:11 PM
Page 4 of 8
Mason County
Mason County - Division of Community Development
615 W. Alder St. Bldg.8
Shelton, WA 98584
360-427-9670 ext 352
www.co.mason.wa.us
NEW COMMERCIAL PERMIT COM2019-00116
* FIRE:
Type I hood w/suppression, Deferred permit
Fire Alarm System, deferred permit
Fire Extinguisher locations noted plans
Panic hardware, occupant load signs
Post address
Knox box
* STORAGE RACKS
Storage racks greater than 59" and up to 8'0"in height shall be installed in accordance to manufacturer specifications for
seismic attachment. When seismic attachment is not provided by the manufacturer an engineered design and attachment
details shall be required. Installation specifications or engineer's design shall be available during inspections performed by
the Mason County Building Department.
Storage racks greater than 8-ft in height shall require an engineer's design addressing seismic conditions and attachment.
In addition, storage racks 8-ft tall or more shall require special inspection performed by the design professional or an
approved representative. The special inspection report and engineered design shall be provided to the Mason County
Building Department for approval prior to the final occupancy inspection.
* Accessible parking spaces shall be provided in accordance the 2015 International Building Code Section 1106 and
constructed in accordance with Section 1101.2/ICC A117.1. Accessible parking spaces shall be provided in accordance with
Table 1106.1 as follows:
1 to 25 total parking spaces requires not less than one accessible parking space
26 to 50 total parking spaces requires not less than two accessible parking spaces
51 to 75 total parking spaces requires not less than three accessible parking spaces
76 to 100 total parking spaces requires not less than four accessible parking spaces
See IBC Section 1106 and table for more than 100 parking spaces.
Construction and design shall be completed in accordance with ICC A117.1, Section 502. Accessible parking spaces shall
be located on the shortest accessible route of travel from adjacent parking to an accessible building entrance. Car parking
shall be not less than 96-inches wide and access aisles not less than 60-inches wide shall be properly marked. Parking
surfaces shall be firm, stable, and slip resistant material and shall not be steeper than 1:48. Accessible parking spaces shall
be clearly identified by signs containing the International Symbol of Accessibility placed not less than 60-inches above
ground surface.
* System commissioning required per section C408 of the 2015 Washington State Energy Code (WSEC).The proposed
project requires commissioning reports for the following elements: Lighting Occupant Sensor Control (C408.3.1.1). See
approved plans for occupant sensor requirements.
* C402.5 Air leakage—thermal envelope (Mandatory).
The thermal envelope of buildings shall comply with Sections C402.5.1 through C402.5.8
C402.5.1 Air barriers. A continuous air barrier shall be provided throughout the building thermal envelope. The air barriers
shall be permitted to be located on the inside or outside of the building envelope, located within the assemblies composing
the envelope, or any combination thereof. The air barrier shall comply with Sections C402.5.1.1 and C402.5.1.2.
Printed by:Corey Bennett on:02/22/2021 04:11 PM
Page 5 of 8
Mason County
Mason County - Division of Community Development
615 W. Alder St. Bldg.8
Shelton, WA 98584
360-427-9670 ext 352
www.co.mason.wa.us
NEW COMMERCIAL PERMIT COM2019-00116
C402.5.1.1 Air barrier construction. The continuous air barrier shall be constructed to comply with the following:
1. The air barrier shall be continuous for all assemblies that are the thermal envelope of the building and across the joints
and assemblies.
2.Air barrier joints and seams shall be sealed, including sealing transitions in places and changes in materials being sealed
and shall be securely installed around the penetrations so as not to dislodge, loosen or otherwise impair the penetrations'
ability to resist po rials. The joints and seals shall be securely installed in or on the joint for its entire length so as not to
dislodge, loosen or otherwise impair its ability to resist positive and negative pressure from wind, stack effect
and mechanical ventilation.
3. Penetrations of the air barrier shall be caulked, gasket or otherwise sealed in a manner compatible with the construction
materials and location. Joints and seals associated with penetrations shall be sealed in the same manner or taped or
covered with moisture vapor-permeable wrapping material. Sealing materials shall be appropriate to the construction and
negative pressure from wind, stack effect, and mechanical ventilation. Sealing of concealed fire sprinklers, where required,
shall be in a manner that is recommended by the manufacturer. Caulking or other adhesive sealants shall not be used to fill
voids between fire sprinkler cover plates and walls or ceilings.
4. Recessed lighting fixtures shall comply with Section C402.5.8. Where similar objects are installed which penetrate the air
barrier, provisions shall be made to maintain the integrity of the air barrier.
5. Construction documents shall contain a diagram showing the building's pressure boundary in plan(s)and section(s)and a
calculation of the area of the pressure boundary to be considered in the test.
* C402.5.1.2 Building test. The completed building shall be tested, and the air leakage rate of the building envelope shall not
exceed 0.40 cfm/ft2 at a pressure differential of 0.3 inches water gauge (2.0 L/s x m2 at 75 Pa) at the upper 95 percent
confidence interval in accordance with ASTM E 779 or an equivalent method approved by the code official.A report that
includes the tested surface area, floor area, air by volume, stories above grade, and leakage rates shall be submitted to the
building owner and the Code Official. If the tested rate exceeds that defined here, a visual inspection of the air barrier shall
be conducted, and any leaks noted shall be sealed to the extent practicable. An additional report identifying the corrective
actions taken to seal air leaks shall be submitted to the building owner and the Code Official and any further requirement to
meet the leakage air rate will be waived.
1. Test shall be accomplished using either(1) both pressurization and depressurization or(2) pressurization alone, but not
depressurization alone. The test results shall be plotted against the correct P for pressurization in accordance with Section
9.4 of ASTM E779.
2. The test pressure range shall be from 25 Pa to 80 Pa per Section 8.10 of ASTM E779, but the upper limit shall not be less
than 50 Pa, and the difference between the upper and lower limit shall not be less than 25 Pa.
3. If the pressure exponent n is less than 0.45 or greater than 0.85 per Section 9.6.4 of ASTM E779, the test shall be rerun
with additional readings over a longer time interval
" Minimum 2A10BC rated fire extinguishers shall be permanently installed, unobstructed and located in a conspicuous
location not more than 75-feet travel distance in approved locations mounted not more than 48-inches from the finished floor
to the top of the extinguisher.
The structure is subject to inspection by the Mason County Fire Marshal. All corrections deemed necessary by the Fire
Marshal, to assure the minimum fire and life safety requirements as adopted by Mason County and Washington State may
be required.
POST OCCUPANT LOAD
Every room or space that is assembly occupancy, such as a restaurant, bar, or meeting room, shall have the occupant load
of the room or space posted in a conspicuous place, near the main exit or exit access doorway from the room or space.
Posted signs shall be of an approved legible permanent design and shall be maintained by the owner or agent. (IBC1004.3)
Printed by:Corey Bennett on:02/22/2021 04:11 PM
Page 6 of 8
Mason County
' Mason County - Division of Community Development
615 W. Alder St. Bldg.8
Shelton, WA 98584
360-427-9670 ext 352
www.co.mason.wa.us
NEW COMMERCIAL PERMIT COM2019-00116
* Commercial Hoods
All kitchen hood systems shall be installed and maintained as required by the International Fire Code, Building Code and
Mechanical Code. Inspection and maintenance records shall be available for inspectors during all inspections.
* An approved grease interceptor shall be correctly sized and properly installed in grease waste lines leading from sinks and
drains as required in the 2015 Uniform Plumbing code, Chapter 10.
* Rooms and enclosed spaces shall have Class C interior wall and ceiling finishes or better. Class C finishes shall have a
smoke developed index of 0-450 and a flame spread index of 76-200. Provide classification information during inspection.
Combustible waste material creating a fire hazard shall not be allowed to accumulate in buildings or structures or upon
premises (IFC 304.1). A maintenance plan shall be available for during the final occupancy inspection performed by the
Mason County Fire Marshal.
OWNER/ BUILDER acknowledges submission of inaccurate information may result in a stop work order or permit
revocation. Acknowledgement of such is by signature below. I declare that I am the owner, owners legal representative, or
contractor. I further declare that I am entitled to receive this permit and to do the work as proposed. I have obtained
permission from all the necessary parties, including any easement holder or parties of interest regarding this project. The
owner or authorized agent represents that the information provided is accurate and grants employees of Mason County
access to the above described property and structure(s)for review and inspection. This permit/application becomes null &
void if work or authorized construction is not commenced within 180 days or if construction work is suspended for a period of
180 days. PROOF OF CONTINUATION OF WORK IS BY MEANS OF INSPECTION. INACTIVITY OF THIS PERMIT
APPLICATION OF 180 DAYS WILL INVALIDATE THE APPLICATION.
Any changes in proposed construction shall be reviewed by the engineer or architect of record and submitted in writing to
the Mason County Building Department prior to construction. All engineering and/or architectural documents are a part of
the approved set of plans and shall remain attached thereto. If documents are removed, approval will not be granted. In
addition, a re-inspection fee (refer to current fee schedule, minimum 1 hour) will be charged and shall be collected by the
Building Department prior to any further inspections being performed or approvals granted.
* The use, handling and storage of hazardous materials or flammable and combustible liquids in excess of 10 gallons is not
allowed without the approval of the Mason County Fire Marshal.
* In an Assembly Occupancy group with less than 300 occupant load, occupancy groups B, F, M, and S you may only use a
lock that prevents operation of the door at the MAIN door ONLY. In"Main" door (front door, primary door). It is intended to be
limited to the door that customers come in. The main door only, a lock is allowed ONLY if the following three criteria are
satisfied: 1. The lock is readily distinguishable as locked (storefront door deadbolts that have an indicator that reads
OPEN/LOCKED) and 2. A readily visible sign with 1" letters high on a contrasting background. 'THIS DOOR TO REMAIN
UNLOCKED WHEN THIS SPACE IS OCCUPIED" And 3. The provision of key-locking doors allowance may be revoked by
the building official. X
" All doors shall be pivoted or sides hinged and swing in the direction of exit travel. Means of egress doors shall be readily
distinguishable from the adjacent construction and finishes such that the doors are easily recognizable as doors. Egress
doors shall be side-hinged unless specifically exempted in the Section 1010.1.2.1 & 10.10.1.2 of the International Building
Code & International Fire Code. X
* Concrete used for basement walls, foundation walls, exterior walls, porches, carport slabs, steps exposed to the weather,
garage floor slabs and other vertical concrete work exposed to the weather shall have a minimum compressive strength of
3000 psi (IRC Table R402.2).
Parking shall be sufficient for standard parking stalls (9 feet by 20 feet) and handicap parking stalls (12.5 feet by 20 feet)
with sufficient maneuvering aisles. Handicap stalls shall be of a smooth surface at level or ramped to entry, located closest
to the building entry, and shall be signed with the International Symbol of Access. Screening from adjacent residential
properties is required.
Printed by:Corey Bennett on:02/22/2021 04:11 PM
Page 7 of 8
Mason County
I ' Mason County - Division of Community Development
615 W. Alder St. Bldg.8
Shelton, WA 98584
360-427-9670 ext 352
www.co.mason.wa.us
NEW COMMERCIAL PERMIT COM2019-00116
* All propane tanks must be installed in accordance with the International Fire Code and all applicable Mason County
ordinances. All propane tanks must meet the installation requirements and minimum setbacks as listed in the Mason County
Fire Marshal's Standards for the Installation of Propane Tanks.
* All propane tanks must be installed in accordance with the International Fire Code and all applicable Mason County
ordinances. All Propane tanks between 125 and 500 gallons must be located a minimum of 10'from any building, possible
source of ignition (electrical outlets, electrical fixtures, compressors, etc), and/or any weeds, grass, brush, trash or any other
similar combustible materials. Setback to the public way, or access easements shall be the greater of 25-ft or as specified in
the Mason County Development Regulations. Setback to property lines shall be the greater of 10-ft or as specified in the
Mason County Development Regulations. If a propane tank is exposed to probable vehicular damage, protective bollards
must be installed.
* Retaining walls needed to support a surcharge such as structures, roads, or to support slopes, shall require a separate
building permit and approval prior to construction of the retaining wall.
* All slabs within the heated space shall be insulated to a minimum R-10 for at least 24". Monolithic slabs shall be insulated
around the perimeter from the top of the slab to the bottom of the footing. If slab is heated then entire slab and perimeter are
to be insulated to an R-10.
* Compliance with an approved Storm Water Plan shall be subject to an on site inspection, or inspections, by the engineer
of record or an authorized representative. Said inspection(s) shall be performed in accordance with the approved plan, and
prior to any modification that would make a determination of compliance impossible.
Inspection reports and as-built drawings shall be submitted to verify all engineering requirements have been completed in
accordance with the approved storm water plan. Reports shall be submitted to the Mason County Department of Community
Development prior to each corresponding inspection and final permit approval. Copies of all special inspection reports shall
Jbmade available at time of inspection.
roof of Water System completion and final approval required prior to any form of occupancy or use of structure.
0 An annual food establishment permit will be required for the use described within permit. Contact environmental health for
permit application prior to occupancy.
I hereby certify that I have read and examined this application and know the same to be true and correct.
All provisions of Laws and Ordinances governing this type of work will be complied with whether
specified herein or not. The granting of a permit does not presume to give authority to violate or cancel
the provisions of any other state/local law regulating construction or the performance of construction.
Issued By:
Contractor or Authorized Agent: Date: