Construction Stormwater Pollution Prevention Plan
Manke Family Resources
3500 E Johns Prairie Road
Parcel No. 32009-09-02000
Mason County, Washington
April 1, 2024
Project#24030
Prepared For:
Manke Family Resources, LLC
PO Box 1302
Shelton, Washington 98584
(360) 427-8726
Prepared By:
Envirotech Engineering
PO Box 984
Belfair, Washington 98528
Phone: 360-275-9374
v:asyy
43015
Ff. ltiTER �—.
4/1/24
TABLE OF CONTENTS
1.0 INTRODUCTION.................................................................................................................................1
PROJECTDESCRIPTION............................................................................................................................... 1
EXISTINGSITE CONDITIONS....................................................................................................................... 1
OFFSITE DRAINAGE TO THE PROPERTY PRIMARILY ORIGINATES FROM THE NORTH,EAST,AND WEST.
EROSION WAS NOT OBSERVED ON THE PROPERTY....................................................................................... 1
ADJACENTAREAS...................................................................................................................................... 1
CRITICALAREAS........................................................................................................................................2
SOILS..........................................................................................................................................................2
EROSIONPROBLEM AREAS.........................................................................................................................2
CONSTRUCTIONPHASING...........................................................................................................................2
CONSTRUCTIONSCHEDULE........................................................................................................................3
ENGINEERINGCALCULATIONS...................................................................................................................3
2.0 SPECIFIC CONSTRUCTION SWPPP ITEMS.................................................................................4
2.1 ELEMENT I-PRESERVE VEGETATION/MARK CLEARING LIMITS........................................................4
2.2 ELEMENT 2-ESTABLISH CONSTRUCTION ACCESS...............................................................................4
2.3 ELEMENT 3-CONTROL FLOW RATES..................................................................................................4
2.4 ELEMENT 4-INSTALL SEDIMENT CONTROLS.......................................................................................4
2.5 ELEMENT 5-STABILIZE SOILS.............................................................................................................5
2.6 ELEMENT 6-PROTECT SLOPES............................................................................................................5
2.7 ELEMENT 7-PROTECT DRAIN INLETS..................................................................................................5
2.8 ELEMENT 8-STABILIZE CHANNELS AND OUTLETS..............................................................................5
2.9 ELEMENT 9-CONTROL POLLUTANTS..................................................................................................5
2.10 ELEMENT 10-CONTROL DEWATERING..............................................................................................6
2.11 ELEMENT 11-MAINTAIN BMP'5.......................................................................................................6
2.12 ELEMENT 12-MANAGE THE PROJECT...............................................................................................7
2.13 ELEMENT 13-PROTECT LOW IMPACT DEVELOPMENT BMP'S..........................................................7
1.0 Introduction
Envirotech Engineering (Envirotech) has completed this construction stormwater pollution
prevention plan (SWPPP) in conjunction with the stormwater management plan for a property
located at 3500 Johns Prairie Road (Parcel 32009-09-02000) in Shelton, Mason County,
Washington.
Best Management Practices (BMP's) selected for this project includes a stabilized construction
entrance and silt fencing. It is our opinion that these selected BMP's adequate for preventing
significant construction stormwater pollution from leaving the project site,and meets the intent of
the Stormwater Manual. The following 13 items have been addressed per the prevailing
Stormwater Manual.
Project Description
Information pertaining to the development of this project was provided by the proponent of the
property. The proposed development is expected to consist of land clearing in support of future
mining activities..
The project is not expected to create any new impervious surface. See the accompanying
stormwater management plans for an illustration of current and proposed site features.
Existing Site Conditions
The property is accessed from E Johns Prairie Road an existing paved roadway in unincorporated
Mason County. The Project is currently undeveloped, with clearing on-site. Vegetation is typical
of the Pacific Northwest. E State Route 3 extends to east of the property. Beyond the property,
rural residential and industrial development exists.
Maximum sloping grades within 300 feet of the proposed development area with a vertical relief
in excess of at least 10 feet were observed to be 42% on the property, with slopes exceeding 60%
beyond.
Erosion was not observed on the property.
Adjacent Areas
The area of land that contributes stormwater runoff to the proposed development areas of the
property is generally non existant.
The natural drainage from the property is directed to the southeast edge of the property. Runoff is
intercepted by an existing roadway ditch along E state Route 3, eventually draining into Oakland
Bay.
Envirotech Engineering SWPPP
PO Box 984 page I Parcel 32009-09-02000
Belfair,Washington 98528 Mason County,Washington
Ph. 360-275-9374 April 1,2024
Critical Areas
Other than the aforementioned moderate slopes located on the property, critical areas were not
observed within the vicinity of the project. This project is not anticipated to disturb any critical
area.
Soils
Information on infiltration rates and soil conditions pertaining to the Project was accomplished by
Envirotech. Selected information pertaining to the drainage aspect of the project is provided
below.
The following subsurface conditions are estimated descriptions of the Project subgrade utilizing
information from the depth of penetration at all testing, sampling, observed and investigated
locations. Soils for this project were described utilizing the Unified Soil Classification System
(USCS). Using the USCS in conjunction with estimated relative densities and other anticipated
engineering properties of the soil, susceptibility for potential landslides, erosion and seismic
hazards may be assessed.
Soils within the upper 180 feet are mostly sand and gravel. See the Geotechnical Report for
specific details.
According to the "Soil Survey of Mason County," by the United States Department of
Agriculture, Soil Conservation Service(SCS), the site soils are described as Grove gravelly sandy
loam with 30%-45%slopes.
According to the USDA Textural Classification System,the site soils are a loamy sand.
Based on the fines content, erodibility of the site soils is considered to be medium. Based on the
fines content and fraction of clay within the fines content, settleability of the site soils is expected
to be fast. Permeability is expected to be moderate for this site due significance of moderate
density,and fine-grained soils.
According to the Critical Aquifer recharge Areas Map for Mason County, the site is within a
Category II Aquifer Recharge Area.
Erosion Problem Areas
There are no identified or mapped erosion hazard areas for this property. The soil characteristics
provide a low to moderate erodibility factor.
Construction Phasing
Construction phasing for this project is not expected. Upon finishing the clearing, mining of the
soils is expected to occur.
Envirotech Engineering SWPPP
PO Box 984 page 2 Parcel 32009-09-02000
Belfair,Washington 98528 Mason County,Washington
Ph. 360-275-9374 April 1,2024
Construction Schedule
Construction of the project may occur as early as June 2024. Wet season erosion control is not
likely required for this project. However, wet season construction constraints are not necessary
for critical areas.
Engineering Calculations
Standard sediment ponds and traps were not utilized for this project. However, sedimentation due
to construction runoff is anticipated to be retained on site. Significant diversions and waterways
were not utilized for this project. Silt fencing is deemed adequate for this project, and calculations
are not required for this erosion control.
Envirotech Engineering SWPPP
PO Box 984 page 3 Parcel 32009-09-02000
Belfair,Washington 98528 Mason County,Washington
Ph. 360-275-9374 April 1,2024
2.0 Specific Construction SWPPP Items
The following 13 items have been addressed per the prevailing Stormwater Manual.
2.1 Element 1 -Preserve Vegetation/Mark Clearing Limits
Before beginning land disturbing activities, including clearing and grading, clearing limits,
sensitive areas and their buffers shall be clearly delineated on-site.This includes delineating trees
that are to be preserved within the construction area. Construction activities are not permitted
beyond the designated clearing limits without prior approval.
Retain the duff layer, native top soil, and natural vegetation in an undisturbed state to the
maximum degree practicable.
2.2 Element 2-Establish Construction Access
Construction access is designated as the ingress/ egress connecting to E Johns Prairie Road.
Existing mining construction entrances may be utilized. One construction access is allowed for
this project. Stabilize the construction access with rock per the stormwater plans in order to
minimize tracking of sediments off-site. If the stabilized construction entrance proves ineffective,
locate wheel wash or tire baths on-site.If sediment is tracked off-site,clean the affected roadway
thoroughly at the end of each day, and more frequent as necessary. Remove sediments by any
means necessary, and transport the sediment to a controlled sediment disposal area. After
sediment removal, conduct street washing, and control wash water by pumping back on-site, or
otherwise prevent it from discharging into systems tributary to waters of the State.
2.3 Element 3-Control Flow Rates
At all times, flow rates shall be controlled for this project. Natural drainage patterns shall be
protected as much as possible during construction, and concentrated flow should not be
permitted, unless directed to an engineered drainage facility. Protect downstream waterways and
properties from associated discharge of turbid waters.
2.4 Element 4-Install Sediment Controls
Sediment discharges from the project site must be minimized. Sediment controls deemed
adequate for this project is temporary silt fencing, and shall be located downslope from all
disturbed areas.
If sediment control is not working as intended, additional controls such as sediment traps, hay
bales,filters,or other standard controls will be necessary.
Envirotech Engineering SWPPP
PO Box 984 page 4 Parcel 32009-09-02000
Belfair,Washington 98528 Mason County,Washington
Ph. 360-275-9374 April 1,2024
2.5 Element 5-Stabilize Soils
Soil stabilization is not necessary for this project. Temporary seeding and permanent soil
stabilization requirements are provided in the erosion control section of the design drawings.
Always minimize the area of exposed soils during construction, including disturbance on steep
slopes. In addition, soil compaction should be minimized, and topsoil preserved as much as
possible.
Soils shall not remain exposed and unworked for more than 7 days during the dry season (May 1
—September 30),and more than 2 days during the wet season(October 1 —April 30).
2.6 Element 6-Protect Slopes
Slopes are not expected to be protected for this project.
2.7 Element 7-Protect Drain Inlets
There are no existing drain inlets close to the project that would be influenced by the
construction.Newly installed catch basins and other inlets, shall be protected from runoff siltation
via silt fence inlet barriers, inserts, or other appropriate means. Clean or remove and replace inlet
protection devices when sediment has filled one-third of the available storage (unless a different
standard is specified by the product manufacturer).
2.8 Element 8-Stabilize Channels and Outlets
There are no Channels of Outlets planned for this project.
2.9 Element 9-Control Pollutants
Pollution generated from construction must be controlled at all times. Control of pollutants other
than sediments includes the following:
• All pollutants other than sediments shall be handled and disposed of in a manner that
does not cause contamination of stormwater.
• Cover, containment and protection from vandalism shall be provided for all chemicals,
liquid products,petroleum products,and non-inert wastes present on the project site.
• Maintenance and repair of heavy equipment and vehicles involving oil changes,
hydraulic system drain down, solvent and de-greasing cleaning operations, fuel tank drain
down and removal, and other activities which may result in discharge or spillage of
pollutants to the ground or into stormwater runoff must be conducted using spill prevention
measures, such as drip pans. Contaminated surfaces shall be cleaned immediately following
any discharge or spill incident. Emergency repairs may be performed on-site using
temporary plastic placed beneath and,if raining,over the vehicle.
Envirotech Engineering SWPPP
PO Box 984 page 5 Parcel 32009-09-02000
Belfair,Washington 98528 Mason County,Washington
Ph. 360-275-9374 April 1,2024
• Wheel wash or tire bath wastewater shall be discharged to a separate on-site treatment
system or to the sanitary sewer,if available.
• Application of agricultural chemicals including fertilizers and pesticides shall be
conducted in a manner, and at application rates that will not result in loss of chemical to
stormwater runoff. Manufacturers' recommendations for application rates and procedures
shall be followed.
2.10 Element 10-Control Dewatering
Although dewatering will not be likely for this project, special provisions are required to be
followed when dewatering. The outlet for dewatering shall be located in a position as to prevent
sediments and pollution from leaving the site.This may be accomplished by pumping water into a
sedimentation pond,or other standard control.
2.11 Element 11 -Maintain BMP's
All BMP's must be inspected and maintained in order to assure continued performance of their
intended function. Remove all temporary erosion and sediment control BMP's within 30 days
after achieving final site stabilization or after the temporary BMP's are no longer needed.
Inspection and maintenance for this project includes the following:
Stabilized Construction Entrance
The stabilized construction entrance shall be inspected at reasonable increments. Increased usage
of the construction entrance warrants more frequent inspections. Additional rock shall be added
periodically to maintain proper function of the pad.
Permanent Vegetation
Permanent vegetation shall initially be inspected regularly to insure establishment and healthy
growth. Once established, vegetation may need to be periodically fertilized for continuous
growth.Vegetation shall be re-established in areas,if necessary.
While active construction is in process, all temporary erosion and sediment control facilities shall
be inspected and immediately maintained if necessary per the requirements provided above. In
the event that construction activities are discontinued for at least 4 consecutive days, the owner
shall be responsible for the inspection, and immediate maintenance if necessary, of all temporary
erosion and sediment control facilities immediately after storm events, and at least once every 7
days.
In addition to the aforementioned inspection and maintenance schedule, the owner shall install
additional erosion and sediment control facilities if proposed erosion and sediment control
measures prove to be inadequate.
Envirotech Engineering SWPPP
PO Box 984 page 6 Parcel 32009-09-02000
Belfair,Washington 98528 Mason County,Washington
Ph. 360-275-9374 April 1,2024
2.12 Element 12-Manage the Project
Inspection, maintenance, and financial liability of all temporary/ permanent erosion and
sedimentation control facilities shall ultimately be the responsibility of the current property
owner. All construction facilities and BMP's shall be assured continued performance of their
intended function. Since more than 1 acre is planned to be disturbed, a Certified Erosion and
Sediment Control Lead (CESCL) may be required. Currently, the designated manager for this
project is:
Manke Family Resources,LLC
PO Box 1302
Shelton,Washington 98584
(360)427-8726
2.13 Element 13—Protect Low Impact Development BMP's
Prevent compaction of vegetated flow paths delineated for this project, and other low impact
development BMP's that may be associated with this project. This should be done by excluding
construction equipment and foot traffic.
Envirotech Engineering SWPPP
PO Box 984 page 7 Parcel 32009-09-02000
Belfair,Washington 98528 Mason County,Washington
Ph. 360-275-9374 April 1,2024
NOTE:ENTRANCE TO MINE 11UPP PRUPFRTY ENTRANCE TO RR
All,f W l N V N'A)N;t LyR�TIN STARAUZED CONSTRUCTION ENTRANCE.SEE DFTAIIA.
1^N
S1111,
akland lIOT
IN mm•nbylel!1 � �370s� .',�r'
/ ,v
N ICIMTY MAP
N.T.S.
/ HXISTINO ROAD
TO RR IISSDRDR
ua.sL uese'xvrrox LOOGINO
Ie)el nl'us uP wN NOIlauwe•Itu+slaavAtcANtu xw.ao - r /�1�� T " )) ARR 7 S
"-DI EHd IANNOT Bd 'VI
! / DISPHRSION CANNOT DE A<MIE1'ED
NIDnlx)arss / , i' ��; Iser nNlADAI
Jf00F LIMITS UP LIX)OMG AREA �-
IlnTlns:NAww / / _lOM MMHW RL'FTdR
i+
SOIL LOG: A
TEL: 6ISO'BROWN POORLY ORADED GRAVELS AND SAND(OP,SP) / PULLDQIPFRMONWIIRRE)RO'FLOW
PJJIL IIK PRnPRKTYIR%F IMnLF.
ET.ARIL1770(V)NSTIQATIONLNTRANC'E ' IA'PRt)PFRTV I.MF SPTBAEYI
kI.VLRRVV PR1)R TO LI:AI�MG � j/ j''
LEGEND PK tGRTY SL7 UL'TA LRRNUTtE !1 )4 APPRUXIMA'I H MHRW
AND 1'OL OP SLI)Pk
EXISTING TOPOGRAPHY
• PROPERTY CORNER % m9
•111 SOIL TEST PIT
PROPERTY LIKE %
— ROW/EASEMENT j
AVERAGE ELOPES
�^ SILT FENCE
_._..._..� VEGETATION BUFFER
——— BUILDING SETBACK
CLEARING LIMITS --� —�
< DRAINAGE DIRECTION
• ELEVATION
INDEX OF SHEETS
SHEET I OF A GENERAL SITE FLAW COVER SHEET
SHEET 2OF4 DETAILED SITE PLAN
SHEET)OF 4 GENERAL NOTES AND DETAILS
SIffbT4 OF 4 EROSION CONTROL NOTES AND DETAILS APPRX LOGGING AREA 6.17 ACRES
CREATED BC: R,MCNEARNr E.I.T CALL BEFORE YOU DIG' PrRPAREDFOR. PNOMPPR KIIItNI
DATE 4'I 24 — KRn— COVER SHEET
REVISm VY bRenRPvw YM1w, MANKE DEVELOPMENT MANKV FAMILY KAROLIR(P.R.LL( HNVIROTTB'HENGMEEAIKI. �*'; OF
viN)rne PROPOSED CONDITIONS ro Rux lRa P.0 WON IRW
DATE:
opOCAi:MNINN GENERAL SITE PLAN DRAINAGE AND EROSION/SEDIMENT , i rON,WAMGNGTON NbbN RRLFAIR,WASIONGTON 4kSfb 4
REVISED BY: wNwiNrN+YN1YfY I'i ltlNl;.IJMH b$1.P17A PW)N71:(JFA12Tf.A)1A >rr
eem n'Mmm I CONTROL PLANZ
GATE'.
ENGINEER: M.STATEN P.E. NUM. RENSION R� DA TF NOT FOR DWLMPE OVTRIOE Oi ENVNf01ECN ORAffAIAIEE EXCEPI u'S2N+.uI:IFN.GULL�.LN'
LEGEND
EXISTING TOPOGRAPHY
• PROPERTY CORNER
•nl SOIL TEST PR
—� PROPERTY LINE
ROW,EASEMENT J
\f AVERAGE SLOPES ++/
SILT FENCE
VEGETATION BUFFER /
——— BUILDING SETBACK
CLEARING LIMITS /
< DRAINAGE DIRECTION
F1111 Mtl ROAD TO
RT VNBD fcR LGjW
i
LIMITS O/IAEgRNG
APPROXIAMATF MHHW
Y AND TOE OF SLOPE
EXISTING CO(MIY ROAD
+ % DITCHTOINERCRPr RUNOFF
BRASH BARRIER
'+ / rSER DETAILS)
7^y j Itl PROPP.RTYLOYESETBACK
• ,i4' / / ^--11-Y NIYIHW RUPFRR
I /
d Td d—6
CREATED BY'. R.MGNEARN',€I r CALL.13L'FORL•YOU DICE' WHET
DATES 4'I 24 a ro��Wva
W11SEDB; behFc:r PROPOSED CONDITIONS MANKE DEVELOPMENT-UNIT 1 MANFIE FAMILY RBSOLTIKES,LL( ENVIRI"WHIR7INEERIRI .
GENERAL SITE PLAN FG Buz IRrz PO Box"R4
rare: u�l DRAINAGE AND EROSION/SEDIMENT SHELTON,WARHINOTONVEIM D(ELFAIR,WASHINOTON ftt1'� 4
RT'V^.ED E`!. 1 TAxlcIIl»a PHONE:cW)4274726 PHONE.(3N)371A174
GATE �
relNncmRmrnrtnnran CONTROL PLAN '+ Dj
:
E NGiNEER. M.STATEN P.E. NUM, RE'AMON BY DATE NOT fOR MIRX01)RE OVTSOEOF ENVIR0110 N NfLAIESEFOEPI UNIIERWWTENA4RUB1W
PFDDRIFD PY,HP PF<AAAmw;
mP�,EONnA�IGII MIGII rG,NE mInAT�l9 GFEW9TPtXTaN
�wNn.C'NaAI;;�CIOWR'�s:EfloNf 9LE Na I.00A,pIG ANDEUNInIMIxa THE De.Msoi.LLt F]D„1Nc
EX.MINR ROAD
OF EXT%W1SOP
ol IS RDroNSIBu iOR IA0KHM
AND PEOtHam sETencx9�
AI D,SMEGDAAINoau O'HHut MATERIAL TO BE MINED
IEWISCT�vsm vnOTs:R zzl[uee Iv[tTWN wvD SUHftT'OF iN[NIDIIC IN COHNECrgHwml rxe
N TNFse mxsraucrwNelwxs Tau'Nr roNTxa Mnv xe xi Malin rFA rHE
MImX�v�mxsnucTlu+.
.fE. 9R 7
PT raG TPX.R ILA PPEsrwTTrD
P YUNEs fID r.(K {�
'111E fWmANntt PSt1MA1FX As MnFMeDON sxF£!I OFTvsE Puxs. ~'
EX.CRAVE[-VEL MINE RECESSIONA U'IWASH OAK ND
OE
IwrTNP.n. n90 OMrts.rsuNinmwMnv ninnw+nlsxm Hs nnwmo BAY
HAr PEGInPF THE IA.
aseWFmlmomaEm _
I2.1H¢nnoxLSwnrEn rPUN GEPIENi sTenN SNALL B¢CONSnUCnD At'('ORDING mT11ESE APnOSTD
m EDPuxSllA RE IRlwAGTex APPPOVAE
A EX
SECTION ALA
IPgDIFICAT10N9 AS SIpwN ON1HE9ECON9nUt'OONHAN9MEDESIGNEDVIXTIIEZDXIS'sI NWAIFA N.TS.
OAii-IAnwwsepxAHs oxMMVN fw uHe�14w to,v�O�w9'LL'MATEA.'L 1111
It2S.SEPTIC DPAIxnflDA OR sFwpl LINES SH.All BE DD 1
'ETRKIn VPD PHIOI m SITING¢OIEfH AS AND DPAD AOE FACIDS 11 ORDFA m wAINI'AHI NECESSASY
z.EGY¢P,CDNT�IMNM¢NT AND nOTPCDONFIpA 5'ANDA49M
LrtTW1 BE nOVIDFD fOP ALL CHnHA1S rn_AIDnOCIY'I5,
Yl'EWDS®STAND
AIDR�A=Mll
AIF
m[TDEmT.ENENEINCT PEP.AYS MAT¢¢PnFOPMHFD
111LAII AID,
PnttEl¢Eps APEsntImEs sx.LLl eE mNDtx'IiEDpA
MANNERAND ATAP ATwNaATDTNATMTllxOT
IS
IIAI
fMYIIPPAA mnG'exlSmX CON11npN5 A91pr¢n ON i11E n.AN9.
ED.
o>RII DP nIE wSlzmaRANDAno svFCIFlcnnGrov.FMeAN[MENT
I.l��NnNEw m saTxxl zazHMK'.uCTNIw a ur SuosTAnDAaD
PEP sf(TWia5.44.IC.MFiIATS IIALL 4rnNM,SFD YFlC TgrsP••MnxIMIIMDexsm
Now Amvl.vl�wi��mu nu w,TE�Iw.ANAu eE rPEinPFDerPwuvlr«+vD1ETArIDN.
��iNAN s n.FS werxTHra E 9GuxucowPE I M TO I lFl D AL AInTo av A IS
wxsnuETxm SGlu[I9C'E
ITIOI.AL rE.MNwwY ERGSxINaxX.nDE MLSLTIES H
I I�IAuuulwEFimecl wfAa mc.
re:w'L °t
Pis.M.wFzrt elOSpN CONTaOEmgIDF TO STABHYt 1HE
CREATED BY: R.MCNEARNY E.I.T. CALL BEFORE YOU DIG! SHEET
DATE: 4 t 2A c rE--DAn 3
REVISED BY: EIt MANKE DEVELOPMENT MANKE FAMB.Y RESOURCES,I,I.0 EWIROTECN ENGINEERING +'DpSyl OF
DATE "DGGHD DETAILS AND NOTES MHOX IM2 P.O.BOX 94
DRAINAGE AND EROSION/SEDIMENT SHELTON.WASHINGTON9P5RA BELFAIR,WASHINGTON915)S 4
�, �TXwE96 PHONE:1760)4274726 PHONE:()60)27Y 374
REASED CONTROL PLAN
DATE:
ENGINEER: M.STATEN P.E. NUN. REMSION BY DATE NOT FOR DkSXOSURE OUTSIDE OF ENVROTECH OR AFFILIATES EXCEPT MICER TAHTTEN AGREEMENT.
R
MITIANDARDS
1,IREFING.-.BE-I AFTER 1-1 TOESCREEND me mufwwurrww
1,.BNORN.NETTEND-1 BE_.ACRIVES THE-I OFORES OF I.I I t I, I- TLX_OF,..'A 1.11 1.11,
A--.1 OPARCELES I--ON THESE MFX C_..._TAF_.lFM. I OPROLLANECOLD.1i _43 A.
qT Iii THE R, 17 1., DEFFLECTE...R,FIFF =I XA-IN,IT CNP A.0- NOTS lll IN.11 Hl=
INSTALEADDETICINAL.FROSION ANDRED=T'-._�_1A_-- VnI.- FTHO i=1.11-IN
LES I- FER-CE"...- 4 RRIEV-4-Ell NICALE REA A— 6 N=
I XF= __TRIE OIX*TRILE,
I ALL FACESTER AND I.`N"`C_"1ACH-AXIDESID-11FAIL.RDISPECTE. 1Z,1iCX11.ElE 1-1 L_i I I.ALLIATER1--.1-TE.
DtY AND INFEAFFEATIL .-All OF __�I.T'A.I-AS =E= I MIL, I IX;Xl FNERE-DIDED EFTMEEN AI AM-1,-ATEL-LELF1-RETATEREE-1
LE BE Eni
-All ER.I.n%. . TOP
I
FEEL .. I Ti FATIF AlIr THAIL IF r.1 TON-ESI.A1.1,1IONESEREFIDEL-Et. IVAII-1 11-11 AT A-.I AIE
IN PLAIL UNTIL THE ITILOPE ABLEAS ii AN 5 LET OF I F.XEE7TLE_ THE I EEAA =1'7 A-
I PROTECT STALL CCAIELY RNIN THE FITIHIN ANCIEDEMENFITIOTHETROL I III Ili FIEFFIXICREACE. 4 ITERINDIG S.ZLFCON1TD 1. =T_
�1 MRII1� I I=1'44'i I= IT-FOR.AEp11REMF.NTS.WHERE APPLICABLE.IN THE� TER��E�T MANUAL FOR I. EX%_ L,-FRONS TRE-1Z."i... BE-. ili INIAL, III IN-SEPHALTEEN.111-IFFECTON STATE D A- TO _. ON •PN_NnlxiwnwsiwrUwe'E=LI _l_A_
SEDIMENT Z.H.-Aii AS'ET�D$ IS N=I-Ri II1=I HE Ll 1.1 ED IN A I 1 11 DIPTH III=I A�l 1,1 E NO Ei A !.AN Pil A 7.IF TO i I A,%VLATERIEN I PARTELIC M I I IF I ;IE,AN
CIBI FOAT.IRHSET E-NJEZT ICE'I OTSFIN1E`VCTO`=CO0II=CHIIII-..E.l,UI,R NF AS IF.-TRAPS. B I
''VAAN%T=,'IEC'IDOFO=F,�TNIi'
Nl1RAl1 OPAD THE EFF.. E ==RE NECEASAl I-R-Li Mr,
ZiIl
, LEE
RNLE
CONSTROCION PROCE. N ANt' FRE RHEIT1 1 I'Ll PRODERFLE, FORRID DBE L-N I 11.FAR-RAT PLEVIR11.l A 1FOLL IAD CO 1.Ill
ell rtwT
I At--.1 1 ME. I AN.A-IN I:, IDE It 1.1 Eki A,=1
SELIMENO I IIIIIN Ill 10111 ILCTI 11 IFTI,I HAT IS 71-ELD ONTO PUBLIC ROADIAYI 11F1IFALI.FIIANLFFEDI.$LNI,R It. Li
I BE =TA_
FEENTO IFFiED XX:DDTFFY.AND ENCRODGETLYCLEINEDATIFFEEND '_TCIi'-'"i"A=.....I= 13VE=N`01=1`=E
Oi EACH Ay D=C CON ASHING SHALL HOT BE DONE wrv.sFCO
,1=l
lit ILLMRERE"'IN HAVE DFFl 11RIPPED OF I EGEIATION OR IFIFFERFEENCED LAN. RICO" ANDIR El"
F EINEFT rLLYFAZN:11'=T;A=VF-=-"` I.AEIF-ENT I-l OF
DEO ICTIVIT R,A" 'FIE EXI 1ORTHEIR WIF IS A�A�FOR A PERECID L=I FILE IN IT -� INIXELATS
P"Fulli THE LQ)
ALL OISTOREFi CA I C�9,PI71.-EN THE XLEENTATI 11 AXEAIII.
ITA-DED BOTH NOR CH 11 11SEEFFHATTLY EXCE=l El I
EL RE OR
ER-COAT- ED I R FI.SUPPOREI 1-1
TREA Pit OR i == ==RZIS11=y
FA-AP%1-11 T=-11 YEAR 111.,E=,.Lll 1711 11 1L.T A I CTE.1 1=D I IN DEM-CE-111TV,
_LEPERELF. ill �F, _
THE I OF APRIF THREADO LEMNVE THEL AL--STIFIED- r'Il. .
MIRTOR PRO S
4"' Y ISTt1"D=1$tFVS "' -'=:t
ALSO RIP--ENEVERRTS I.liTEEN AACEETTFFIETEIXG OR-APPROVETHE INTEREST Or THE D.-I PROPORTECE3 PENTY GRAMEHATERN I.1 1.1 DP-1.1F.I.RE,SO-MX.NT I I-I A.1 I OSINI-AL FAINIAX11-
LL 'i I IN
ID,
-.E BY NSRALI ACCORTINGTOTHE-RANG.
I=EK)TRi 0�7,84!Z��F.InD�MIal BE =Y:�, TENAT D I N`=X417ri F
CIA 14 111 C�I�I D tS. F, AL(RIXIED
.BY 1--1 1 THERIC 1--..1-THE C11AOF LAND.F.CLIEDING THE, _1 DR.- IS .1 EM "IT N I="AT SIXEL'OF 'OF IN
RINKFAFFIFFIRE 2=OR OTHEROLN1D OF ,MIT IF UINTIED TO ONLY It IELINEVE xt� A
AS X_LAND AS
CAN RECEDE
E, APPROPRIATE
PID-COVER01B-I
IT D.AFTER HAVENG BEEN CLEABEFFER NISE RELED.IT 11 LATER "NFENI 11"I PAII
SF=� PARE - AIN1.TX-NEA--AXF---
HER"OfAGIVENYEAPLENLESIUMEE=TE�Ei TO_ TIFFIN .�L Ri All A I LE L,Di'V'IR IN It Z��i �i BE P=IN ALL
E��A�DS��MKII.ALL�RFAS�EA'�OR� SETH-BED ON
MOST HE AT A USE OF NULLEFING.EFETTIZ PLAR,E,
MATERIAL. lIP-EF
"'D THR=MEN SILT FENCE 'FILE _L It 'I
FREE DRA -1 IRNEFRlNTEE.- NE ELL
FM STA� =1=
SIREETTIG.=DTLAZi FER
PER THE APPROIREL PLAN OF ACTION ON-
THERIDE APPROVED BY THE 'A""'
It-.- AND-W-IF 11*1111 TER"i OF IF-TEX I.V.,D CRE OFF THES Rm I-, T..-Dit AREAS A EARERE r R,!rTI'My R.
Al. A I.-PrECIT, X.NOILEIIINCH
AUGUST===0"S-;=.T=EL2.1ii�'Et IF OFFEE VON—PHYRICAL 2 POOR SHALL D BE M.CED A'A StMON(TI==-APAIT=i.EXCEFFILl INTO THE
N�IAT VA�,.�."=THXi SNALLIEST
==TD=IR IN 111. 111D I 11A OLLE I A IF_
'VENTEN PRE
A11_1%. -EC-"ICINCE.-III
ATIMENEH SEALLFREXCATEDAPPROXIMATELY I INCELICS AIDE All 12 INCHISEEREP ro
NPLARTEL E.- 11,-IT BE.._BY N,_FX ACENG.1-1 OF-IS AND UPSEENT HROEN I-..I PREENCLI-RE 1.1.A.I.I.FECIRE ELLE AFR011 IVARSIALL-r
THAN A,-. RE;= "'!i
.Ll;CT AENR'SL..R.__H_N__. TER OtIll.POINELDE-1.1 E
1.IN IZXREN i- 11
LITHE IN III ITI,
ATTRL "``LY TO 'FEE IS ON. Ti Ei Z
FAFFFEFTNATF��Fi UE�A Oil DIFFER SITE DEVEI-NEENTE LREXTARLE I Y-1-1 I-SIX--I
IT'Lli
AR= ECITTIVE OAI I-
BE Fril rELR BYRON EVENTE.AND AT LEAST ORELF FIERYTHE 3 111 SLANDRELISIREACIIII IILEB I"Fli 11 FF�,��Fli�ltl HE
CONEXACTOR SHALL
FIF-IFFOR
THE MATEETERIANCE AND REPARR OF ALL "ED M=LTA =1 I ;A1T=ll=-
All 21 PECHES IF THE 1AFFIF IIALL BE PARES.A. I F ,Axe ...BEA IN.A
AN I--CONTROL 111 US F%TI"CS ADL`="ST= AL ""E"'FILTER
1Z- EE=R.. FNCOFLAEREX�- IR -11=
SFAXON I-�Tlfftl ALIL 1*1-ON ICIES-11-ITED-- FTC;"AEL NOTBERCENROVEDICTOMILTHE
CE PRELL LYS
Ei AND CEND u=T�1.XCEL LAND
-1.IFALL I IFAIIEC PENCIS SHALL ll�FISPECTED MEETRATELI AFTEA EACH RADIALL AND Ili=A L�VM=A IN.I At L`
CAN BE C011BED OR STABILLEP.WIXN_2H=IN FEET El FELL A IIE A DAILY PERINEL PREELONEXED AFERNIALL AEO,�Fki REPALKS SKALL.BE AMIDE E �Ni I-- A I OT I TI I=1 I'l F=
..I-AID I SPORTFEEKORIERIE.T 'Z=_
I SILT rFACCT WILL BE-A-PARALL-ELL TO AN M I
=BLANKEE"TAS:,�FIDRE EEFTSBT D;aD ILREI�VE"���TFPWTEIIIIE'�FRIR i THAN IMMET
DEo.=ULW D=FEE
Al.ll
ENGMACERIAL =5 O*��IFRDW_ISE��S_EDIF Mi V.�Y�D,�TFE�.S INEENT LEDONOTERIVEIIIII.R.LELVE.111- NERCEEN,
I IF FEE RFL_ r F
=EEIN THE I-THAT ANY LAED AREA 21 1=1 AcE I TIVE A FORLY i BE I
"'T"HAS NOT REEN APPROPRIATELY STAEN5 DAYS AFTER HAV7
CLEAKED ALNXTILCT I ACTIVITY IN THE STIE,EXCEFT FOR PROSIONI AND MENT�O
ACTIV-SELA-11ROTERATE111.1-SUCHATTINE- 1.F E I REEK THAI-111 Tx- ;=:=ED-=
LAND AIREA HAS BEEN APPICEPRIATTLY?�Oft SL�7
......L ZAADO ONELL NOR
"E`1E 111.1,1,INA I I IFFIN I. .......
FFAR____ IA FIT AN IF IYEZ��r IF A __,I =CELDED ON SNil A.AIENENT [f required drape fillet fabric
THE-PLAH, over brush and secure in 4 X4
I-CONS Ie lvn'll NO "ITT All I'IOI�Eli I I D1RF2�'EID),]ICHARGE OF MIATERPRO DEVI PROM TRENCIER OR OFFER AREAS ALL Al 1-11 111.1-1.IN AR1111-OR APER-11 roawnLmin,trench with compacted
Eli = 'i
IF u_ It_T
;;r FEZ, NO IF I- =I- t`1TW_'R_` bai
=Z;F III S� DEWATERONG DEVICES SHALL EX TO=A I. L`DiN`=L7`F=;R`1=1�1`N'l I..,I R IFFOR. I,-
NCTEDEN %CCENAL REACK SELAIL ASED INERFORICALF1 TO 1.-1 ERN LRE 1-1 IN A
RIDE IRZA'�Slti TFVDDIAI��=-.11LA.11 I 1 11 A _1 I I FT 'NRI1VAE1LTl`EE
ARTNER EXER AL111 Y_ y",
FKATE ENIATED AND__THE COX_ 1 .1 T11-1 I F
I NOT..A=R--E
LACEM THE ==.. Fl.THE
Rill THERWASEENGS ALL HE COMPLETEDONTR QuALLOYSPALLSOR CROSETEDROCIA.AND _1=T===
.AMNRFATFRXHA-TL.CNTT.SI ANALL.STAPEDOR ROPICH ALL I'=1111FRED FORON MILL LENGTH All THEIRSELAIL It AT LEAST
MAEFF-PER-TESEFEBONANDIFF-C- Anchor donhIII edge of
LDeEeu filler fabric with stakes,
ITZ ..wpm, R%R=' .31==THE
�FTFRTHE '=IFETRAIALL EIRNADO T`E1HEI At III TOP%ILOP11 lDM Z- sandbags,or equivalent
i Ci INIENT 11111 LNEIDEDON THESE EFROILAti
BERSAIIIISLODIREFINA
HY�S�Dlc FOR BECIFILTRATION 91A 711,11D H"ht
IAIA RI.IIH H SEERE ADS M INET_m OFE 5_INKIN DS-P BEAR.LRD WILEA DI ARL�� MIT.5' Ido brush baffler with
max 6 diameter woody debris
.
2-
A;:=XZvLmiml,9Alternatively topsoil stripping&
L HAILIN AREA ACT-OF IFFIT.OE FERTILIZER-BE ma)re used to form the b3i AS__ 11 11
S.ESTAB STAMETTIMMj
4-VOR"EX""A'A=.WATFA RUNO LLNG FEE PRCDDE IEGIIATEDI
Flaure 4.2.11-Brush Barrier
=RSU=DEFYCH%EDXT G IN RLIN AULLUST SHOULD MEET THIS REQUIREMENT.I'DESEERN POSSIBLE,COVER SCOLABLA
EROSION CCITT!-COVER
5,DURINGABLIHNFNT.MAJIFFAIN VEGETATION VIA WIGAibN DIIRIHC MY
THEREDS
E.--Prr OF VE FICATION MAY BE-DIFE TO OVER-ACTION
TEDIFING CONSTITUTION.FEE COMPACESON OCT-S,TELL FICESIVALP NFIEDIF PLANTTNO
CREATED BY: R.MCNEARNY E.I.T. CALL BEFORE YOU DIG! SHEET
DATE: 4/1/24 CALL I IR--1
REVISED BY: .-I YCO-1 CONTROL MANKE DEVELOPMENT-UNIT 1 MANKE FAMILY RESGURCES.i ENVIROTECH EEIGINEEILING 4
EROSION CO PRO BOX 1302 P.o,BOx 914 F
DATE: DRAINAGE AND EROSION/SEDIMENT SHELTON.WASHINGTON 1115. BELFAIR,WASHINGTON"528
PHONE:(30)4274n6 PHONE:(360)27SM74 4
REVISED BY: TORWIALLEFERSHICTRIDELCON CONTROL PLAN
DATE:
JENGINEER: STATEN P.E. NUM. REVISION BY DATE
is
FPI�?�24-�C�oo i
Drainage Report
Manke Family Resources
3500 E Johns Prairie Road, Shelton
Parcel No. 32009-09-02000
Mason County, Washington
April 1, 2024
Project#24030
Prepared For:
Manke Family Resources, LLC
PO Box 1302
Shelton, Washington 98584
(360) 427-8726
Prepared By:
Envirotech Engineering
PO Box 984
Belfair, Washington 98528
Phone: 360-275-9374
CLYDF Sp
\\ASy��n'l��y
S
43045
ss�C).\A0�C
4/1/24
TABLE OF CONTENTS
1.0 PROJECT DESCRIPTION.................................................................................................................. 1
2.0 EXISTING CONDITIONS...................................................................................................................2
2.1 TOPOGRAPHY.....................................................................................................................................2
2.2 SURFACE DRAINAGE..........................................................................................................................2
2.3 SUBSURFACE CONDITIONS.................................................................................................................2
2.3.1 SUBSURFACE CONDITIONS..............................................................................................................2
2.3.2 GROUNDWATER...............................................................................................................................3
3.1 DEVELOPED SITE DRAINAGE CONDITIONS.......................................................................................4
3.2 DOWNSTREAM ANALYSIS...................................................................................................................4
3.2.1 TRIBUTARY DRAINAGE AREA.........................................................................................................4
3.2.2 DOWNSTREAM DISCHARGE.............................................................................................................4
3.2.3 DOWNSTREAM EROSION AND WATER QUALITY............................................................................4
3.2.4 DOWNSTREAM CONCLUSIONS........................................................................................................4
3.3 HYDROLOGY AND HYDRAULIC ANALYSIS/DESIGN..........................................................................5
3.4 FULL DISPERSION.........................................................................................................................5
3.5 BRUSH BARRIER............................................................................................................................5
4.0 INSPECTION AND MAINTENANCE...............................................................................................6
4.1 INSPECTION AND MAINTENANCE SCHEDULE....................................................................................6
4.2 INSPECTION AND MAINTENANCE RESPONSIBILITY...........................................................................6
5.0 CONTROL OF POLLUTANTS OTHER THAN SEDIMENTS......................................................8
6.0 PROJECT ENGINEER'S CERTIFICATION...................................................................................9
Appendices
Appendix A—Site Map
Appendix B—Pollution Source BMP
1.0 PROJECT DESCRIPTION
Envirotech Engineering (Envirotech) has completed this drainage report in conjunction with the
stotmwater management plan for a property located at 3500 Johns Prairie Road(Parcel 32009-09-
02000) in Shelton, Mason County, Washington.See the Vicinity Map below for a general
indication of the Project location.
Information pertaining to the development of this project was provided by the proponent of the
property. The proposed development is expected to consist of land clearing in support of future
mining activities.
The project is not expected to create any new impervious surface. See the accompanying
stormwater management plans for an illustration of current and proposed site features.
- v`' -
MCEWEN PRAIRIE C��obsrt'i
F,
Project
-71
F�tf
6
vakland Bay
a rlle
1
HammersL lnkt
-J VALLEY
ACII Credh
Vicinity Map from Mason County Website
Envirotech Engineering Drainage Report
PO Box 984 page 1 Parcel 32009-09-02000
Belfair,Washington 98528 Mason County,Washington
Ph. 360-275-9374 April 1,2024
2.0 EXISTING CONDITIONS
The property is accessed from E Johns Prairie Road an existing paved roadway in unincorporated
Mason County. The Project is currently undeveloped, with clearing on-site. Vegetation is typical
of the Pacific Northwest. E State Route 3 extends to east of the property. Beyond the property,
rural residential and industrial development exists.
2.1 Topography
Maximum sloping grades within 300 feet of the proposed development area with a vertical relief
in excess of at least 10 feet were observed to be 42% on the property, with slopes exceeding 60%
beyond.
2.2 Surface Drainage
The natural drainage from the property is directed to the southeast edge of the property. Runoff is
intercepted by an existing roadway ditch along E state Route 3, eventually draining into Oakland
Bay.
2.3 Subsurface Conditions
Information on infiltration rates and soil conditions pertaining to the Project was accomplished by
Envirotech. Selected information pertaining to the drainage aspect of the project is provided
below.
The following subsurface conditions are estimated descriptions of the Project subgrade utilizing
information from the depth of penetration at all testing, sampling, observed and investigated
locations. Soils for this project were described utilizing the Unified Soil Classification System
(USCS). Using the USCS in conjunction with estimated relative densities and other anticipated
engineering properties of the soil, susceptibility for potential landslides, erosion and seismic
hazards may be assessed.
2.3.1 Subsurface Conditions
Soils within the upper 180 feet are mostly sand and gravel. See the Geotechnical Report
for specific details.
Expanded and specific subsurface descriptions, other than what is provided in this
section,are provided within the Geotechnical Report.
According to the "Soil Survey of Mason County," by the United States Department of
Agriculture, Soil Conservation Service (SCS), the site soils are described as Grove
gravelly sandy loam with 30% -45% slopes.
According to the USDA Textural Classification System,the site soils are a loamy sand.
Based on the fines content,erodibility of the site soils is considered to be medium. Based
on the fines content and fraction of clay within the fines content, settleability of the site
Envirotech Engineering Drainage Report
PO Box 984 page 2 Parcel 32009-09-02000
Belfair,Washington 98528 Mason County,Washington
Ph. 360-275-9374 April 1,2024
soils is expected to be fast. Permeability is expected to be moderate for this site due
significance of moderate density,and fine-grained soils.
2.3.2 Groundwater
From the water well report(s)and knowledge of the general area, permanent groundwater
is at least 100 feet below the current ground surface.
4
Project
LZ
;�.
Aeriall Soils Map from USDA NRCS Website
Envirotech Engineering Drainage Report
PO Box 984 page 3 Parcel 32009-09-02000
Belfair,Washington 98528 Mason County,Washington
Ph. 360-275-9374 April 1,2024
3.0 HYDROLOGIC/HYDRAULIC INFORMATION
3.1 Developed Site Drainage Conditions
The project is not expected to create any new impervious surface. Best Management Practices
(BMPs) for this project includes full dispersion and brush barriers. Natural drainage patterns are
to be maintained to the maximum extents practicable.
3.2 Downstream Analysis
This project has been analyzed as a Level 1 Downstream Drainage Analysis in accordance with
the prevailing Western Washington Stormwater Drainage Manual.
3.2.1 Tributary Drainage Area
The upslope watershed is non existent as the area of land modification is at the crest.
3.2.2 Downstream Discharge
The natural drainage from the property is directed to the east end of the property. The
water travels by sheet flow to a drainage ditch located along E State Route 3, eventually
draining into Oakland Bay.
3.2.3 Downstream Erosion and Water Quality
FEMA mapping, and other documentation do not reveal flooding or erosion hazards on
the property.
Water quality within the project watershed is not known to have major issues. Ordinary
pollution caused by residences, industrial and roadways are pollution contributors in the
area.
Off-site mitigation is not deemed necessary for this Project. This is based on the scale of
the proposed Project,and on-site mitigation design.
3.2.4 Downstream Conclusions
Existing mild sloping green areas appear to have sufficient vegetation and pollution
removal qualities for the pollution generating surfaces.
The proposed drainage design encourages sheet flow dispersal for the runoff. It is our
opinion that with proper maintenance and care of the proposed drainage facility, the
proposed development will not constitute measurable runoff to offsite properties.
Envirotech Engineering Drainage Report
PO Box 984 page 4 Parcel 32009-09-02000
Belfair,Washington 98528 Mason County,Washington
Ph. 360-275-9374 April 1,2024
3.3 Hydrology and Hydraulic Analysis/Design
The Stormwater Management Manual for Western Washington (SMMWW) was used to calculate
all stormwater management facilities.
3.4 Full Dispersion
Storm water runoff from the west to south will be directed to a downhill beyond the clearing area.
A minimum of 100 feet of naturally vegetation shall be maintained beyond the logging area.
3.5 Brush Barrier
Per SMMWW, BMP C231, Brush Barrier, shall be installed along the southeast portion of the
clearing where a 100 foot vegetated flowpath is not viable. The barrier shall be a minimum of five
feet wide, be a minimum of two feet in height, and have no more than six inch diameter woody
debris.It is acceptable to use existing materials from the logging.
Envirotech Engineering Drainage Report
PO Box 984 page 5 Parcel 32009-09-02000
Belfair,Washington 98528 Mason County,Washington
Ph. 360-275-9374 April 1,2024
4.0 INSPECTION AND MAINTENANCE
Erosion and sediment control measures that may be necessary for this project includes:
• Temporary stabilized construction entrance,located at the entrance at the mine.
• Permanent Vegetation
The following subsections provide details regarding inspection and maintenance schedule,
inspection and maintenance responsibility,and an engineer's inspection report.
Stabilized Construction Entrance
The stabilized construction entrance shall be inspected at reasonable increments. Increased usage
of the construction entrance warrants more frequent inspections. Additional rock shall be added
periodically to maintain proper function of the pad.
Permanent Vegetation
Permanent vegetation shall initially be inspected regularly to insure establishment and healthy
growth. Once established, vegetation may need to be periodically fertilized for continuous
growth.Vegetation shall be re-established in areas,if necessary.
4.1 Inspection and Maintenance Schedule
While active construction is in process, all temporary erosion and sediment control facilities shall
be inspected and immediately maintained if necessary per the requirements provided above. In
the event that construction activities are discontinued for at least 4 consecutive days, the owner
shall be responsible for the inspection, and immediate maintenance if necessary, of all temporary
erosion and sediment control facilities immediately after storm events, and at least once every 7
days.
In addition to the aforementioned inspection and maintenance schedule, the owner shall install
additional erosion and sediment control facilities if proposed erosion and sediment control
measures prove to be inadequate.
For permanent facilities, an Operation and Maintenance Manual should be required for this
project.
4.2 Inspection and Maintenance Responsibility
Inspection, maintenance, and financial liability of all temporary/ permanent erosion and
sedimentation control facilities shall ultimately be the responsibility of the property owner.
Currently,the property owner is:
Manke Family Resources,LLC
PO Box 1302
Shelton,Washington 98584
(360)427-8726
Envirotech Engineering Drainage Report
PO Box 984 page 6 Parcel 32009-09-02000
Belfair,Washington 98528 Mason County,Washington
Ph. 360-275-9374 April 1,2024
An operation and maintenance covenant is usually required to cover all stormwater facilities.
Performance bonding, or other appropriate instrument, shall be required for this project to ensure
compliance with the standards presented in this report.
Furthermore, the owner may need to retain an Erosion and Spill Control (ESC) Lead for
construction observation and oversight of the project if required by the County to ensure
compliance with the ESC components of the approved Drainage and Erosion/ Sediment Control
Plans.
Envirotech Engineering Drainage Report
PO Box 984 page 7 Parcel 32009-09-02000
Belfair,Washington 98528 Mason County,Washington
Ph. 360-275-9374 April 1,2024
5.0 CONTROL OF POLLUTANTS OTHER THAN SEDIMENTS
Upon completion of this project and future development of the lot, this project is not expected to
generate any pollutants other than sediments. However, potential source of pollutants may occur
from spills, leaks, excessive usage, ordinary usage, or vandalism of several pollutants including
the following:
• Fuel
• Oil
• Solvent
• Degreaser
• Dust
• Pesticide
• Herbacide
• Fertilizer
• Other Chemicals
The aforementioned pollutants are not expected to be currently on-site. The potential sources may
be released into the stormwater due to development of the facilities, and/or future use of the
facilities.
Control of pollutants other than sediments include the following:
• All pollutants other than sediments shall be handled and disposed of in a manner
that does not cause contamination of stormwater.
• Cover, containment and protection from vandalism shall be provided for all
chemicals, liquid products, petroleum products, and non-inert wastes present on the
project site.
• Maintenance and repair of heavy equipment and vehicles involving oil changes,
hydraulic system drain down, solvent and de-greasing cleaning operations, fuel tank
drain down and removal, and other activities which may result in discharge or
spillage of pollutants to the ground or into stormwater runoff must be conducted
using spill prevention measures, such as drip pans. Contaminated surfaces shall be
cleaned immediately following any discharge or spill incident. Emergency repairs
may be performed on-site using temporary plastic placed beneath and,if raining,over
the vehicle.
• Wheel wash or tire bath wastewater shall be discharged to a separate on-site
treatment system or to the sanitary sewer,if available.
• Application of agricultural chemicals including fertilizers and pesticides shall be
conducted in a manner,and at application rates that will not result in loss of chemical
to stormwater runoff. Manufacturers' recommendations for application rates and
procedures shall be followed.
See the Best Management Practices for this development that should be adhered to after
construction is complete.
Envirotech Engineering Drainage Report
PO Box 984 page 8 Parcel 32009-09-02000
Belfair,Washington 98528 Mason County,Washington
Ph. 360-275-9374 April 1,2024
6.0 PROJECT ENGINEER'S CERTIFICATION
I hereby state that this drainage plan has been prepared by me or under my supervision and meets
the standard of care and expertise which is usual and customary in this community for
professional engineers.
Please contact Michael Staten at 360-275-9374 if you have any questions, comments, or require
additional information.
Sincerely,
Envirotech En meering
Ft CLYDF S
0 Ats���t T��Z
43045
FCIsrenN
�SS/ONALENG` 4/1/24
Michael Staten, P.E.
Project Director
Envirotech Engineering Drainage Report
PO Box 984 page 9 Parcel 32009-09-02000
Belfair,Washington 98528 Mason County,Washington
Ph. 360-275-9374 April 1,2024
APPENDIX A
SITE MAP
EXISTING ROAD
TU HE USED FOR
LOGGING \�
V BRUSH BARRIER WHERE FULL
DISPERSION CANNOT BE ACHIEVED
(SF.E DETAILS)
LIMITS OF LOGGING AREA
2W MHHW BUFFER
i
i
FULL DISPERSION WHERE IW FLOW
PATH ON PROPERTY IS AVAILABLE
STABILIZED CONS'PRL'CTION ENTRANCE 10 PROPERTY LINE SETBACK
REQUIRED PRIOR TO LEAVING
PROPERTY,SEE DETAILS&NOTES. '�-- APPROXIMATE MHHW
AND TOE OF SLOPE
1/
n,9 1
/
APPENDIX B
POLLUTION SOURCE BMP
S407 BMPs for Dust Control at Disturbed Land Areas and Unpaved Roadways
and Parking Lots
Description of Pollutant Sources:Dust can cause air and water pollution
problems particularly at demolition sites and in and areas where reduced
rainfall exposes soil particles to transport by air.
Pollutant Control Approach:Minimize dust generation and apply
environmentally friendly and government approved dust suppressant
chemicals,if necessary.
Applicable Operational BMPs:
• Sprinkle or wet down soil or dust with water as long as it does not
result in a wastewater discharge.
• Use only local and/or state government approved dust suppressant
chemicals such as those listed in Ecology Publication#96-433,
Terhniuues for Dust Prevention and Suppression.
• Avoid excessive and repeated applications of dust suppressant
chemicals.Time the application of dust suppressants to avoid or
minimize their wash-off by rainfall or human activity such as
irrigation.
• Apply stormw•ater containment to prevent the conveyance of sediment
into storm drains or receiving waters.
Votunre 1V-.Source Con1m1 B,t1Ps August 2Al2
2-15
• Ecology prohibits the use of motor oil for dust control- Take care when
using lignin derivatives and other high BOD chemicals in areas
susceptible to contaminating surface water or ground water.
• Consult with Ecology and the local permitting authority on discharge
permit requirements if the dust suppression process results in a
wastewater discharge to the ground,ground water,storm drain,or
surface hater.
Recommended Additional Operational BMPs for Roadways and
Other Trafficked Areas:
• Consider limiting use of off-road recreational vehicles on dust
generating land.
• Consider graveling or paving unpaved permanent roads and other
trafficked areas at municipal, commercial,and industrial areas.
• Consider paving or stabilizing shoulders of paved roads with gravel,
vegetation,or local government approved chemicals.
• Encourage use of alternate paved routes,if available.
• Vacuum sweep fine dirt and skid control materials from paved roads
soon after winter weather ends or when needed.
• Consider using pre-washed traction sand to reduce dust emissions.
Additional Recommended Operational BMPs for Dust Generating
Areas:
• Prepare a dust control plan.helpful references include: Control of
Open Fugitive Dust Sources(EPA-450/3-88-088),and Fugitive Dust
Background Document and Technical Information Document for Best
Available Control Measures(EPA-450!2-92-004).
• Limit exposure of soil(dust source)as much as feasible.
• Stabilize dust-generating soil by growing and maintaining vegetation,
mulching,topsoiling,andlor applying stone,sand, or gavel.
• Apply windbreaks in the soil such as trees,board fences, tarp curtains,
bales of hay,etc.
S411 BMPs for Landscaping and Lawn/Vegetation Management
Description of Pollutant Sources:Landscaping can include grading,soil
transfer,vegetation removal,pesticide and fertilizer applications,and
watering.Stormwater contaminants include toxic organic compounds,
heavy metals,oils,total suspended solids,coliform bacteria, fertilizers,
and pesticides.
Lawn and vegetation management can include control of objectionable
weeds,insects,mold,bacteria,and other pests with pesticides. Examples
include weed control on golf course lawns,access roads,and utility
corridors and during landscaping.sap stain and insect control on lumber
and logs.rooftop moss removal.killing nuisance rodents. fungicide
application to patio decks,and residential lawmfplant care. It is possible to
release toxic pesticides such as pentachlorophenol,carbamates,and
organometallics to the environment by leaching and dripping from treated
parts,container leaks,product misuse,and outside storage of pesticide
contaminated materials and equipment.Poor management of the
Volume 1V-Source C(Mtlrol BMPs--August 2012
_'-21
S413 BMPs for Log Sorting and Handling
I)escription of Pollutant Sources: Log yards are paved or unpaved areas
where logs are transferred,sorted,debarked,cut,and stored to prepare
them for shipment or for the production of dimensional lumber,plywood,
chips,poles,or other products. Log yards are generally maintained at
sawmills,shipping pans,and pulp mills_Typical pollutants include oil and
grease,BOD,settleable solids,total suspended solids(including soil),high
and low pH,heavy metals,pesticides,wood-haled debris,and leachate
The following are pollutant sources:
• Log storage,rollout,sorting,scaling,and cutting areas
• Log and liquid loading areas
• Log sprinkling
• Debarking, hark bin and conveyor areas
• Bark,ash,sawdust and wood debris piles,and solid wastes
• Metal salvage areas
• Truck,rail,ship,stacker,and loader access areas
• Log trucks,stackers,loaders,forklifts,and other heavy equipment
• Maintenance shops and parking areas
• Cleaning areas for vehicles,parts,and equipment
• Storage and handling areas for hydraulic oils,lubricants,fuels,paints.
liquid wastes,and other liquid materials
• Pesticide usage for log preservation and surface protection
• Application of herbicides for weed control
• Contaminated soil resulting from leaks or spills of fluids
Ecology's Baseline General Permit Requirements:
Industries with log yards are required to obtain coverage under the
Industrial Stormwater General Permit for discharges of stormwater
associated with industrial activities.The permit requires preparation and
on-site retention of an Industrial Stormwater Pollution Prevention Plan
i plume IV-Srurrce Cibnlml B,btPs Augw; 2012
2-31
(SWPPP). Required and recommended operational,structural source
control, and treatment BMPs are presented in detail in Ecology's
Guidance Document: hrdu-vtrial Stormtrater General Permit
h►rnlemenlation Manual far Lne Yard_v, Publication # 04-10-031. Ecology
recommends that all log yard facilities obtain a copy of this document.
S416 BMPs for Maintenance of Roadside Ditches
Dcscription of Pollutant Sources: Common road debris including eroded
soil,oils,vegetative particles,and heavy metals can be sources of
stormwater pollutants.
Pollutant Control Approach: Maintain roadside ditches to preserve the
condition and capacity for which they were originally constructed,and to
minimize bare or thinly vegetated ground surfaces.Maintenance practices
should provide for erosion and sediment control(Refer to BMP
Landwapine and Lau-n11'e.L-elation -Wanaeement).
Volume 1V-Source Conlml BMP.r-August 7012
1-35
Applicable Operational BMPs:
• Inspect roadside ditches regularly to identitj sediment accumulation
and localized erasion.
• Clean ditches on a regular basis,as needed. Keep ditches kee of
rubbish and debris.
• Vegetation in ditches-often prevent%erosion and cleanses runoff
waters.Remove vegetation only when flow is blocked or excess
sediments have accumulated.Conduct ditch maintenance(seeding•
fertilizer application,harvesting)in late spring andi or early tall,where
passible.This allows rr-establishment of'vegetative cover by the next
wee season thereby minimizing erosion of the ditch as well as making
the ditch et3ective as a biottlter.
• In the area between the edge ofthe pavement and the bottom of the
ditch,commonly known as the"bare earth zone;'use grass vegetation,
wherrver possible. Establish vegetation from the edge of the
pavement,ifpoe%sible,ar at least from the top of the slope of the ditch.
• Maintain diversion ditches on top ofcut slopes constructed to prevent
slope erosion by intercepting surlace drainage to retain their diversion
shape and capability.
• Do not leave ditch cleanings on the roadway surfaces_ Sweep,collect,
and dispose of dirt and debris remaining on the pavement at the
completion ol'ditch cleaning operations.
• Consider screening madside ditch cleanings,not contaminated by
%pill%or other releases and not associated with a stormwater treatment
system such as a hioswale,to remove litter. Separate screenings into
soil and vegetative matter(leaves,grass,ncedlcw.branches,ctc.)
categories.Compost or dispose of the vegetative matter in a municip;d
waste landfill.Consult with the jurisdictional health department to
discuss use or disposal options iirr the soil portion_ For more
in#bmmation,please sec Rer•otiiniendatirrns Jim-:Lfcaraberuenr qj Swee(
if7stec,in Appendix IV G.of this volume.
• Roadside ditch cleanings contaminated by spills or other releases
known or suspected to contain dangerous waste must be handled
161lowing the Dativerous Waste Rceulatioxts Whanter 173 Y13 WAC1
If'testing dctermincw materials an not dangerous waste but
contaminants are present,consult with the jurisdictional health
department liir disposal options.
• Examine culverts on a regular basis tier scour or sedimentation at the
inlet and outlet.and repair as necessary.Give priority to those culverts
conveying perennial and•'or salmon hearing%trearn%and culverts near
streams in areas of high sediment load,such as those near subdivisions
during construction.
t islumr !t%-.4arrrr (rmdnl R•Nf§ 4ugiat 201_'
'-36
FPA 201y-0000
Maintenance and Operation Manual
(Temporary)
Johns Prairie Mine Expansion — Unit 1
3500 E Johns Prairie Road
Parcel No. 32009-09-02000
Mason County, Washington
April 1, 2024
Project#24030
Prepared For:
CLYDF ST
Manke Family Resources, LLC -0 WA,SH -1
PO Box 1302 2
Shelton, Washington 98584
i443045
Prepared By: �,n��E'I STV'
SS/O\,\LI o
Envirotech Engineering, PLLC 4/1/24
PO Box 984
Belfair, Washington 98528
Phone: 360-275-9374
Introduction
Envirotech Engineering, PLLC (Envirotech) has completed this maintenance manual for
the Johns Prairie Mine Expansion — Unit 1 located at 3500 Johns Prairie Road (Parcel
32009-09-02000)in Shelton,Mason County,Washington
Manual Purpose
The purpose of this manual is to provide the property owner with a specific maintenance
plan in order to ensure the continued proper operation of all stormwater management
facilities associated with this project. Lack of maintenance could lead to local flooding,
water damage, excess pollution, and/ or costly repairs or replacements of property or
drainage systems.
This manual is temporary for the clearing aspect of the project only. Once mining of the
cleared area is completed, this manual is no longer valid.
Maintenance Responsibilities
Facility maintenance is ultimately the responsibility of the current property owner. At the
time of completing the stormwater design, dated April 1, 2024, stormwater maintenance
responsibility for this property belongs to:
Manke Family Resources,LLC
PO Box 1302
Shelton,Washington 98584
Maintenance Requirements
The stormwater management facilities provided in Attachment A include provisions for
inspection procedures and maintenance, when necessary. All stormwater facilities that
were designed for are accounted for. Maintenance procedures for additional components
are also provided, which consist of general practices for some of the selected drainage
features for this development. Only applicable facilities and components per the
stormwater design are required to be inspected and maintained.
ATTACHMENT A
No. 10-Filter Strips
Maintenance Defect or Condition When Recommended Maintenance to Correct
Component Problem Maintenance is Needed Problem
(-4,11 fal Sediment Sediment depth exceeds 2 Remove sediment deposits,re-level so
Accumulation on inches- slope is even and flows pass evenly through
Grass strip
Vegetation When the grass becomes Mow grass,control nuisance vegetation,
excessively tall(greater such that flow not impeded.Grass should be
than 10 inches),when mowed to a height between 3-4 inches,
nuisance weeds and other
vegetation starts to take
over.
Trash and Debris Trash and debris Remove trash and Debris from filter.
Accumulation accumulated on the filter
strip.
Erosion/Scouring Eroded or scoured areas For ruts or bare areas less than 12 inches
due to flow channelization, wide,repair the damaged area by filling with
or higher flows crushed gravel.The grass will creep in over
the rock in time If bare areas are large,
generally greater than 12 inches wide,the
filter strip should be re-graded and re-
seeded For smaller bare areas,overseed
when bare spots are evident
F'uw;apreader Flow spreader uneven or Level the spreader and clean so that flows
clogged so that flows are are spread evenly over entire filter width.
not uniformly distributed
through entire filter width.