HomeMy WebLinkAboutSite Preparation and Foundation - BLD Letters / Memos - 8/18/1977 TELEPHONE MAIN 4-3946
NEIL H. TWELKER & ASSOCIATES
CONSULTING SOILS ENGINEERS
Alaska Trade Buildins
Mail To: P.O. Box 21328
Seattle,Washington 98111
August 18, 1977
KPFF
Consulting Engineers
Lloyd Building
Seattle, Washington 98101
Attention: Mr. Dave Green
Be : Site Preparation and Foundation
Construction for Proposed Alder-
brook Inn
Dear Dave :
On July 8, 1977 we examined the proposed site and borrow sources
for your forthcoming Alderbrook Inn expansion program. We present
herewith a report of our findings, conclusions and recommendations.
Previous Investigations Our report of April 2, 1974 contains con-
clusions and recommendations for foundation construction of a some-
what different project on the same building site. From a brief sub-
surface exploration performed at that time we concluded that the soil
formation throughout the area of the proposed construction consists
of moderately dense fairly clean gravelly sand and that excellent
support conditions will be found for the proposed construction.
Detailed conclusions and recommendations were submitted in the pre-
vious report. A copy of which is attached hereto.
Recent Examination The examination in July 1977 was made primarily
to ascertain the suitability of material across the road from the
project site [immediately east of the Alderbrook office structure; .
Methods used in that examination consisted of reconnaissance of the
roadcuts in the general area and shallow hand excavations.
Conclusions and Recommendations From our examinations of proposed
borrow souces we draw the following principal conclusions [which may
be appended to our letter of April 2, 19741 ;
1. We anticipate that material encountered in the excavation
east of the existing office structure will encounter dense,
fine-grained materials. We believe the natural moisture con-
tent of these materials will allow compaction to- produce structural
KPFF Aucust 1a, 1977 Pace 2
Pills on which building elements can be placed, using bearing
pressures of 4000 psi'. We point out however, that un;avorable
weather during construction could interi'ere with compaction
and make an alternative borrow source necessary.
2. In the event that material from the preFerrred borrow
source cannot be employed as structural rill, a pit-run
gravelly sand or excellent quality is available two miles
from the project site. The gravel pit is also owned by ;.he
Alderbrook management and is therefore available, if needed.
3. Structural fills of fine-grained material should be spread
in uniform lifts not exceeding 6 inches loose thickness with
each liFt thoroughly compacted by routing of loaded 'hauling
equipment, repeated coverages of heavy crawler tractors,
sheeps---Foot rollers, or heavy rubber tired rollers. The
entire surface of the fill should be accessible at all times
to the equipment used in construction of the fill . Compacted
fill slopes to declivities steeper than 1 vertical to 2 horizontal
should not be attempted. In the event that steeper fill slopes
are desired [as in the vicinity of the peripheral concrete wall)
the fill could be constructed beyond the intended slope and
excavated back to the desired declivity [which for heights not
exceeding 6 Feet, may be 1 vertical zo 1 horizontal) .
4. All backFill between rime grained fill and exterior peripheral
walls should be made with the pit run sand or gravel from the
upland source. Compaction by small vibratory equipment is
recommended For the backfill zone. Sackfill should also be
provided with a perforated foundation drain-
5. In the event the pit run sand or gravel must be used for
the body of the structural fill , it should be placed in lifts
not exceeding 9 inches loose thickness, with each li`'t compacted
by repeated coverages or loaded hauling equipment, crawler tractors,
heavy rubber tired rollers, or heavy vibratory rollers.
B. The degree of compaction sought For structural Fills of
either material is 95 percent oi' maximum density as determined
by vibratory compaction test AASHO T-99.
We request that we be noti=ied when excavation of zhe proposed
borrow area is about to be undertaken in order that we may schedule
a visit to the project site for the purpose OF conFirming usability
of the prop osed,_,bor-r-aiu source.
of WgS;'i-ram Very truly yours,
NSIL H. T WcLKEH C r^,SSOCI ATES
b Y
Neil H. Twelker L
NHT :a mt ^y10
��„�'fi
cc : Howard S. ` cam Attn : Ed Muskat
Alderbrook Inn Attn : Wes Johnson
Incl .