HomeMy WebLinkAboutRAP2008-00209 - RAP Permit / Conditions - 10/15/2008 ROD ACCESS PERMIT APPROVED RAP2008-00209
Mason County Road Department
415 North 6th ST Road Number. 50810
PO BOX 1850 Road Name: Shelton Springs 50810
Shelton, WA 98584
(360) 427-9670 ext 450 Road District: 101
Applicant: STEVE BEHLING Phone:
360-427-4152
11750 N US HWY 101
SHELTON, WA 98584
To Install: Commercial
Location: On the south side of Shelton Springs Rd . About the 1500 block.
Parcel kl"'i!' ber: 4201222901083
Legal Description: LOT: 3 OF SP #2956 OF TR 8 EX NW NW S 28/1
The road access permit is hereby approved, subject to any comments below
This permit shall be void and the bond forfeited to Mason County unless the work herein contemplated
shall have been completed on or before: 03/17/2009
Once the access has been completely installed, please notify the Public Works Dept. so we may conduct a
final inspection.
Specifications:
Access to be graveled to property line with 3" depth of clean gravel
Access will be staked and flagged by the permittee for the pre-inspection
Access will be inspected by this office prior to installation
Access installation shall be in accordance with Mason County specifications
Commercial /Multi use access shall require STOP sign(s), installed in conformance to the MUTCD manual, at intersection
with the county road
Culvert to be aluminum, concrete or polyethylene
Culvert will lay in line of ditch
Culvert to be a minim of 12" diameter by 30'length
Data at Shalt
�u.., � ..�,.,,�c , v ��1„ I tc,,, tehis 1, " uay of Sep«imber, 20003
Issued by: Title: 4'c
Culvert Required?: N Site Distance Left:GOOD Site Distance Right: GOOD Surface Type: Crushed Rock
Comments:
Access will need to be 40' wide at the road edge. Needs a 25' radius on each side. Access to slope
back from the road edge. Finish with crushed rock and compact.
Done By: Gary Corey
r
Access Connection Permit
Name f Applicant: Permit Number
a e and Address o pp Width 30 Asphalt
42803
Steven Arthur Behling
11750 N US 101 SR 101 MP 344.170 LT/RT Left
Shelton, WA 98584 LONGITUDE Region
LATITUDE Olympic
County Tax Parcel Number
Mason 42M--22=00060%:::�.00080
Government Lot Number 14 00$'1/....�Da
n/a
Phone (Optional) 360 427-4152 NW 1/4 of NW 1/4 of s 12 ,T 20N R 4
Permit Category Current Highway Classification
1 - Minimum Connection 11 - 1320' Minimum Approach Spacing Required
✓i, 2 - Minor Connection 2 -660' Minimum Approach Spacing Required
�! 3 - Major Connection ✓ 3 -330' Minimum Approach Spacing Required
4 -Temporary Connection 4 -250' Minimum Approach Spacing Required
5 - 125' Minimum Approach Spacing Required
Access Connection meets current Department location, spacing, and design criteria: 7 Conforming ✓.Non-Conforming Variance
The Applicant, hereinafter referred to as the"Grantee", having applied for a permit to construct/upgrade, use, and
maintain an access connection to serve:
Access to Retail Nursery and Espresso Stand.
Note: Chain Link Fencing will be installed along Grantee's Property Line (not on WSDOT right of Way).
Note: Entrance/Exit gate is to be positioned no closer than 30 feet from the US 101 White Edge Line (fog line).
The Washington State Department of Transportation or its designee, herein after referred to as the"Department",
hereby orders that this permit be granted, subject to the terms and provisions stated upon the General Provisions
hereof and Exhibits attached hereto and by this reference made a part hereof:
Exhibit A -Special Provisions for Highway Encroachments, 2 Pages
Exhibit B -WSDOT Right of Way Sheet, Shelton to Purdy Canyon, Page 1, Sheet 5 of 8 Sheets
Exhibit C -Owner's Site Plan, Page 1
Exhibit D -WSDOT Road Approach Design Template D1 (SU)
This permit shall be void unless the construction herein contemplated is started within 90 days of issuance and completed
within 120 days of issuance, unless otherwise provided herein.
This permit is adepted and approved by the antee, subject to the terms and provisions as herein set forth.
PERMIT HOL DEPARTMENT OF TRANSPORTATION
By: By: „c�( (
v
DALE C. SEVERSON, P.E.
Title: /V7T Title: Development Services Engineer
Date: ' e o' a OD 8, Date:
RAMPS-Access Connection Permit-Page 1
AdMk
Washington State Olympic Region Headquarters
Department of Transportation 5720 Capitol Boulevard,Tumwater
Paula J. Hammond, P.E. P.O.Box 47440
Secretary of Transportation Olympia,WA 98504-7440
360-357-2600
Fax 360-357-2601
TTY 1-800-833-6388
January 14, 2009 www.wsdot.wa.gov
Steven Behling R E C E I V E D
11750 N US 101 JAN 15 2009
Shelton, WA 98584
R SM CO.RAN"DEPT.
RE: Access Connection Permit No. 42803
US 101, Mile Post 344.170
Retail Nursery and Espresso Stand
Dear Mr. Behling:
Thank you for your prompt attention and return of the permit documents. Enclosed
is a copy of your executed General Permit.
Prior to performing any work on this project, a pre-construction conference is
required per Provision No. 2 of the attached Exhibit "A" Special Provisions for
Highway Encroachments. Please contact Larry Deemer, Assistant Superintendent, of
our Port Orchard Maintenance Office, at (360) 874-3050, to schedule this required
meeting.
The property owner has full responsibility that all work completed on this project,
p P Y P Y P p J
within the state right-of-way, will be to current state standards.
If you have any questions about this permit, please contact me at (360) 357-2736.
it
Sincerely,
Dale C. Severson, P.E.
Development Services Engineer
WSDOT, Olympic Region
DCS:pr
DLM
Enclosures
cc: Mason County Community Development, PO Box 279, Shelton, WA 98584
Larry Deemer,Asst. Superintendent,Port Orchard, WB-12
General Provisions
1. The Permit Holder, its successors and assigns,agrees to protect the State of Washington,its officers and employees and save them harmless
from all claims,actions or damages of every kind and description which may accrue to or be suffered by any person,persons,or property
by reason of the acts or omissions of the Permit Holder, its assigns,agents,contractors, licensees,employees or any person whomsoever, in
connection with Permit Holder's, its assigns',agents',contractors', licensees'or employees'construction,installation,maintenance,operation,
use or occupancy of the right of way or in the exercise of this permit. In case any suit or action is brought against the State of Washington,
its officers and employees,arising out of or by reason of any of the above causes,the Permit Holder, its successors or assigns will, upon notice
of such action,defend the same at its sole cost and expense and satisfy any judgement against the State of Washington, its officers,or
employees:PROVIDED,that if the claims or damages are caused by or result from the concurrent negligence of(a)the State of
Washington's agents or employees and(b)the Permit Holder or Permit Holder's agents or employees,this indemnity provision shall be valid and
enforceable only to the extent of the negligence of the Permit Holder or the Permit Holder's agents or employees.
The Permit Holder,and on behalf of its assigns,agents, licensees,contractors and employees agrees to waive any claims for losses, expenses,
damages or lost revenues incurred by it or its agents,contractors, licensees,employees or customers in connection with Permit Holder's, its
assigns', agents',contractors', licensees'or employees'construction, installation, maintenance,operation, use or occupancy of the right of
way or in the exercise of this permit against the State of Washington, its agents or employees except the reasonable costs of repair to
property resulting from the negligent injury or damage to Permit Holder's property by the State of Washington, its agents,contractors or
employees.
2. During the progress of the work,such barriers shall be erected and maintained as may be necessary or as may be directed for the protection
of the traveling public;the barriers shall be properly lighted at night.
3. Except as herein authorized, no excavation shall be made or obstacle placed within the limits of the State highway in such a manner as to
interfere with the travel over said road.
4. If the work done under this permit interferes in any way with the drainage of the State highway,the Permit Holder shall wholly and at its own
expense make such provision as the Department may direct to take care of said drainage.
5. Permit Holder hereby authorizes the Department to enter upon their lands where necessary to construct or reconstruct the permitted access
connection and/or construct and maintain traffic control devices and appurtenances.
6. The access connection shall be maintained between the right of way line and the shoulder line of said(highway,frontage service road of said
highway, highway and/or frontage service road,'="Line of said highway)by the Permit Holder,their heirs,successors or assigns.
7. On completion of said work herein contemplated,all rubbish and debris shall be immediately removed and the roadway and roadside shall be
left neat and presentable and satisfactory to the Department.
8. The cost of construction or modification of a connection shall be the responsibility of the Permit Holder, including the cost of modification of any
connection required as a result of changes on property site use in accordance with WAC 468-51-110.
g. The Department hereby reserves the right to order the change of location or the removal of any structure or structures authorized by this
permit at any time,said change or removal to be made at the sole expense of the party or parties to whom this permit is issured,or their
successors and assigns.
10. Existing permitted connections impacted by the Department's work program and which, in the consideration of the Department, necessitate
modification,relocation,or replacement in order to meet current Department connection location,quantity, spacing,and design standards,
shall be modified,relocated,or replaced in kind by the Department at no cost to the Permit Holder. The cost of further enhancements or
modification to the altered, relocated,or replaced connections desired by the Permit Holder shall be the responsibility of the Permit Holder.
11. If any changes are made or proposed in the land use,intensity of development,type of traffic,or traffic flow of the property served by this
connection permit,the Permit Holder is required to contact the Department to determine if further analysis is needed to determine if the change is
significant and would require a new permit and modifications to the connection.
12, All such changes, reconstruction,or relocation by the Permit Holder shall be done in such manner as will cause the least interference with any of
the Department's work, and the Department shall in no way be held liable for any damage to the Permit Holder by reason of any such work by the
Department,its agents or representatives,or by the exercise of any rights by the Department upon roads,streets,public places,or structures
in question.
13. This permit or privilege shall not be deemed or held to be an exclusive one and shall not prohibit the Department from granting other permits
or franchise rights of like or other nature to other public or private companies or individuals, nor shall it prevent the Department from using
any of its roads,streets,or public places,or affect its right to full supervision and control over all or any part of them, none of which is hereby
surrendered.
14. The Department may revoke, amend,or cancel this permit or any of the provisions thereof at any time by giving written notice to the Permit Holder.
The Permit Holder shall immediately remove all facilities from the right of way. Any facilities remaining upon the right of way 30 days after written
notice of cancellation shall be removed by the Department at the Permit Holder's expense.
15. It is the responsibility of the apllicant or Permit Holder to obtain any other local permits or other agency approvals that may be required, including
satisfaction of all environmental regulations. It is also the responsibility of the Permit Holder to acquire any property rights necessary to provide
continuity from the applicant's property to the Department's right-of-way if the Permit Holder's property does not abut the right of way.
16. The party or parties to whom this permit is issued shall maintain at its or their sole expense the structure or object for which this permit is
granted in a condition satisfactory to the Department.
17. Any breach of any of the conditions and requirements herein made,or failure on the part of the Permit Holder of this permit to proceed with due
diligence and in good faith after its acceptance,with construction work hereunder,shall subject this permit to cancellation as herein provided.
18. This permit is subject to all applicable provisions of 468-51 WAC,468-52 WAC, Chapter 47.50 RCW,Chapter 47.32 RCW,and/or
Chapter 47.44 RCW,and amendments thereto.
RAMPS-Access Connection Permit-Page 2
Special Provisions for
Highway Encroachments
Permit No. 42803
Applicable provisions are denoted by
✓ 1. No work provided for herein shall be performed until the Permit Holder is authorized by the following Department representative:
Larry Deemer, Asst. Maint. Supt.
WSDOT Port Orchard Maintenance
8293 Spring Creek Road SE
Port Orchard,WA 98367
(360) 874-3050
V, 2. Prior to the beginning of construction,a preconstruction conference shall be held at which the Department and the Permit Holder and Permit Holder's
engineer,contractor,and inspector shall be present.
✓' 3. Should the Permit Holder choose to perform the work outlined herein with other than its own forces, a representative of the Permit Holder shall be
present at all times unless otherwise agreed to by the Department representative. All contact between the Department and the Permit Holder's
contractor shall be through the representative of the Permit Holder. Where the Permit Holder chooses to perform the work with its own forces,it
may elect to appoint one of its own employees engaged in the construction as its representative. Failure to comply with this provision shall be
grounds for restricting any further work by the Permit Holder within the State right of way until said requirement is met. The Permit Holder, at its
own expense,shall adequately police and supervise all work on the above described project by itself, its contractor,subcontractor, agent, and
others,so as not to endanger or injure any person or property.
✓ 4. A copy of the permit must be on the job site and protected from the elements at all times during any of the construction authorized by said permit.
✓ 5. This permit does not give the Permit Holder or any agent or contractor of the Permit Holder any rights to cut,spray, retard,remove,destroy,
damage,disfigure or in any way modify the physical condition of any vegetative material located on the highway right of way, except by written
permission from the Department or for purposes as described by No.6 if denoted below. All restoration shall be done to the satisfaction of the
Department at the sole expense of the Permit Holder.
✓ 6. If necessary to increase sight distance, brush shall be removed from both sides of the access connection and stumps shall be removed.
The indiscriminate cutting of merchantable timber or disfiguring of any feature of scenic value shall not be permitted.
7. The access connection(s)shall be constructed in accordance with the attached Exhibit D -SU
Sufficient length of 12" diameter culvert pipe shall be placed in ditch and laid to a true line and grade.
The access connection(s)shall be surfaced to the limits as shown on the plan with a 150 millimeter(6 inch)minimum compacted depth of gravel
base material and a 80 millimeter(3 inch)compacted depth of crushed surfacing top course. Asphalt paving will not be required. Finished grade
of the access connection shall be in accordance with the profile control as shown on the attached plan. Directing of surface water from private
property to Department right of way will not be permitted, unless otherwise approved by the Department.
8. The access connection(s)shall be constructed in accordance with the attached
Sufficient length of diameter culvert pipe shall be placed in ditch and laid to a true line and grade.
The access connection(s)shall be surfaced to the limits as shown on the plan with a 150 millimeter(6 inch)minimum compacted depth of gravel
base material,a 80 millimeter(3 inch)minimum compacted depth of crushed surfacing top course,and paved with a 80 millimeter(3 inch)
minimum compacted depth of Asphaltic Concrete Class B unless otherwise specified by the Department. Any existing oil mat on shoulder or
roadway shall be removed and new pavement laid to a butt joint with existing pavement. Finished grade of new pavement shall be in accordance
with the profile control as shown on attached plan. Directing of surface water from private property onto Department right of way will not be
permitted, unless otherwise approved by the Department.
✓, 9. All buildings and appurtenances shall be so located at a distance from the right of way line of any State Highway that none of the right of way
therefore is required for use of the patrons or customers of any such establishment. Permit Holder shall comply with local building codes. Set-back
requirements for the location of buildingts in relation to the right of way line are a function of local authorities,and they should be consulted
regarding requirements that must be adhered to.
RAMPS-Special Provisions-Page 1 Page 1 '
9 Exhibit 'A"
10. The Permit Holder agrees to schedule the work herein referred to and perform said work in such a manner as not to delay the Department's
contractor in the performance of his contract.
✓ 11. Work within the right of way shall be restricted to between the hours of 8:00 AM and 4:00 PM and/or
,and no work shall
be allowed on the right of way Saturday,Sunday,or holidays,unless authorized by the Department. Any lane closures must be submitted for
approval in advance of use. The hours of permitted closure may differ from the above noted hours.
✓ 12. The shoulders,where disturbed,shall be surfaced with crushed surfacing top course minimum compacted
depth,or as directed by the Department. The surface of the finished shoulder shall slope down from the edge of pavement at
the rate of 5%unless otherwise directed. The restored shoulder must not have any strips or sections less than 0.6 meters(2 feet)wide.
The restored shoulder shall be surfaced with Asphalt Concrete Pavement
•✓'' 13. The Permit Holder shall be responsible for constructing and maintaining the access connection(s)and appurtenances between the shoulder line of
the highway and the right of way line inclusive of surfacing and drainage. The Department has the right to inspect all installations at the time of
construction and at any time afterward and to require that necessary changes and repairs be made. Unsatisfactory work will be corrected by the
Department, at the Permit Holder's expense,or access may be removed at the Permit Holder's expense. Directing of surface water from private
property onto Department right of way will not be permitted.
✓ 14. The access aconnection shall be sufficiently surfaced back an adequate distance from the edge of the pavement to prevent any tracking of
material onto the highway. Any tracking of material onto the highway shall be subject to enforcement of Chapter 46.61.655 RCW and shall be
immediately cleaned up by the Permit Holder or the Permit Holder's agent.
15. Standard highway warning signs designated as"Truck Crossing"sign, plate W8-6,shall be placed and maintained at Permit Holder's expense on
each side of the access connection. Signs shall be in evidence only when access is actually being used. If necessary,flagmen shall be
provided. Sufficient parking space shall be provided by the Permit Holder outside Department right of way so no vehicles will be parked on
said right of way.
✓ 16. All manholes,valve covers,and like appurtenances shall be constructed at such an elevation to conform to the shoulder slope from the edge of
pavement or as directed by the Department.
_✓ 17. All slopes,slope treatment,top soil,ditches,pipes,etc.,disturbed by this operation shall be restored to their original cross section and
condition. All hazards shall be marked by warning signs,barricades,and lights. If necessary,flagmenshall be employed for the purpose of
protecting the traveling public. Roadside operations shall be specified by the Department's representative.
✓ 18. During the construction and/or maintenance of this facility,the Permit Holder shall comply with the Manual on Uniform Traffic Control Devices for
Streets and Highways, (Federal Highway Administration)and Washington modifications thereto. If determined necessary by the Department,
the Permit Holder shall submit a signing and traffic control plan to the Department's representative for approval prior to construction or maintenance
operations. No lane closures shall be allowed except as approved by the Department representative. Approvals may cause revision of special
provisions,including hours of operation.
19. Bond coverage required to ensure proper compliance with all terms and conditions of said permit will be furnished by a Blanket Surety Bond
held by the Department at the Olympia Service Center.
20. A surety bond in the amount of written by a surety company authorized to do business in the State of Washington
shall be furnished to ensure compliance with any and all of the terms and conditions of this permit and shall remain in force until
all work under this permit has been completed and approved by the Department.
✓ 21. Relative to advertising adjacent to all State highways,we wish to call your attention to the Sceni Vistas Act of 1971,Chapter 47.42 RCW and
State Transportation Commission ruling Chapter 468-66 WAC. Violation of this section of the statutes will be sufficient cause for cancellation
of this permit. On-premise signs are allowed.
22. The Permit Holder shall notify the Department's representative upon completion of the work under this permit so that a final inspection can be made.
✓' 23. The responsibility of the Permit Holder for proper performance, safe conduct, and adequate policing and supervision of the project shall not be
lessened or otherwise affected by Department approval of plans,specifications,or work,or by the presence at the work site of Department
representatives,or by compliance by the Grantee with any requests or recommendations made by such representatives.
✓! 24. All material and workmanship shall conform to the Washington State Department of Transportation Standard Specifications for Road, Bridge
and Municipal Construction,current edition,and amendments thereto,and shall be subject to inspection by the Department.
RAMPS-Special Provisions-Page 2 Page 2 Exhibit"A"
i
1:20N.,R.4W. W.M: -
�^
NE%4 NEY4 Sec 11
p gIICT, ' EYI SE* Sec 2 X �^►
SW% NW* Scc12
5corra si'��• ,
;e
$
..
'1•I�J.!/�{� yy,, �' _ __ O.]r iTA.16ai.O EA s A Of00 CO RD
3-IMO a-N a0•oo
' tl �C' S/ .�t�+v�.. }OT=01 � OCIi•.s•A° a rN�9'ciewlnG•°p'a9n�T•0'lsn
..AA 0 Oe• 400 f,.vJ Clua,'C
r sr I •oo e.....ea. /�•' v" acix � Sti "6• a �r .
}Om9 lM ]0'Lr•),INede•a iee H.1 \ MI ♦ /
a c+.w.cwz• .. \\ :•/ Q NEY4 5E16 S+c 2
'Tk to
l•,•. // / TO COUNTY-C
Sec.12 /4 Oe ii L I \ 3'�/ COUNTY. Y 0.GD.}N:Bi,: / r}•�
j st I/a N W%a sa f p'rgr.• — — -� • SR 101
w a
SVJ� 'S !4 5.c 1 / vim````•. �.,f .: "•:";.°:e,•.
\ ' �4� e s,�x•. I �� M�MABONCOVNTV—
�• r Ll Mdit Na H]•W r Nt IET•00 NEP
-OG331 NIKLETHUN LWNYR 9•t4 Ae O.ODAr. ).tl e. ! R / �\ .„• .. I •••••.^"^.•r+••-'•'•••.•a•••`°^-••'•a•
•T M.i !-Ociio ifvKE ♦.�1 As. •o. r /•.�� \\ .e m~ w.�wo.°i w..ac ..}i•} •..•w.......n.•••... 'a(.•../-
!� ac.O+) FLO[KINGIR V1,1 Q%Ac O.OJ Ac O-)tA• . �.-I \ � H a
2-06— AT O SHE LTON N . O. 4c •O.4DAa! I•./ y •••1••p lIN tOa 'y�•OP/ qO M+.Mtii4.H w��/r•ti°�Y y "'r
\\ \ -_ Ma 1 MI Ixd NAL.W ah i�Cwn•Y Jl11J61:_— ,
P.R L-. NAKE WT]L AIYA qlw v, fRNMMDER RT EA�H'T �,• • \ .RLtIJLe _N 111�1. 1 -11�.1 D .. -... •ww.•e ew,M r wrw
OWNERSHIPS \ _ xl�1A
yl-I�t:r O a.leE:ra r
z4
ILT
!o!—3l11
1•i i 07 - PODT W NELTON SIEET N0.♦ cl
I t t T
j t • ]-OM NYE ]4a. 0.T M T iro�Mn) s
1 � �i T a sE4nL-r si o Ac �+ gel MILE 24 g
Clwring 44 Awe
Grvoblrrqq PO C$,�
F^l SYf E]eovaibl�:mon 01 OIYd s.t
•OON]TMICTMMI PEt]IT iZ. 3trwtura 40 >t:�
O SEE JMT i I011 TOTAL PARCEL PETAL d Overi—,1004}}. 3290 d
CmcreTe Clain• 4%
i PbMC=Pi,.%VD,.. EO U.Ft
Raul - 16.• 114
Y4 70
]W
goo .: •, Y IC.
Imp I
zs�
='N lol d8
Oct 27 08 01 : 30p Valerie Campo 360 427 4152 p. 4
wvA
I
f i i
, , I
_
ram_
r ,
- l
,
t 1 aiL r
- .1,E _3
_ _ I
• f
,
-
,
r
-r
KAL
LL
i
-T-
Exhibit"C"
Variable
Normal shoulder plus 1 ft
Match shoulder o Ipe lam— Curb as required
Slope
7(,
maXEdge of traveled�s as required. 12 in nin diameter culvert pipe
Profile Controls
115 ft minim 11� 5 ft minim
c
o! Ei m ►► I I a! O
N I ; I I o_ Right of way
Edge of shoulder ; my ►Paving limit)
_ E I H �� Edge of shoulder
25:1 taper to ��C �IF ! — 25:1 taper to
existing '\, .� ► i existing
j—A �� J
- -----------
state highway J
Taper B Edge of traveled way
Asphalt concrete pavement
Condition A B C D E F j G H J
Primary SU and less — — Q) 30 15 — — 30 M
— —Primary combination Vehicle WB 40 fZ 65 15 — — 55 0
4 25 M 50 15 7 25 45 L22
Primary combination Vehicle WB 50 — — L1 70 20 — — 50 L�
and doubles 4 25 U3 55 20 — — 50
Notes:
M All values in ft L5) Vertical curves between the shoulder slope and the
(2) Normal shoulder width.(See Chapter 440.) road approach grade not to exceed a 3'/,in hump or a
2 in depression in a 10 ft cord.
j3� Normal shoulder width less A.
(4) For larger vehicles,use turning templates.
(See Chapter 910.)
Road Approach Design Template D1
Figure 920-5
Design Manual Exhibit "D" Road Approaches