HomeMy WebLinkAboutBLD2023-01253 Solar - BLD Inspections - 1/9/2024 (2) INSPECTION CARD
Mason County
615 W. Alder St.
Building 8, Shelton, WA 98584
360-427-9670 ext 352
www.masoncountywa.gov
PERMIT# BLD2023-01253 PROJECT ADDRESS 1961 N Lake Cushman Rd Hoodsport, WA 98548
PARCEL# 422103490180 PROJECT DESCRIPTION PV Solar Roof Mount Installation 1 circuit, 4.860kw
OWNER SPENCER CHRISTOPHER ADDRESS PO BOX 296 PHONE
CONTRACTOR SOLGEN POWER LLC ADDRESS 5100 ELM ROAD PHONE 509-931-1663
CONTRACTOR LICENSE SOLGEPL830RJ LENDER
INSPECTION INSP DATE Comments INSPECTION INSP DATE Comments
BLD-Final Inspection Q L
�Pak� Tb 140fk4 trw" P lury ^'• t- qr� ;t
Mason County
Mason County - Division of Community Development
615 W. Alder St.
Building 8
Shelton, WA 98584
360-427-9670 ext 352
www.masoncountywa.gov
FPROJECT
3-01253 ROOF MOUNT SOLAR PANEL-
RESIDENTIAL
ESCRIPTION: PV SOLAR ROOF MOUNT INSTALLATION 1 ISSUED: 10/16/2023
860KW
ESS: 1961 N LAKE CUSHMAN RD HOODSPORT EXPIRES: 04/13/2024
PARCEL: 422103490180
APPLICANT: SPENCER CHRISTOPHER OWNER: SPENCER CHRISTOPHER
PO BOX 296 PO BOX 296
HOODSPORT,WA 98548 HOODSPORT,WA 98548
CONTRACTOR: SOLGEN POWER LLC
5100 ELM ROAD
PASCO,WA 99301
509-931-1663
GENERAL CONTRACTOR'S LICENSE: SOLGEN POWER LLC License: SOLGEPL830RJ
5100 ELM ROAD Expires: 01/24/2024
PASCO,WA 99301
509-931-1663
FEES: Paid Due
Final Inspection $80.00 $0.00
State Fee-Residential $6.50 $0.00
Technology Surcharge $1.60 $0.00
Solar/PV Base Fee $30.00 $0.00
Solar/PV Fee $19.00 $0.00
Totals : $137.10 $0.00
REQUIRED INSPECTIONS
BLD-Final Inspection
CONDITIONS
Applicant has indicated this is a replacement unit. Prior to Mason County allowing any occupancy of the new proposed
unit, the existing unit which is on-site and is being replaced MUST be removed from the parcel.
Printed by:Nikita Huckabey on:11/15/2023 12:05 PM Page 1 of 3
Mason County
Mason County - Division of Community Development
615 W. Alder St.
Building 8
Shelton,WA 98584
360-427-9670 ext 352
www.masoncountywa.gov
ROOF MOUNT SOLAR PANEL-RESIDENTIAL BLD2023-01253
All furnace installations shall meet the minimum efficiencies set forth in the current edition of the Washington state energy
code (WSEC). any portion of the mechanical system that is altered or replaced shall meet the minimum standards set forth
in the WSEC and international mechanical code.
" The installation of solar(thermal or photovoltaic)energy systems to provide space heating or cooling, hot water and
swimming pool heating shall conform to Chapter 23 of the International Residential Code, Chapter 14 of the International
Mechanical Code, Uniform Plumbing Code, the International Fire Code, and be shall be listed and labeled in accordance
with UL1703.
Roof mounted panels shall weigh no more than 4 Ibs per square foot. Supports for solar panels are to be installed to spread
the dead load across as many roof-framing members as needed to ensure that no point loads in excess of 50-Ibs are
created. Panels may be installed on roof assemblies with a single layer of roofing material. Roof assemblies with more than
one roofing material layer shall require an engineered analysis demonstrating that the roof will support the additional load of
the solar panel system. Attachment to the roof shall be in accordance with manufacturer specifications provided during the
inspection by the Mason County Building Inspector.
Roof mounted equipment shall comply with the International Fire Code Section 605.11, including signage and access
pathways. Roof access points shall not be located in areas where access ladders would block window or doors openings.
Not less than two-3-foot wide access pathways shall be provided from the eave to ridge.
Ground-mounted panels and modules, installation must be in accordance with the manufacturer's instructions and be
available at time of inspection.
Inverters shall be listed and labeled in accordance with UL 1741. Systems connected to the utility grid shall use invertors
listed for the utility interaction
Collectors and thermal storage units shall be listed and labeled to show manufacturer's name, model number, serial number,
collector weight, collector maximum allowable temperatures and pressures, and the type of heat transfer fluids that are
compatible with the collector.
Connections to potable water supplies shall be provided with backflow protection in accordance with the Uniform Plumbing
Code. Solar energy systems containing pressurized fluids shall be protected with a temperature and pressure relief valve
and be protected from freeze damage. Systems shall be equipped with means to limit the maximum water temperature of
the system fluid entering or exchanging heat with any pressurized vessel inside the dwelling to 180 degrees Fahrenheit.
Solar energy collectors, controls, dampers, fans, blowers and pumps shall be accessible for inspection, maintenance, repair
and replacement. The roof shall be constructed to support the loads imposed by roof-mounted solar collectors and shall be
constructed of noncombustible materials,flashed and sealed to prevent entry of water, rodents, and insects. The building
inspector may require additional information, including an engineered design, to verify that existing roof or floor construction
are adequate to support the additional load of the solar energy equipment. When required provide an engineered design for
inspection.
" OWNER/BUILDER acknowledges submission of inaccurate information may result in a stop work order or permit
revocation. Acknowledgement of such is by signature below. I declare that I am the owner, owners legal representative, or
contractor. I further declare that I am entitled to receive this permit and to do the work as proposed. I have obtained
permission from all the necessary parties, including any easement holder or parties of interest regarding this project. The
owner or authorized agent represents that the information provided is accurate and grants employees of Mason County
access to the above described property and structure(s)for review and inspection. This permit/application becomes null &
void if work or authorized construction is not commenced within 180 days or if construction work is suspended for a period of
180 days. PROOF OF CONTINUATION OF WORK IS BY MEANS OF INSPECTION. INACTIVITY OF THIS PERMIT
APPLICATION OF 180 DAYS WILL INVALIDATE THE APPLICATION.
Printed by:Nikita Huckabey on:11/15/2023 12:05 PM
Page 2 of 3
Mason County
Mason County - Division of Community Development
615 W. Alder St.
Building 8
Shelton, WA 98584
360-427-9670 ext 352
www.masoncountywa.gov
ROOF MOUNT SOLAR PANEL-RESIDENTIAL BLD2023-01253
All construction must meet or exceed all local and state ordinances in addition to the International Codes requirements as
adopted and amended by Mason County and the State of Washington. Occupancy is limited to the approved and permitted
classification. Any non-approved change of use or occupancy would result in permit revocation.
Contractor registration laws are governed under RCW 18.27 and enforced by the WA State Dept of Labor and Industries,
Contractor Compliance Division. There are potential risks and monetary liabilities to the homeowner for using an
unregistered contractor. Further information can be obtained at 1-800-647-0982. The person signing this condition is either
the homeowner, agent for the owner or a registered contractor according to WA state law.
The demolition and disposal of debris must meet the regulations of Mason County and Olympic Region Clean Air Agency
(ORCAA).
It is unlawful for any person to cause or allow the demolition (or major renovation)of any structure unless all asbestos
containing materials have been identified and removed from the area to be demolished. Work shall not commence on an
asbestos project or demolition project unless the owner or operator has obtained written approval from ORCCA.2490 B
Limited Lane NW, Olympia WA 98502, 360.586.1044/800.422.5623 www.orcaa.org
I hereby certify that I have read and examined this application and know the same to be true and correct.
All provisions of Laws and Ordinances governing this type of work will be complied with whether
specified herein or not. The granting of a permit does not presume to give authority to violate or cancel
the provisions of any other state/local law regulating construction or the performance of construction.
Issued By:
Contractor or Authorized Agent: Date:
Printed by:Nikita Huckabey on:11/15/2023 12:05 PM Page 3 of 3