HomeMy WebLinkAboutGEO2018-00068 for BLD2018-01029 - GEO Geological Review - 11/29/2018 �1��i801ONRECEIVED
MASON COUNTY DEC 0 3 2018 Submittal Checklist
• l COMMUNITY SERVICES
Building,Planning,Environmental Health,Community Healt 1 J ,• /'Uder StreQeotechnical Report
Instructions:
This checklist must be submitted with a Geotechnical Report and completed, signed, and stamped by the licensed
professional(s)who prepared the Geotechnical Report for review by Mason County pursuant to the Mason County
Resource Ordinance. If an item is found not applicable, the report should explain the basis for the conclusion.
Note:Unless specifically documented, this report does not provide compliance to the International Residential Code Sections
R403.1.7 for foundations on or adjacent to slopes, Section R403.1.8 for expansive soils or section 1808.7.1 of the International
Building Code Section for Foundations on or adjacent to slopes. n p
Applicant/Owner VL/%YP Parcel#
Site Address e% c;
(1) (a) A discussion of general geologic conditions in the vicinity of the proposed development,
Located on page(s)
(b) A discussion of specific soil types,
Located on page(s) & - C7
(c) A discussion of ground water conditions,
Located on page(s)
(d) A discussion of the upslope geomorphology,
Located on page(s) / 0
(e) A discussion of the location of upland waterbodies and wetlands,
Located on page(s) / 0
(f) A discussion of history of landslide activity in the vicinity, as available in the referenced maps and records.
Located on page(s) /0
(2) A site plan which identifies the important development and geologic features.
Located on Map(s) /D F/4 01r Z
(3) Locations and logs of exploratory holes or probes.
Located on Map(s) I /�—/G Wr Z
(4) The area of the proposed development, the boundaries of the hazard, and associated buffers and setbacks shall
be delineated (top, both sides, and toe) on a geologic map of the site.
Located on Map(s) I 0
(5) A minimum of one cross section at a scale which adequately depicts the subsurface profile, and which
incorporates the details of proposed grade changes.
Located on Map(s) 20 2 3 -2 L/
1
(6) A description and results of slope stability analyses performed for both static and seismic loading conditions.
Analysis should examine worst case failures. The analysis should include the Simplified Bishop's Method of
Circles. The minimum static safety factor is 1.5, the minimum seismic safety factor is 1.1, and the quasi-static
analysis coefficients should be a value of 0.15.
Located on page(s) /() - i Z
(7) (a) Appropriate restrictions on placement of drainage features,
Rev. February 2018
K Located on page(s 13
(b) Appropriate restrictions on placement of septic drain fields,
Located on page(s) 13 2-
(c) Appropriate restrictions on placement of compacted fills and footings,
Located on page(s)
(d) Recommended buffers from the landslide hazard areas shoreline bluffs and the tops of other slopes.
Located on page(s) 1_/
(e) Recommended setbacks from the landslide hazard areas shoreline bluffs and the tops of other slopes.
Located on page(s) 14/
(8) Recommendations for the preparation of a detailed clearing and grading plan which specifically identifies
vegetation to be removed, a schedule for vegetation removal and replanting, and the method of vegetation
removal.
Located on page(s) l
(9) Recommendations for the preparation of a detailed temporary erosion control plan which identifies the specific
mitigating measures to be implemented during construction to protect the slope from erosion, landslides and
harmful construction methods.
Located on page(s) / S
(10) An analysis of both on-site and off-site impacts of the proposed development.
Located on page(s)
(11) Specifications of final development conditions such as, vegetative management, drainage, erosion control, and
buffer widths.
Located on page(s) 115-
(12) Recommendations for the preparation of structural mitigation or details of other proposed mitigation.
Located on page(s) l
(13) A site map drawn to scale showing the property boundaries, scale, north arrow, and the location and nature of
existing and proposed development on the site.
Located on Map(s) / 6-
I, C v2nS hereby certify under penalty of perjury that I am a civil engineer licensed in the
State of Washington with specialized knowledge of geotechnical/geological engineering or a geologist or engineering
geologist licensed in the State of Washington with special knowledge of the local conditions. I also certify that the
of W Geotechnical Report, dated and entitled
meets all the requirements of the Mason County Resource Ordinance,
Geologically Hazardous Areas Section, is complete and true, that the
2439
G g� assessment demonstrates conclusively that the risks posed by the
landslide hazard can be mitigated through the included geotechnical
�Sed 0 design recommendations, and that all hazards are mitigated in such a
Curtis Dean Cushman manner as to prevent harm to property and public health and safety.
Page 2 of 2
Disclaimer. Mason County does not certify the quality of the work done in this Geotechnical Report.
i
GEOTECHNICAL REPORT
GAGE RESIDENTIAL SITE
419 NE BEARCREEK-DEWATTO ROAD
BELFAIR, WASHINGTON
PREPARED FOR
VALERIA GAGE
BY
ALL AMERICAN GEOTECHNICAL
OLYMPIA, WASHINGTON
NOVEMBER 29, 2018
ALL AmEmcm GEoTEcnNtcAL
CONTACT INFORMATION
PREPARER INFORMATION
AAG PROJECT NUMBER: AAG18-082
CONTACT: CURTIS D.CUSHMAN
ADDRESS: 8947 BUTTONWOOD LANE NE
OLYMPIA,WASHINGTON 98516
TELEPHONE: (360)491-5155
CELL/TEXT: (360)481-6677
EMAIL ADDRESS: CURTIS.CUSHMAN@COMCAST.NET
CLIENT INFORMATION
CLIENT: VALERIE GAGE
ADDRESS: VALERIE GAGE
4739 BLACKBERRY HILL LN
PORT ORCHARD,WASHINGTON 98366
SITE ADDRESS: 419 BEARCREEK-DEWATTO ROAD
BELFAIR,WASHINGTON
TELEPHONE: (360)769-2429—LAND (360)565-9317-CELL
CLIENT CONTACT: TOM FULKERSON
TELEPHONE: (253)230-6268
EMAIL ADDRESS: TFULKERSON@MSN.COM
PARCEL: 12309-31-90074
GPS LOCATION: N470 29'37.81" W1220 48' 57.84" (at residential site)
AAG 18-082 8947 Buttonwood Lane NE,Olympia, WA 98516 2
Phone#: (360)491-5155 Cell#: (360)481-6677
ALL Am N G T aNicAL
SCOPE OF UNDERSTANDING
VALERIE GAGE
4739 BLACKBERRY HILL LN
PORT ORCHARD,WASHINGTON 98366
RE: GEOTECHNICAL REPORT
419 BEARCREEK—DEWATTO ROAD
BELFAIR,WASHINGTON
N470 29'37.81" W 122°48'57.84"
PARCEL 12309-31-90074
NOVEMBER 29,2018
Dear Valeria Gage:
Valeria Gage (client) hired All American Geotechnical, Inc. (AAG) in October 2018 to prepare a
geotechnical report for a proposed single-family residence off Bearcreek-Dewatto Road north of Belfair,
Washington. This is in keeping with a requirement of Mason County in the Critical Areas Ordinance in
accordance with the Submittal Checklist For a Geotechnical Report. The site had but a few trees on the
edges of the area to be developed. Proposed improvements include the replacement manufactured home
and extending the parking area to accommodate a larger recreational vehicle.
As per client request, we have conducted a soils exploration, foundation evaluation, and slope stability
analysis for the above-mentioned parcel. The results of this investigation, together with our
recommendations, are to be found in the following report. We have provided two copies for client
review and distribution.
We appreciate this opportunity to be of service to you and we look forward to working with you in the
future. If you have any questions concerning the above items,the procedures used, or if we can be of any
further assistance please call us at the phone number listed below.
Respectfully Submitted,
°t ash; ALL AMERICAN GEOTECHNICAL,INC.
��a r
s/
Engin"nn9 G�ologyt t
�.0 2439 �5 Curtis D. Cushman, L.G., L.E.G.
sod Geoff° Senior Engineering Geologist
Curtis Dean Cushman
AAG 18-082 8947 Buttonwood Lane NE,Olympia, WA 98516 3
Phone#: (360)491-5155 Cell#: (360)481-6677
. ALL AmimtcAN GRoTEcHNICAL
TABLE OF CONTENTS
' SCOPE OF UNDERSTANDING 3
INTRODUCTION 6
1) SITE CONDITIONS 7
' SURFACE CONDITIONS 7
' A) SITE GEOLOGY 8
B) SOIL TYPES 8
C) GROUND WATER CONDITIONS 9
' D) UPSLOPE GEOMORPHOLOGY 10
E) UPSLOPE WATERBODIES AND WETLANDS 10
F) LANDSLIDE ACTIVITY 10
2) SITE PLAN 10
3) EXPLORATORY HOLES OR PROBES 10
4) PROPOSED DEVELOPMENT 10
5) CROSS SECTION 10
6) SLOPE STABILTY ANALYSIS 10
' GEOSEISMIC SETTING 12
LATERAL EARTH PRESSURES 13
7) RESTRICTIONS 13
A) PLACEMENT OF DRAINAGE FEATURES 13
B) PLACEMENT OF SEPTIC DRAIN FIELDS 13
1 C) PLACEMENT OF COMPACTED FILLS AND FOOTINGS 13
RECOMMENDATIONS FOR SITE PREPARATION 13
RECOMMENDATIONS FOR STRUCTURAL FILL 14
I RECOMMENDATIONS FOR SUITABILITY OF ONSITE SOILS AS FILL 14
D) BUFFERS 14
E) SETBACKS 14
8) CLEARING AND GRADING PLAN 14
9) EROSION CONTROL PLAN 15
10) ON AND OFFSITE IMPACTS 15
11) FINAL DEVELOPMENT CONDITIONS 15
12) STRUCTURAL MITIGATION 15
13) SITE PLAN 15
CONCLUSIONS AND RECOMMENDATIONS 16
PROVISIONS 16
CONTRACTORS ARE RESPONSIBLE FOR SITE SAFETY ON THEIR OWN CONSTRUCTION PROJECTS 16
READ THESE PROVISIONS CLOSELY 16
REFERENCES 18
AAG 18-082 8947 Buttonwood Lane NE,Olympia, WA 98516 4
Phone#: (360)491-5155 Cell#: (360)481-6677
I
ALLAMMCANGNOT&CMICAL
I
I
APPENDIX 20
' 2009 AASHTO DESIGN SPECIFICATIONS 21
2015 IBC DESIGN SPECIFICATIONS 22
I
SLOPE MODELS 23
I
STATIC MODEL A-A'LINE 23
DYNAMIC MODEL A-A'LINE 24
FIGURES 25
FIGURE 1.VICINITY MAP 25
I FIGURE 2.SITE PLAN 26
FIGURE 3. EROSION CONTROL NOTES 27
I
I
I
I
1
I
I
I
I
I
1
I
I
I
I
1
I
AAG18-082 8947 Buttonwood Lane NE,Olympia,WA 98516 5
Phone#: (360)491-5155 Cell#: (360)481-6677
I
I
i
ALL AmmcAN Gr&oTiErnrn iL
i
i INTRODUCTION
This report summarizes the results of our geotechnical consulting services for the residential site herein
described. The proposed residence is located north of Belfair, Washington. The site is accessed from
i State Highway 3 via NE Old Belfair Highway which connects to the Bearcreek-Dewatto Road. The
residential site is located on a shared private road south of the Bearcreek-Dewatto Road. The site is
approximately 4 direct miles north of downtown Belfair. The location of the site is shown relative to the
surrounding area on the Vicinity Map, Figure 1.
I
The parcel is a 1.2 acre irregular triangle, long to the north-south. The residential building site will be on
a relatively flat area near the north end of the lot where there was a mobile home to be replaced by a new
manufactured home.
I
Our understanding of the project is based on our discussions with the client's brother and information
sent to us from AHC Homes. In general, this will be a project involving replacing one manufactures
I residence with another. An area for RV parking is also proposed. The approximate layout of the site is
I shown on the Site Plan, Figure 2.
I
I Figure 2 shows the footprint of the proposed manufactured home and the RV parking site. Figure 2 also
shows the presence of a retaining wall proposed for the RV site as well as the steeper terrain to the
I southeast of the site.
I
I The purpose of our services is to evaluate the surface and subsurface conditions at the site in order to
satisfy the requirements of the Mason County Critical Areas Ordinance, and as a basis for providing
I geotechnical recommendations and design criteria for the project. All American Geotechnical is
I therefore providing geotechnical services for the project. Specifically, our scope of services for this
I project includes the following as needed:
I 1. A review of the available geologic, hydrogeological and geotechnical data for the site
I area.
2. A geologic reconnaissance of the site area and surrounding vicinity.
I 3. Investigation and identification of subsurface conditions at the site by characterizing the
exposed soil, reviewing published well logs, and sampling.
4. Comparison of site to published geologic maps, previous field investigations, and open
I file reports. Inspection of aerial photography is to determine the geomorphology of the
I site.
5. Evaluation of the landslide, erosion, and seismic hazards at the site per the Mason County
Critical Areas Ordinance regulations(as of January 1, 2007).
6. Building setbacks determined from static and dynamic slope stability modeling.
7. Geotechnical recommendations for site grading including site preparation, subgrade
preparation, fill placement criteria (including hillside grading), temporary and permanent
cut and fill slopes, drainage, and typical erosion control measures.
The most critical slope is on the east side of the proposed building site. This is a slope that is greater than
40%with a height over 10 feet. Therefore, Mason County requires that a geotechnical report be prepared
in accordance with the Critical Areas Ordinance.
AAG 18-082 8947 Buttonwood Lane NE, Olympia, WA 98516 6
Phone#: (360)491-5155 Cell#: (360)481-6677
I
1) SITE CONDITIONS
SURFACE CONDITIONS
The proposed building site is on a natural flat on a continuous slope descending from the northwest to the
southeast. This natural platform is suitable for a single-family dwelling. Much of the area has been
cleared, notably the pre-existing site for the residence.
Blaise Jelinek E.I.T. of AAG visited the site for this project on November 5, 2018; at which time, Mark
Gage, the brother of the client; was on site and explained the proposed improvements. The purpose of
any site visit is to physically observe the property and adjacent properties in order to identify any
recognized geologic conditions. A site map is prepared identifying features of the property. Surficial
exploration and inspection of subsurface samples were done. Visual observations were documented and
site-specific features were mapped.
The proposed development is on a platform underlain by glacial deposits. There is no extreme
topography above the project site as it rises toward a north-south drumlin-like glacial ridge 1200 feet or
more to the northwest part of which is an active aggregate operation. No surficial water is present. No
active erosion was seen.
{
The LiDAR map to the right FIN.
(from the Washington
Interactive Geologic Map
portal) is a bare earth
depiction of the property. The "
blocky terrain is
depositional/erosional in
nature and shows no active
landsliding.
The original mobile home has f j
been removed from the site. X .
The upper area of the site that -
will be developed has but a
few trees on the edges of the
graded area to the south and
west. The surface of the
graded area is mostly gravel
with sparse grass. The slope to the west has low growth plants and volunteers. The lower portion of the
parcel to the west is forest.
The site is too far inland to be mapped on the DOE Coastal Zone Atlas map.
The LHA on the slope above the site of the proposed replacement mobile home is limited in height. The
proposed site is located within the lower 50 foot vegetation buffer as seen on Figure 2, but as this is
AAG 18-082 8947 Buttonwood Lane NE,Olympia, WA 98516 7
Phone#: (360)491-5155 Cell#: (360)481-6677
1
ALL Ammcm GrmucaNICAL
entirely cleared of old-growth and is currently vegetated with domestic plants and juvenile trees,
development of the manufactured home inside tis buffer is acceptable.
The slope below the site is defined as a landslide hazard area(LHA). The 50' vegetation buffer from this
LHA will not impinge upon the development of the new manufactured home.
A) SITE GEOLOGY
The site is situated within the Puget Sound glacial province. The existing topography, as well as much of
the sedimentary deposits and surficial subsurface soils in the area, is the result of the most recent Vashon
stade (stage) of the Fraser glaciation that occurred between about 9,000 and 11,000 years ago, and
weathering and erosion that has occurred since. A description of the surficial soils is included in the
"Site Soils" section of this report, below. In general, the deposits are composed of glacial material with
the soils directly derived from this material.
The Geologic Map of the Belfair 7-5-minute Quadrangle, Mason, Kitsap, and Pierce Counties,
Washington Open File 2009-07 by Polenz, Michael, and others (2009), published by the Washington
Division of Geology and Earth Resources, maps the site as follows. The description below is ordered
with the younger deposits above the older.
Qgic
Vashon glacial ice-contact deposits—Sand, gravel, lodgment till, and flow till; minor silt and
clay beds; tan to gray; variably sorted; loose to compact; massive to well stratified; locally
includes over-steepened beds that typically reflect sub-ice flow, but their dip may, along with
small-scale shears, also have developed as collapse features or due to glaciotectonic and tectonic
deformation;formed in the presence of meltwater alongside ice, generally toward the end of the
glaciation, and is thus commonly accompanied by stagnant-ice features, such as kettles and less-
orderly hummocky topography, eskers (also separately mapped as subunit Qge), and subglacial
or subaerial outwash channels.
This description is characteristic of the site and the overall depositional area. Samples taken indicated the
soil to be very gravelly sands and very gravelly loamy sands. .
B) SOIL TYPES
The soil (from the USDA WSS) at the site is:
Ek—Everett very gravelly sandy loam, 15 to 30 percent slopes
Map Unit Setting
• National map unit symbol: 2t62c
• Elevation: 30 to 900 feet
• Mean annual precipitation: 35 to 91 inches
• Mean annual air temperature: 48 to 52 degrees F
• Frost free period: 180 to 240 days
AAG 18-082 8947 Buttonwood Lane NE,Olympia, WA 98516 8
Phone#: (360)491-5155 Cell#: (360)481-6677
ALL AMERICAN GrwncHNICAL
Map Unit Composition
• Everett and similar soils: 80 percent
• Minor components: 20 percent
• Estimates are based on observations, descriptions, and transects of the mapunit.
Description of Everett
Setting
• Landform: Karnes, eskers, moraines
• Landform position (two-dimensional): Backslope
• Landform position (three-dimensional): Side slope
• Down-slope shape: Convex
• Across-slope shape: Convex
• Parent material: Sandy and gravelly glacial outwash
Typical profile
• Oi - 0 to I inches: slightly decomposed plant material
• A - I to 3 inches: very gravelly sandy loam
• Bw-3 to 24 inches: very gravelly sandy loam
• CI -24 to 35 inches: very gravelly loamy sand
• C2- 35 to 60 inches: extremely cobbly coarse sand
Properties and qualities
• Slope: 15 to 30 percent
• Depth to restrictive feature: More than 80 inches
• Natural drainage class: Somewhat excessively drained
• Capacity of the most limiting layer to transmit water (Ksat): High(1.98 to 5.95 in/hr)
• Depth to water table: More than 80 inches
• Frequency offlooding: None
• Frequency of ponding: None
• Available water storage in profile: Low(about 3.2 inches)
This description well describes the soils seen on site. The surficial soil at the residential site were likely
fully removed when the original mobile home was installed. Any further work will be in deeper soil,
which is the same as the glacial deposit.
C) GROUND WATER CONDITIONS
No surface water flow was observed on site. There was no evidence of springs on the slope.
AAG 18-082 8947 Buttonwood Lane NE,Olympia, WA 98516 9
Phone#: (360)491-5155 Cell#: (360)481-6677
ALL AminuN GEOTECHNiCAL
D) UPSLOPE GEOMORPHOLOGY
The slope rises in an irregular fashion to the aggregate quarry on the crest of a drumlin over 1200 feet to
the northwest. This area, under active exploitation, in on the other side of the Bearcreek-Dewatto Road
from the client property and poses no hazard to the site.
E) UPSLOPE WATERBODIES AND WETLANDS
There are none.
F) LANDSLIDE ACTIVITY
The only landslides on the quadrangle are a few minor ones mapped as Qls in Courtney Creek over a
half-mile to the southwest. Landslides of a minor size are also mapped in the headwaters of Hazel Creek
to the north, again well away from the client property.
2) SITE PLAN
The proposed location of the residential site is shown on Figure 2. The building envelope where this
construction is acceptable from a geotechnical sense is marked. .
3) EXPLORATORY HOLES OR PROBES
There were two soil excavations completed on the property. The soils encountered were very gravelly
sands and loamy sands.
4) PROPOSED DEVELOPMENT
Figure 2 shows the required features of. proposed construction, the boundaries of the hazard (LHA), and
associated buffers and setbacks.
5) CROSS SECTION
A cross-section along line A—A' is in the Appendix.
6) SLOPE STABILTY ANALYSIS
As noted above, there are no mapped landslides in the area. LiDAR shows no landslides in the area of
the proposed residence. There was no evidence of significant recent erosion observed onsite at the time
of our investigations.
In general, the undisturbed native soils of the site consist of a mixture of variable amounts of sand, silt,
and gravel. These soil materials are in a dense condition except where they have been disturbed by
AAG 18-082 8947 Buttonwood Lane NE,Olympia,WA 98516 10
Phone#: (360)491-5155 Cell#: (360)481-6677
ALL A r,&RI N GEoTEc'HNICAL
weathering activity and where they have been loosened by failure. Weathering, erosion, and the resultant
sloughing and shallow landsliding are natural processes that can affect steep slope areas. Instability of
this nature is typically confined to the upper weathered or disturbed zone, which has been disturbed and
has a lower strength; however, the planned setback should prevent harm to the residence caused by major
or minor slippages.
Following construction, encouraging vegetation and discouraging runoff from the steep slopes can reduce
erosion in steep slope areas such as this. Erosion control recommendations for the sloping areas are
provided in the"Erosion Control" section of this report.
17.01.100E5 (6) -- A description and results of slope stability analyses performed for both
static and seismic loading conditions. Analysis should examine worst-case failures. The
analysis should include the Simplified Bishop's Method of Circles. The minimum static
safety factor is 1.5, the minimum seismic safety factor is 1.1 and the quasi-static analysis
coefficients should be a value of 0.15.
Factors of safety were determined using the Bishop (semi-circular) method. The site was modeled
monolithically with information from the glacial unit described in the literature and as seen on-site. The
parameters used in this modeling were based on experience with the surroundings and the types of
materials encountered on site. A continuous load of 1200-lb per foot was placed across the intercept of
the proposed building envelope and the cross-sections.
Slope stability was modeled using the GALENA 6.1 program in both static and dynamic conditions (ca=
0.224). "Static" condition refers to an "as is" state of a given slope. "Dynamic" puts seismic
acceleration into the model for earthquake conditions. The factor for ground acceleration (ca) was
determined from the Peak Ground Acceleration from the USGS Seismic Design Maps, included in the
Appendix.
The soil was field identified as SP-SM Silty sand with gravel. These contain varying amounts of gravel
and larger clasts but overall the deposits are matrix-supported. This classification requires selecting
conservative values in the interests of safety.
The site was modeled as a monolithic unit, based upon available mapping The units were modeled using
the following soil parameters presented in Table 1. Geologic Modeling Values.
Table 1. Geologic Modeling Values
Geologic Unit Unit Weight Cohesion Phi Angle
Qgic-- Vashon Ice Contact Deposits 118 250 ;7
Two analysis were calculated along the one cross-section, itemized on Table 2. Modeling Parameters
and Findings. The Analysis Number corresponds to the output presented on pages 23-24. The slope
was modeled based upon observations, field measurements, and available mapping. Initial positions
AAG 18-082 8947 Buttonwood Lane NE, Olympia, WA 98516 11
Phone#: (360)491-5155 Cell#: (360)481-6677
i
ALL A r,&RICAN Gm'[` cHINICAL
I
were selected based upon the placement of the structure and the shape of the slopes. The initial points
were varied over the analysis range indicated; with 50 different positions tested across these ranges. A
total of 125,001 calculations were performed for analysis 1 though 4. Calculated Factors of Safety are
presented in Table 2.
I
I
Table 2. Modeling Parameters and Findings
I
Analysis Load Across Analysis Initial Positions(Analysis Range) Configuration~JFactor of
Number Building Envelope Type Lower U r Radius Auialvzed Safety
I
Cross-Section A-A'
...... ...... ........... ............ti............. ............ti............................ .
I Analysis_I_.__ _-- 1200# :Static :80(]00} :415(100) :365(40) : 125,001 : 2.23
Analysis 2 : ___-___1200t1_______Dynamic :80(100) ___:415000)__365(40)___�_____125.001_ : _ 1.25
-- ------a• ---- - -�--------- ------
I
I Under static conditions, the slopes generally did not show susceptibility to deep-seated failure that would
cause damage to the proposed residence. Under dynamic loading (Ca=0.224), the computations
demonstrated that the slope is safe and not susceptible to a deep-seated movement.
These calculated Factors of Safety (FoS) meet the requirements set forth by Mason County for static
conditions (1.50) and meet the requirement(1.10) for dynamic loading scenarios. The site appears stable
based on our slope models representing critical slopes at the subject site.
As the values inputted were selected to be as conservative as possible,the FoS are likely higher.
I
The Liquefaction Susceptibility Map of Mason County, Washington by Palmer, Magsino, Poelstra,
Bilderback, Folger, and Niggemann (September 2004) maps the site area as having a Very Low
I liquefaction potential.
I
i The Site Class Map of Mason County, Washington by Palmer, Magsino, Bilderback, Poelstra, Folger, and
Niggemann (September 2004) maps the site area as site Class. Site class C is a very stiff soil or soft
rock.
GEOSEISMIC SETTING
According to the Seismic Zone Map of the United States contained in the 2006 International Building
Code (IBC), the project site is located where the maximum spectral response acceleration is 40 percent of
gravity(g).
We recommend following seismic factors for design purposes.
• Site Class: C (Soft Rock)
• Spectral response acceleration, short period(SMs): 1.386g(Fa= 1.05)
• Spectral response acceleration, 1-second period(Smi): 0.862g(F,= 1.55)
• Peak Ground Acceleration(PGA) 0.408g
AAG 18-082 8947 Buttonwood Lane NE,Olympia, WA 98516 12
Phone#: (360)491-5155 Cell#: (360)481-6677
ALL AmEkicAN GmTEcHNICAL
LATERAL EARTH PRESSURES
Lateral loads may be resisted by friction on the bases of footings and floor slabs and as passive pressure
on the sides of footings. An allowable coefficient of friction of 0.40 may be used to calculate friction
between the concrete and the underlying native soil. We recommend the following be used to determine
the lateral earth pressures considering the onsite Silty sand with gravel(SP-SM)
• 0 (soil friction angle) 37 degrees
• Ko(at rest earth pressure coefficient) 0.40
• Ka(active earth pressure coefficient) 0.25
• Kp (passive earth pressure coefficient) 4.02
7) RESTRICTIONS
A) PLACEMENT OF DRAINAGE FEATURES
The geology and topography of the site indicates the flow from the residence may be directed away from
the residence by downspouts as long as these drain away from the slope. No surface water and no storm
discharge of any sort should be directed toward the lower slope.
B) PLACEMENT OF SEPTIC DRAIN FIELDS
The septic drainfield is located as on Figure 2.
C) PLACEMENT OF COMPACTED FILLS AND FOOTINGS
RECOMMENDATIONS FOR SITE PREPARATION
All areas to be excavated should be cleared of deleterious matter including debris, duff, and vegetation. .
Any material that is excavated may be stockpiled and later used for erosion control and landscaping.
Otherwise, deleterious material must be removed from the residential site. No dumping should take place
in the setback or LHA.
If demonstrated to be acceptable, the sand/gravel till material on site may be suitable for re-use as
structural fill.
Where placement of fill material is required, the exposed subgrade areas should be compacted to a firm
and unyielding surface prior to placement of any fill. Over-excavation in any building area should be
backfilled with structural fill, compacted to the density requirements described in the "Structural Fill"
section of this report.
AAG 18-082 8947 Buttonwood Lane NE,Olympia, WA 98516 13
Phone#: (360)491-5155 Cell#: (360)481-6677
ALL mERICAN GEOTECHNICAL
RECOMMENDATIONS FOR STRUCTURAL FILL
All fill material should be placed as structural fill. In general, the structural fill should be placed in
horizontal lifts of 8 inches to allow adequate and uniform compaction of each lift. Fill should be
compacted to at least 95 percent of MDD (maximum dry density as determined in accordance with
ASTM D-1557)to grade.
The final appropriate lift thickness will depend on the fill characteristics and compaction equipment used.
Material placed for structural fill should be free of debris, organic matter, trash, and cobbles greater than
6 inches in diameter. The moisture content of the fill material should be adjusted as necessary for proper
compaction.
RECOMMENDATIONS FOR SUITABILITY OF ONSITE SOILS AS FILL
Onsite soils may be considered for use as structural fill only if industry standards are satisfied. Fill
material requirements are found on page 9-26 to 9-30 of the WSDOT Standard Specifications 2010. In
general, a native soil (sand, silt, and gravel) encountered on a site must have less than 10 percent fines
(material passing the US No. 200 sieve) to be suitable for use as structural fill. For this site, a sample for
laboratory testing would be required.
D) BUFFERS
The residential site as currently planned is within the 50 foot vegetation buffer. As this is a replacement
for the current mobile home, and the area was already cleared,this is acceptable.
The lower LHA and buffers will not be affected by the proposed manufactured home or other
development.
E) SETBACKS
The replacement of the current mobile home with the manufactured home in keeping with the envelope
of Figure 2 will satisfy the geotechnical setbacks.
8) CLEARING AND GRADING PLAN
The primary cutting and grading of the site has been done in the area because of the previous on-site
residence. "No Disturb"zones will not be required.
Further work will be to develop the footings of the structures and improve the road. This is minor in
scope. No major grading shall occur. All job site safety issues and precautions are the responsibility of
the contractor providing services and/or work.
AAG 18-082 8947 Buttonwood Lane NE,Olympia, WA 98516 14
Phone#: (360)491-5155 Cell#: (360)481-6677
1
ALL AMERICAN GEoncumcAL
I
I
9) EROSION CONTROL PLAN
1
It is our opinion that the potential erosion hazard of the site is not a limiting factor for the proposed
1 developments. Removal of natural vegetation has been done at the time of timbering and clearing of the
I residential building site. Revegetation as needed should occur immediately following construction if any
1 is required. Any hazard trees may be removed with the roots left in place if possible.
I IThe possibility of down-slope contamination is hi Yunlikel if proper control methods are employed.
If there is little or no earth-moving, then simple swales or berms may be enough. If there is more, then a
silt fence may be required. Work should be one under dry conditions as much as possible.
1 Straw, hay, or jute matting shall be used to cover exposed soils until permanent vegetation is established.
I The road cut itself should be protected against the rains and revegetation should be a part of the overall
I project. All other denuded slopes should be seeded as soon as practical to facilitate the development of a
I protective vegetative cover, or otherwise protected.
I A revegetation plan should not be required but may be considered. Densely rooted evergreen shrubs are
preferable than tree species on slopes greater than 15% gradient. Tall trees may become unstable in wet
soils under high wind conditions. In general, undeveloped steep sides should be left in a natural
condition.
Please see the erosion notes on Figure 3. This shows the recommended development of a silt fence if
needed. The notes on the generic drainage tightline do not apply.
10) ON AND OFFSITE IMPACTS
There should be no notable on or offsite impacts if the project is completed according to the
recommendations of this report and in accordance with all regulations and to the highest standards and
practices of the building contractor.
11) FINAL DEVELOPMENT CONDITIONS
All final conditions will follow the design by the Engineer of Record and compliance with all regulatory
agencies. If this and the above recommendations are followed, final development conditions will be
achieved.
12) STRUCTURAL MITIGATION
The older mobile home is already removed. The pad may be upgraded.
13) SITE PLAN
Please see Figure 2.
i
AAG 18-082 8947 Buttonwood Lane NE,Olympia, WA 98516 15
Phone#: (360)491-5155 Cell#: (360)481-6677
l�l ALL A RicAN C rwncHNIC.,AL
1.
CONCLUSIONS AND RECOMMENDATIONS
Based on the results of our site reconnaissance, subsurface observations, and our experience in the area, it
is our opinion that the site is suitable for the proposed project. The construction will not affect the
adjacent slopes. Proper drainage control measures will reduce or eliminate the potential for erosion in
( this area.
Construction may be performed under most weather conditions. We recommend that earthwork be
Cundertaken during favorable weather conditions.
Revegetation should be done as per recommendations in the text, above.
I
PROVISIONS
We have prepared this report for the exclusive use of Valeria Gage and her authorized agents for the
proposed residence on the Bearcreek-Dewatto Road in Mason County, Washington. Site inspections,
research, and mapping have culminated in this report. This report is intended to meet the requirements of
' the Mason County Critical Areas Ordinance. This report does not specify setbacks for: line-of-sight
' setbacks, FWHCA setbacks, eagle tree setbacks, wetland setbacks, or property line setbacks. Within the
limitations of scope, schedule and budget, our services have been executed in accordance with generally
accepted practices in the field of geotechnical engineering in this area at the time this report was
prepared. No warranty or other conditions, expressed or implied, should be understood.
Clients and property owners must understand that, despite any calculated Factors of Safety, surficial
failure and landslides can and do occur on steep slopes. The property owners should monitor the stability
of the site following construction.
Moreover, acceptable Factors of Safety do not guarantee there cannot be failures. It is the responsibility
of the property owners association to understand that there are always risks in building on or near steeply
sloped areas.
CONTRACTORS ARE RESPONSIBLE FOR SITE SAFETY ON THEIR OWN CONSTRUCTION PROJECTS
Our geotechnical recommendations are not intended to direct the contractor's procedures, methods,
schedule or management of the work site. The contractor is solely responsible for job site safety and for
managing construction operations to minimize risks to onsite personnel and to adjacent properties.
READ THESE PROVISIONS CLOSELY
Some clients, design professionals, and contractors may not recognize that the geoscience practices
(geotechnical engineering or geology) are far less exact than other engineering and natural science
disciplines. This lack of understanding can create unrealistic expectations that could lead to
disappointments, claims and disputes. All American Geotechnical includes these explanatory
"limitations"provisions in our reports to help reduce such risks.
I
AAG18-082 8947 Buttonwood Lane NE,Olympia, WA 98516 16
Phone#: (360)491-5155 Cell#: (360)481-6677
I
I
ALL AM CAN GROTWRNICAL
The equipment, techniques and personnel used to perform an environmental study differ significantly
from those used to perform a geotechnical or geologic study and vice versa. For that reason, geotechnical
engineering or geologic reporting does not usually relate any environmental findings, conclusions or
recommendations; e.g., about the likelihood of encountering underground storage tanks or regulated
contaminants. Similarly, environmental reports are not used to address geotechnical or geologic concerns
regarding a specific project.
1
1
1
1
' AAG 18-082 8947 Buttonwood Lane NE, Olympia, WA 98516 17
' Phone#: (360)491-5155 Cell#: (360)481-6677
1
1
I
ALL AMERICAN GEOTECKNICAL
REFERENCES
MAPS
1
DeLorme 3-D TopoQuads(2002),Source Data USGS,Yarmouth,Maine.
Dragovich, Logan, Walsh, and Schasse(2002), Geological Map of Washington—Northwest Quadrant(Geological Map GM-
50),published by Washington State Department of Natural Resources.
I Palmer, Magsino, Poelstra, Bilderback, Folger, and Niggemann (September 2004), The Liquefaction Susceptibility Map of
Mason County, Washington, published by Washington State Department of Natural Resources.
I
Palmer, Magsino, Bilderback, Poelstra, Folger, and Niggemann (September 2004), The Site Class Map of Mason County,
Washington,published by Washington State Department of Natural Resources.
1
Polenz,K.,and others.,(2009),Geologic Map of the Belfair 7.S-minute Quadrangle, Mason, Kitsap, and Pierce Counties,
Washington;Washington State Department of Natural Resources Open File 2009-07.
I
Rogers, A. M., Walsh, T. J., Kockelman, W. J., and Priest, G. R. (1996), Map showing known or suspected faults with
quaternary displacement in the Pacific Northwest, published by U.S. Geological Survey OFR 91441-0, Plate 1,
I scale 1:2,000,000.
I
I PUBLICATIONS
I
I ASTM International(2005),Annual Book of Standards 2005, Section 4, Volume 4.08,published by ASTM International, West
Conshohocken,Pennsylvania.
I
International Code Council,Inc. (2006),2006 International Building Code,published by International Code Council,Inc.
I Kollmorgen Instruments Corporation (1994), Munsell Soil Color Charts (1994 Revised Edition), published by Macbeth
Division of Kollmorgen Instruments Corporation,New Windsor,New York.
I Ness, Fowler, Parvin(1960),The Soil Survey of Mason County, Washington, USDA Soil Conservation Service, in cooperation
with the United States Department of Agriculture, and Washington Agricultural Experimental Station, and the Soils
Conservation Service.
I
Parks, Neal, Koloski, Laprade, Molinari, Butler, and Lorentson (November 2006), Guidelines for Preparing Engineering
Geology Reports in Washington, published by Washington State Geologist Licensing Board,Olympia,Washington.
I
Prakash(1981),Soil Dynamics,Figure 6.3,page 173,published by McGraw-Hill,Inc.
►
I Sowers(1979),Introductory Soil Mechanics and Foundations:Geotechnical Engineering,Macmillan Publishing Co.,Inc.
1
I
I
1
I
I
I
i AAG 18-082 8947 Buttonwood Lane NE, Olympia, WA 98516 18
i
Phone#: (360)491-5155 Cell#: (360)481-6677
i
i
ALL AMERICAN GEO TECHNIC L
WEBSITES
Mason County Government Information Services
(http://www.co.mason.wa.us)
Mason County Codes,Ordinances,and Regulations
(http://www.co.mason.wa.us/code)
Slope Stabilization Erosion Control Using Vegetation A Manual of Practice for Coastal Bluff
(http://www.ecy.wa.govibiblio/9330.html)
Vegetation Management Guide for Puget Sound Bluff Property Owners
(http://www.ecy.wa.gov/biblio/9331.html)
United States Department of Agriculture Natural Resource Conservation Service
(http://soildatamart.nres.usda.gov)
Washington Administrative Code
(http://apps.leg.wa.gov/wac/)
Washington Department of Ecology
(http://apps.ecy.wa.gov/welllog)
(https:Hfortress.wa.gov/ecy/coastalatlas/viewer.htm)
AAG18-082 8947 Buttonwood Lane NE, Olympia, WA 98516 19
Phone#: (360)491-5155 Cell#: (360)481-6677
ALL AMERICAN GEOTECHNICiL
1
APPENDIX
USGS Seismic Design Specifications
Slope Models
Figure 1. Vicinity Map
Figure 2. Site Plan
Figure 3. Erosion Control Notes
r
r
r
r
r
r
r
r
r
r
r
r
AAG18-082 8947 Buttonwood Lane NE,Olympia, WA 98516 20
Phone#: (360)491-5155 Cell#: (360)481-6677
r
1
1
ALL AmERICAN GrmnicnNICAL
' 2009 AASHTO DESIGN SPECIFICATIONS
MUM Design Maps summary Report
' User—Specified Input
' Report Title Valerie Gage
Mon November 12,2018 12:43:34 UTC
Building Code Reference Document 2009 AASHTO Guide Specifications for LRFD Seismic Bridge Design
(which utilizes USGS hazard data available in 2002)
Site Coordinates 47.493820N, 122.818°W
Site Soil Classification Site Class C - "Very Dense Soil and Soft Rock"
' Risk Category I/II/III
A Pon
aS WG OR 14 VAL
TOM
Ito SrATY0 N BASE
a
r b *,� ., .. `r�� • Rf MERTON
�,. .. I NATIONA L }
tood A►APORT
1i
vas
rAt
�i ,
r USGS—Provided Output
r
r PGA = 0.447 g A. = 0.447 g
Dean Response Spectrum
r S, = 0.988 g Sos = 0.993 g 1 1
S, = 0.351 g Sp, = 0.509 g
o.+o
OAD
o�o
y oro
• 0M
v:
0A0
030
0M
0.10
r om
r UAl/ U.3) UAU ULU ,Mi li 1.] I.L Ih IM _i r
Period,T Iseel
Although this information is a product of the U.S.Geological Survey,we provide no warranty,expressed or implied,as to the accuracy of
the data contained therein.This tool is not a substitute for technical subject-matter knowledge.
AAG 18-082 8947 Buttonwood Lane NE, Olympia, WA 98516 21
Phone#: (360)491-5155 Cell #: (360)481-6677
I
I
I�
I
2015 IBC DESIGN SPECIFICATIONS
1
U,%S Design Maps summary Report
User-Specified Input
I Report Title Valerie Gage
Mon November 12,2018 12:42:27 UTC
1 Building Code Reference Document 2012/2015 International Building Code
r (which utilizes USGS hazard data available in 2008)
Site Coordinates 47.493820N, 122.818OW
Site Soil Classification Site Class C - "Very Dense Soil and Soft Rock"
I Risk Category I/11/III
BREUER D1NNEX
aAW5os NAVAL
NAL h
STADM SUBM�R!Nf
BR�IFRTON BASF
1
1 -
I 1
I � �9�f,IERTON
NATIONA L
AIRPORT
I vas
I
I USGS-Provided Output
I
SS = 1.498 g S,75 = 1.498 g SDs = 0.998 9
S, = 0.592 g S., = 0.769 g SDI = 0.513 g
Fur information on how the SS and S1 values above have been calculated from probabilistic (risk-targeted)and
deterministic ground motions in the direction of maximum horizontal response, please return to the application and
select the"2009 NEHRP"building code reference document.
I
I 111CF t Response Spectrum Ueslip Response Spectrum
ILS 14
I!S 04
1 1 J Ors
„,i n.]i iJ,i i,bi A Illy 1 T I.In INt IMF ?i1 11„ i, J, i,Yr iib iifi Ir, I.]i I.Y Ib IMF .
Peril,T(swo Period,T twe
Although this information is a product of the U.S.Geological Survey,we provide no warranty,expressed or implied,as to the accuracy of
the data contained therein.This tool is not a substitute for technical subject-matter knowledge.
AAG 18-082 8947 Buttonwood Lane NE, Olympia, WA 98516 22
I Phone#: (360)491-5155 Cell#: (360)481-6677
I
I
ALL A ERICAN GrwTECHNICAL
I'-
SLOPE MODELS
STATIC MODEL A-A'LINE
1
m
1 a
cV
1 t_n c6
0—'R U
C
O
m _ s a R C3
N
1 fig_ � � m �
1 U ti
I �
I
1 �
I
1 �
I
1 g
v
1
c�
I
1
0
0
Q I
1
Q �
cu
Q ¢ �(D U t4
1t 59 S ui c7 �n a
AAG 18-082 8947 Buttonwood Lane NE,Olympia, WA 98516 23
1 Phone#: (360)491-5155 Cell#: (360)481-6677
I
' ALL AmEpticAN GE,OTECHNICAL
1
I'
DYNAMIC MODEL A-A' LINE
tq 3
c" c
N
r � d � d
r
ig
t � y cn m C)
7S 3 a
Qc a W 4
r _ 4
cq
Ls
r
1 �
r g
r
r
r
� g
r
r �
r
r
r
a
a
r -
r o LL
r3
r Q
W Q � �
o Q E
r A
LZ
r AAG 18-082 8947 Buttonwood Lane NE, Olympia, WA 98516 24
r Phone#: (360)491-5155 Cell #: (360)481-6677
1
11 111 111 1/1
N
111111
J� g��l� Idf iV1�
IMP
1 111 111 111 111
I
ALL AMKPtcAN GwTEcHwAL
�'• FIGURE 2.SITE PLAN
I
1
r
C
1
r
1
1
r
r
1
I
1
1
1
1
I
1
1
r
1
1
1
1
1
1
1
►
1
1
1
1 AAG18-082 8947 Buttonwood Lane NE,Olympia, WA 98516 26
1 Phone#: (360)491-5155 Cell#: (360)481-6677
1
GEO Zo I �b- 000le
Mason County Review Checklist
for a Geotechnical Report
Instructions:
This checklist is intended to assist Staff in the review of a Geotechnical Report. The Geotechnical Report is reviewed
for completeness with respect to the Resource Ordinance. If an item is found to be not applicable, the Report should
explain the basis for the conclusion. The Report is also reviewed for clarity and consistency. If the drawings,
discussion, or recommendations are not understandable, they should be clarified. If they do not appear internally
consistent or consistent with the application or observations on site, this needs to be corrected or explained. If
resolution is not achieved with the author, staff should refer the case to the Planning Manager or Director.
Applicant's Name: V OL I e v;-c-,
Permit#: 0 t 07A Parcel#: 12�bOa1- 31- 9 OV-1 4-
Date(s) of the Document(s) reviewed: 2- 3 t-qD
1. (a) A discussion of general geologic conditions in the vicinity of the proposed development,
OK? ✓ Comment:
(b) A discussion of specific soil types
OK? ✓ . Comment:
(c) A discussion of ground water conditions
OK? ✓ Comment:
(d) A discussi n of the upslope geomorphology
OK? ✓ Comment:
(e) A discussion of the location of upland waterbodies and wetlands
OK? ✓ Comment:
(f) A discussion of history of landslide activity in the vicinity, as available in the referenced maps and records
OK? ✓ Comment:
2. A site plan that identifies the important development and geologic features.
OK? ✓ Comment:
3. Locations and logs of exploratory holes or probes.
OK? Comment:
4. The area of the proposed development, the boundaries of the hazard, and associated buffers and setbacks shall
be delineated (top, both sides, and toe)on a geologic map of the site.
OK? ✓Comment:
5. A minimum of one cross section at a scale which adequately depicts the subsurface profile, and which
incorporates the details of proposed grade changes.
OK? '� Comment:
6. A description and results of slope stability analyses performed for both static and seismic loading conditions.
Analysis should examine worst case failures. The analysis should include the Simplified Bishop's Method of
Circles. The minimum static safety factor is 1.5, the minimum seismic safety factor is 1.1 and the quasi-static
analysis coeffients should be a value of 0.15.
OK?,_Comment:
7. (a) Appropriate restrictions on placement of drainage features
OK? `/ Comment:
(b) Appropriate restrictions on placement of septic drain fields
OK?—i,Comment:
(c) Appropriatp restrictions on placement of compacted fills and footings.
OK? J Comment:
Page 1 of 2 Form Effective June 2008
(d) Recommended buffers from the landslide hazard areas shoreline bluffs and the tops of other slopes.
OK? V Comment:
(e) Recommended setbacks from the landslide hazard areas shoreline bluffs and the tops of other slopes.
OK? Comment:
8. Recommendations for the preparation of a detailed clearing and grading plan which specifically identifies
vegetation to be removed, a schedule for vegetation removal and replanting, and the method of vegetation
removal.
OK? Comment:
9. Recommendations for the preparation of a detailed temporary erosion control plan which identifies the specific
mitigating measures to be implemented during construction to protect the slope from erosion, landslides and
harmful construction methods.
OK? ✓ Comment:
10. An analysis of both on-site and off-site impacts of the proposed development.
OK? `� Comment:
11. Specifications of final development conditions such as, vegetative management, drainage, erosion control, and
buffer widths.
OK? ✓ Comment:
12. Recommendations for the preparation of structural mitigation or details of other proposed mitigation.
OK? Comment:
13. A site map drawn to scale showing the property boundaries, scale, north arrow, and the location and nature of
existing and proposed development on the site.
OK? ✓ Comment:
Are the Documents signed and stamped? By whom?
License#: 24a01, License type: I _t e*K--3s kE-r, C-T rec,I ocJ, s
FIRST REVIEW Ef Approved ❑ Need more info.
If not approved, what is the next action/recommendation for further action?
Reviewed by on Z I Time spent in review:7D In�
SECOND REVIEW/ UPDATE ❑ Approved ❑ Need more info.
Reviewed by on Time spent in second review:
THIRD REVIEW/UPDATE ❑ Approved ❑ Need more info.
Reviewed by on . Time spent in third review:
Disclaimer. Mason County does not certify the quality of the work done in this Geotechnical Report.
Page 2 of 2 Form Effective June 2008
NOTES I '
This is not a survey. This map %
/ I /
is a presentation of -
information from county,state,(' ,' /' i ; ,•-' ,,' ,
Ir and federal agencies,client
provided information'and
so pt �.
onsite observations;for —- --------
discussion purposes of the
report with which this map is included. /
101,
Site Geology
sting
Qgie V on glacial ice
co deposits FPleistocene) y '
O
Site Soil' '' __ _ ' ,' oposed Drain
SCALE 1'=60'
,11ai't�Everett v gravelly sand loam, pose RV
4 Parking 8�---- o m b .o
15 to 3 ercent slops 5° efaming Wall
iltFencc
,' ,'
, / , tl Needed
of Wash
,'gyp Q• ,%'
�C 2439
ed Goo I
Cu Deah Cu man '1• '
All American Geotechnical, Inc. Project Drawn By: Site Plan Permit Number: Parcel Number: 12309-31-90074 Figure
8947 Buttonwood Lane NE Number: B WJ Proposed Single-Family Home
Olympia,Washington 98516 AAG18-081 11/28/2018 Belfair, WA Applicant Name: Valerie Gage 419 NE Bearcreek Dewatto Rd 2
PP Site Address:
" FILTER FABRIC MATERIAL 60"WIDE ROLLS
USE STAPLES OR WIRE RING TO ATTACH
FABRIC TO WIRE
2'X2'X14 GAUGE WIRE
FABRIC OR EQUIVALENT
GENERAL EROSION CONTROL NOTES:
2'-W : : : 1. EROSION CONTROL MEASURES SHALL BE IN PLACE PRIOR TO THE
BEGINNING OF CONSTRUCTION. THE PROJECT ENGINEER AND THE COUNTY
s'-o /T\ ND SURFACE //,\��: : SHALL INSPECT AND APPROVE THE INSTALLATION OF 1/2 INCH MINIMUM DIAMETER STEEL ROD
EROSION CONTROL MEASURES PRIOR TO BEGINNING CONSTRUCTION. (STRAP)CLAMPED SECURELY TO PIPE
2'-6' _, --• • ,,, •- - - ----- -- -- -•:•:• .- 2. EROSION CONTROL MEASURES ARE NOT LIMITED TO THE ITEMS
6'MAX ON THIS PLAN. THE CONTRACTOR IS RESPONSIBLE FOR THE CORRUGATED TIGHTLINE 4 INCH
INSTALLATION AND MAINTAINANCE OF ALL EROSION CONTROL MEASURES. MINIMUM,6 INCH SUGGESTED
• • NO SILTATION OF EXISTING OR PROPOSED DRAINAGE FACILITIES 4iN7M
z i
SHALL BE ALLOWED. CARE SHALL BE TAKEN TO PREVENT MIGRATION
2"X4"WOOD POSTS,STANDARD OR BURY BOTTOM OF FILTER OF SILTS TO OFF SITE PROPERTIES. JOF
BETTER OR EQUAL ALTERNATE: MATERIAL IN 8"X12'TRENCH
ciN FFT
STEEL FENCE POSTS 3. THE CONTRACTOR SHALL MAKE DAILY SURVEILLANCE OF ALL EROSION C'
CONTROL MEASURES AND MAKE ANY NECESSARY REPAIRS OR ADDITIONS
TO THE EROSION CONTROL MEASURES. THE CONTRACTOR SHALL PROVIDE
ADDITIONAL EROSION CONTROL MEASURES AS DETERMINED NECESSARY
BY THE COUNTY INSPECTOR AND/OR THE PROJECT ENGINEER. FAILURE
FILTER FABRIC 6• TO COMPLY WITH ALL LOCAL AND STATE EROSION CONTROL �i ' ':.': • :`: i:`'?e:\ 'i ='w'
2"X2"X14 GAUGE WIRE REQUIREMENTS MAY RESULT IN CIVIL PENALTIES BEING LEVIED
FABRIC OR EQUIVALENT AGAINST THE CONTRACTOR AND/OR PROJECT OWNER. �fy'"a i—" :�iu' ` ='s` h� .'+': {�;•:
GROUND SURFACE 5'-0' 4. DURING THE WET SEASON(NOVEMBER TO MARCH)ALL DISTURBED SOILS ;,4•;_. �, r,�,.._ y 1,;.;.,,,.�i:,z�, ; t�.ti:;.gy;
SHALL BE STABILIZED WITHIN 48 HOURS AFTER STOP OF WORK. EROSION ` ,;,ty.-;;•?,�.,,.; = >,,.,;.z-
PROVIDE 3/4'-1 1!2'WASHE CONTROL MEASURES SHALL INCLUDE,BUT NOT BE LIMITED TO, �",":.�'.y. +^:i` »r�;+. `.h `•.' "
D `C::ti.>*'.•.^'h3.:;.:,>,,�'°...:,r.. :•. ;, :;.•.^`'`
COVERING THE EFFECTED AREA INCLUDING SPOIL PILES WITH �.=: 'ai+;+; :'•:'a: r .r •r.
GRAVEL BACKFILL IN TRENCH 12•
AND ON BOTH SIDES OF FILTER PLASTIC SHEETING,STRAW MATTING,JUTE MATTING,STRAW MULCH, xr ;Y•�; ;>:�.
FENCE FABRIC ON THE SURFACE g"MIN OR WOOD CHIPS. SEEDING OF THE DISTURBED AREAS SHALL TAKE
PLACE AS WEATHER PERMITS. TIGHTLINE ANCHORED WITH TWO,
2•X4•WOOD POSTS 5. ALL SEEDED OR SODDED AREAS SHALL BE CHECKED REGULARLY 3 FOOT REBAR LENGTHS OR BOLTS.
ALT:STEEL FENCE POSTS TO MAKE SURE VEGETATIVE COVERAGE IS COMLETE. AREAS SHALL BE
REPAIRED,RESEEDED,AND FERTILIZED AS REQUIRED.
FILTER FABRIC FENCE NOTES:
1. FILTER FABRIC SHALL BE PURCHASED IN A CONTINUOUS ROLL CUT TO 6. TRACKING OF SOIL OFFSITE WILL NOT BE ALLOWED. IF ANY SOIL IS
TRACKED ONTO A COUNTY STREET,IT SHALL BE REMOVED BY THE END
THE LENGTH OF THE BARRIER TO AVOID USE OF JOINTS. WHEN JOINTS
ARE NECESSARY,FILTER CLOTH SHALL BE SPLICED TOGETHER ONLY AT OF THAT WORKING DAY. ANY FURTHER TRACKING OF MUD WILL THEN
A SUPPORT POST WITH A MINIMUM 6-INCH OVERLAP AND SECURELY BE PREVENTED BY SWEEPING OR WASHING OF THE VEHICLES TIRES
FASTENED AT BOTH ENDS TO THE POST. BEFORE DRIVING ON A COUNTY STREET.
I
2. POSTS SHALL BE SPACED A MAXIMUM OF 6 FEET APART AND DRIVEN 7. NO MORE THAN 500 LF OF TRENCH ON A DOWNSLOPE OF MORE THAN 5
` SECURELY INTO THE GROUND(MINIMUM OF 30 INCHES). PERCENT SHALL BE OPENED AT ONE TIME.
3. A TRENCH SHALL BE EXCAVATED APPROXIMATELY 8 INCHES WIDE AND 12
INCHES DEEP ALONG THE LINE OF POSTS AND UPSLOPE FROM THE BARRIER. 8. EXCAVATED MATERIAL SHALL BE PLACED ON THE UPHILL SIDE OF TRENCHES. /Cy FLARE END SECTION
9. TRENCH DEWATERING DEVICES SHALL BE DISCHARGED IN A MANNER THAT WILL � QUARRY SPALL '`r•�'=".:::-,'••
4. WHEN STANDARD STRENGTH FILTER FABRIC IS USED,A WIRE MESH NOT ADVERSELY AFFECT FLOWING STREAMS. DRAINAGE SYSTEMS OR Z OR ENERGY _•:•;, ,:;:;` '=�-�ti ".' ':,��t -�?'
SUPPORT FENCE SHALL BE FASTENED SECURELY TO THE UPSLOPE SIDE z ::
OFFSITE PROPERTIES. DISPERSION DEVICE :t,rt<•;, , �• ='••J. _;:t.;•,x, :asa:: {t
OF THE POSTS USING HEAVY-DUTY WIRE STAPLES AT LEAST 1 INCH
LONG,TIE WIRES OR HOG RINGS. THE WIRE SHALL EXTEND INTO THE ,. _�:,,.„-:;.c:•.;;,:.;
TRENCH A MINIMUM OF 41NCHES AND SHALL NOT EXTEND MORE THAN 36 10.ALL STORM SEWER INLETS RECEIVING RUNOFF FROM THE PROJECT DURING
INCHES ABOVE THE ORIGINAL GROUND SURFACE. CONSTRUCTION SHALL BE PROTECTED SO THAT SEDIMENT-LADEN WATER GRASS-LINED SWALE SHOULD BE A
5. THE STANDARD STRENGTH FILTER FABRIC SHALL BE STAPLED OR WIRED
WILL BE FILTERED BEFORE ENTERING THE CONVEYANCE SYSTEM. MINIMUM ONE FOOT WIDE AT THE
_
TO THE FENCE AND 20 INCHES OF FABRIC SHALL BE EXTENDED 11.ALL OFF-SITE CATCH BASINS IMMEDIATELY ADJACENT TO THE SITE BOTTOM AND ONE FOOT DEEP WITH
INTO THE TRENCH. THE FABRIC SHALL NOT EXTEND MORE THAN 36 SHALL BE PROTECTED FROM SILTATION. A MAXIMUM SLOPE OF 5 PERCENT.
INCHES ABOVE THE ORIGINAL GROUND SURFACE. FILTER FABRIC SHALL
NOT BE STAPLED TO THE EXISTING TREES. MINIMUM 4 FEET
12.ALL DISTURBED AREAS SHALL BE SEEDED OR SODDED UPON COMPLETION LEVEL SECTION
6. WHEN EXTRA-STRENGTH FILTER FABRIC AND CLOSER POST SPACING IS OF WORK. THE CONTRACTOR SHALL BE RESPONSIBLE TO ENSURE THAT
USED,THE WIRE MESH SUPPORT FENCE MAP BE ELIMINATED,IN SUCH COMPLETE COVERAGE OF THE DISTURBED AREAS IS PROVIDED&THAT
A CASE,THE FILTER FABRIC IS STAPLED OR WIRED DIRECTLY TO THE GROWTH OF THE VEGETATION IS ESTABLISHED. GEOTEXTILE FABRIC
POSTS WITH ALL OTHER PROVISIONS OR ABOVE NOTES APPLYING.
7. FILTER FABRIC FENCES SHALL NOT BE REMOVED BEFORE THE UPSLOPE 13.CATCH BASINS SHALL TRAP SEDIMENT OR FILTER FABRIC MUST BE
AREA HAS BEEN PERMANENTLY STABILIZED. PLACED UNDER GRATE UNTIL VEGETATION IS ESTABLISHED.
8. FILTER FABRIC FENCES SHALL BE INSPECTED IMMEDIATELY AFTER EACH
RAINFALL AND AT LEAST DAILY DURING PROLONGED RAINFALL. ANY
REQUIRED REPAIRS SHALL BE MADE IMMEDIATELY.
All American Geotechnical, Inc. Drawn By: Erosion Control Notes 12309-31-90074
Permit Number: Parcel Number: Figure
8947 Buttonwood Lane NE BWJ Proposed Residence
Olympia, Washington 98516 11/28/18 Belfair, Washington Valerie Gage Site 419 NE Bearcreek Dewatto Rd
Revisions: Applicant Name: e Address: