CONCRETE INSPECTION AND TEST REPORT
CLIENT: POE Construction, Inc . DATE OF INSPECTION: 7/5/94
PROJECT: AERO Controls Addition REPORT NO: 8
CONTRACTOR: POE Construction, Inc . PROJECT NO: 94 . 05-11
INSPECTOR: S Bassett CONCRETE SUPPLIER: Miles Sand &
Gravel
FORMS INSPECTED: ---- REBAR INSPECTED: ----
REMARKS: -------
PLACEMENT METHOD: chute CONSOLIDATION METHOD: vibration
LOCATION OF PLACEMENT: center of north slab
LOCATION SAMPLED: same as above
SLUMP: 4 " AIR: ---- % CUBIC YDS . PLACED: 11
CEMENT: 5 . 5 SK. TYPE: ----- MAX. SIZE AGGR: -----
ADMIXTURES: ---------- AMOUNT: ---------
CONC TEMP: 66 . 90 AIR TEMP: 55 . 20 WEATHER: clear
NO. CYLINDERS CAST: 3 TIME SAMPLED: 0824 TRUCK NO: 107
DESIGN STRENGTH: 3000
CYL NO. LAB NO. DATE TESTED AGE PSI
31 6372 7/12/94 7 3780
32 6373 8/2/94 28
33 6373 8/2/94 28
2401 Bristol Court S.W. • P.O. Box 10267 • Olympia, WA 98502 • Phone (206) 357-7883 • FAX (206) 754-4240
Bradley-Noble Geotechnical Comp
P
Geotechnical Consulting
Construction Testing and Inspecting Services
�'FNF / 01994
CONCRETE INSPECTION AND TEST REPORT
S
CLIENT: POE Construction DATE OF INSPECTION: 6/16/94
PROJECT: AERO Controls REPORT NO: 7
CONTRACTOR: POE PROJECT NO: 94 . 05-11
INSPECTOR: S . Bassett CONCRETE SUPPLIER: Miles S & G
FORMS INSPECTED: ----- P.EBAR INSPECTED: -----
REMARKS: -----
PLACEMENT METHOD: pump CONSOLIDATION METHOD: vibratory scree
LOCATION OF PLACEMENT: slab st northeast corner and south side; slab and
footing for loading dock
LOCATION SAMPLED: Set l: east end of south side; Set 2 : west end of south
side
SLUMP: 4 " AIR: ---- % CUBIC YDS . PLACED: 229
CEMENT: 5 . 5 SK. TYPE: ---- MAX. SIZE AGGR: 7/8"
ADMIXTURES: ------ AMOUNT: -----
CONC TEMP: 65 . 90 AIR TEMP: 60 . 70 WEATHER: clear
68 . 6 62 . 8
NO. CYLINDERS CAST: 3 TIME SAMPLED: 0905 TRUCK NO: 012
3 i i30 016
DESIGN STRENGTH: 3000
CYL NO. LAB NO. DATE TESTED AGE PSI
25 6301 6/23/94 7 3180
26 6302 7/14/94 28 4420
27 6303 7/14/94 28 4190
28 6304 6/23/94 7 3330
29 6305 7/14/94 28 4010
30 6306 7/14/94 28 4460
2401 Bristol Court S.W. • P.O. Box 10267 • Olympia, WA 98502 • Phone(206) 357-7883 • FAX (206) 754-4240
Bradley-Noble Geotechnical ComMan
tto�
Geotechnical Consulting Rul
Construction Testing and Inspecting Services n F
J U N 2 9 T51:
CONCRETE INSPECTION AND TEST REPORT gENERAL SERVICES
CLIENT: POE Construction DATE OF INSPECTION: 6/16/94
PROJECT: AERO Controls REPORT NO: 7
CONTRACTOR: POE PROJECT NO: 94 . 05-11
INSPECTOR: S . Bassett CONCRETE SUPPLIER: Miles S & G
FORMS INSPECTED: ----- REBAR INSPECTED: -----
REMARKS: -----
PLACEMENT METHOD: pump CONSOLIDATION METHOD: vibratory scree
LOCATION OF PLACEMENT: slab st northeast corner and south side; slab and
footing for loading dock
LOCATION SAMPLED: Set 1: east end of south side; Set 2 : west end of south
side
SLUMP: 4 " AIR: ---- % CUBIC YDS. PLACED: 229
CEMENT: 5 . 5 SK. TYPE: ---- MAX. SIZE AGGR: 7/8 "
ADMIXTURES: ------ AMOUNT: -----
CONC TEMP: 65 . 90 AIR TEMP: 60 . 70 WEATHER: clear
68 . 6 62 . 8
NO. CYLINDERS CAST: 3 TIME SAMPLED: 0905 TRUCK NO: 012
113ii 016
DESIGN STRENGTH: 3000
CYL NO. LAB NO. DATE TESTED AGE PSI
25 6301 6/23/94 7 3180
26 6302 7/14/94 28
27 6303 7/14/94 28
28 6304 6/23/94 7 3330
29 6305 7/14/94 28
30 6306 7/14/94 28
2401 Bristol Court S.W. • P.O. Box 10267 • Olympia, WA 98502 • Phone (206) 357-7883 • FAX (206) 754-4240
Bradley-Noble Geotechnical Company
Geotechnical Consulting
Construction Testing and Inspecting Services
CONCRETE INSPECTION AND TEST REPORT
CLIENT: POE Construction DATE OF INSPECTION: 6/15/94
PROJECT: AERO Controls REPORT NO: 6
CONTRACTOR: POE PROJECT NO: 94 . 05-11
INSPECTOR: S . Bassett CONCRETE SUPPLIER: Miles S & G
FORMS INSPECTED: ----- REBAR INSPECTED: -----
REMARKS: -----
PLACEMENT METHOD: chute CONSOLIDATION METHOD: vibration
LOCATION OF PLACEMENT: grade beam at southwest corner and at northwest
corner of existing building
LOCATION SAMPLED: grade beam at southwest corner
SLUMP: 4 " AIR: ---- % CUBIC YDS. PLACED: 20
CEMENT: 5 . 5 SK. TYPE: ---- MAX. SIZE AGGR: 7/8"
ADMIXTURES: ------ AMOUNT: -----
CONC TEMP: 69 . 30 AIR TEMP: 61 . 90 WEATHER: overcast
NO. CYLINDERS CAST: 3 TIME SAMPLED: 1230 TRUCK NO: 012
DESIGN STRENGTH: 3000
CYL NO. LAB NO. DATE TESTED AGE PSI
22 6298 6/22/94 7 3180
23 6299 7/13/94 28
24 6300 7/13/94 28
2401 Bristol Court S.W. • P.O. Box 10267 • Olympia, WA 98502 • Phone (206) 357-7883 • FAX (206) 754-4240
Bradley-Noble Geotechnical Comp Ee
Geotechnical Consulting
Construction Testing and Inspecting Services J(�
�+ 191
9g4 _
CONCRETE INSPECTION AND TEST REPORT
�7 CFS
CLIENT: POE Construction DATE OF INSPECTION: 6/15/94
PROJECT: AERO Controls REPORT NO: 6
CONTRACTOR: POE PROJECT NO: 94 . 05-11
INSPECTOR: S . Bassett CONCRETE SUPPLIER: Miles S & G
FORMS INSPECTED: ----- REBAR INSPECTED: -----
REMARKS: -----
PLACEMENT METHOD: chute CONSOLIDATION METHOD: vibration
LOCATION OF PLACEMENT: grade beam at southwest corner and at northwest
corner of existing building
LOCATION SAMPLED: grade beam at southwest corner
SLUMP: 4 " AIR: ---- % CUBIC YDS . PLACED: 20
CEMENT: 5 . 5 SK. TYPE: ---- MAX. SIZE AGGR: 7/8 "
ADMIXTURES: ------ AMOUNT: -----
CONC TEMP. 69 . 30 AIR TEMP. 61 . 90 WEATHER overcast
NO. CYLINDERS CAST: 3 TIME SAMPLED: 1230 TRUCK NO: 012
DESIGN STRENGTH: 3000
CYL NO. LAB NO. DATE TESTED AGE PSI
22 6298 6/22/94 7 3180
23 6299 7/13/94 28 5010
24 6300 7/13/94 28 4890
2401 Bristol Court S.W. • P.O. Box 10267 • Olympia, WA 98502 • Phone (206) 357-7883 - FAX (206) 754-4240
Bradley-Noble Geotechnical Com P4 ire$,
Geotechnical Consulting
Construction Testing and Inspecting Services ✓Uk 1
INSPECTION AND TEST REPORT
CONCRETE
CLIENT: POE Constsruction DATE OF INSPECTION: 6/10/94
PROJECT: AERO Controls Addition REPORT NO: 5
CONTRACTOR: POE Construction PROJECT NO: 94 . 05-11
INSPECTOR: S . Bassett CONCRETE SUPPLIER: Miles Sand &
Gravel
FORMS TiSPECTED: yes REBAR INSPECTED: yes
REMARKS: Mesh was pulled during placement.
PLACEMENT METHOD: pump CONSOLIDATION METHOD: vibration
LOCATION OF PLACEMENT: slab, south center section and north side section;
south side wall for loading dock
LOCATION SAMPLED: Set 1: center of south center section; Set 2 : center of
north side section
SLUMP: 4 "-4 .5 " AIR: ---- % CUBIC YDS . PLACED: 329
CEMENT: 5 . 5 SK. TYPE: ---- MAX. SIZE AGGR: 7/8 "
ADMIXTURES: none listed AMOUNT: ----------
CONC TEMP: 69 . 70 AIR TEMP: 64 . 30 WEATHER: clear, sunshine
74 . 7 76 . 2
NO. CYLINDERS CAST: 3 TIME SAMPLED: 0930 TRUCK NO: 015
3 1�4'_v iu'.'
DESIGN STRENGTH: 3000
CYL NO. LAB NO. DATE TESTED AGE PSI
16 6285 6/17/94 7 3310
17 6286 7/8/94 28 5180
18 6287 7/8/94 28 5400
19 6288 6/17/94 7 3440
20 6289 7/8/94 28 5090
21 6290 7/8/94 28 5510
2401 Bristol Court S.W. • P.O. Box 10267 • Olympia, WA 98502 • Phone (206) 357-7883 - FAX (206) 754-4240
Bradley Noble Geotechnical Compfi�
Geotechnical Consulting JUIV � �}
Construction Testing and Inspecting Services
0002!:,o e-,'ENERALSERVICES
njjt>5 1-5 CONCRETE INSPECTION AND TEST REPORT
,Ibhn
CLIENT: POE Constsruction DATE OF INSPECTION: 6/10/94
PROJECT: AERO Controls Addition REPORT NO: 5
CONTRACTOR: POE Construction PROJECT NO: 94 . 05-11
INSPECTOR: S . Bassett CONCRETE SUPPLIER: Miles Sand &
Gravel
FORHS INSPECTED: yes REBAR INSPECTED: yes
REMARKS: Mesh was pulled during placement.
PLACEMENT METHOD: pump CONSOLIDATION METHOD: vibration
LOCATION OF PLACEMENT: slab, south center section and north side section;
south side wall for loading dock
LOCATION SAMPLED: Set 1: center of south center section; Set 2 : center of
north side section
SLUMP: 4 "-4 . 5 " AIR: ---- % CUBIC YDS . PLACED: 329
CEMENT: 5 . 5 SK. TYPE: ---- MAX. SIZE AGGR: 7/8"
ADMIXTURES: none listed AMOUNT: ----------
CONC TEMP: 69 . 70 AIR TEMP: 64 . 30 WEATHER: clear, sunshine
74 . 7 76 .2
NO. CYLINDERS CAST: 3 TIME SAMPLED: 0930 TRUCK NO: 015
3 1240 107
DESIGN STRENGTH: 3000
CYL NO. LAB NO. DATE TESTED AGE PSI
16 6285 6/17/94 7 3310
17 6286 7/8/94 28
18 6287 7/8/94 28
19 6288 6/17/94 7 3440
20 6289 7/8/94 28
21 6290 7/8/94 28
2401 Bristol Court S.W. • P.O. Box 10267 • Olympia, WA 98502 • Phone (206) 357-7883 • FAX (206) 754-4240
Bradley-Noble Geotechnical Comp ->
Geotechnical Consulting ,} �✓
Construction Testing and Inspecting Service
CONCRETE INSPECTION AND TEST REPORT GENERAL SURV1ICES
CLIENT: POE Construction DATE OF INSPECTION: 6/9/94
PROJECT: Aero Controls Addition REPORT NO: 4
CONTRACTOR: POE Construction PROJECT NO: 94 . 05-11
INSPECTOR: S . Bassett CONCRETE SUPPLIER: Miles Sand &
Gravel
FORMS INSPECTED: yes REBAR INSPECTED: yes
REMARKS: Resteel was per plans .
PLACEMENT METHOD: chute CONSOLIDATION METHOD: vibration
LOCATION OF PLACEMENT: north side of building footing from about center to
LOCATION SAMPLED: footing on north side of guilding
SLUMP: 4 . 5 " AIR: ---- % CUBIC YDS . PLACED: 20
CEMENT: 5 .5 SK. TYPE: ---- MAX. SIZE AGGR: 7/8 "
ADMIXTURES: none listed AMOUNT: -----
CONC TEMP: 73 . 7 ° AIR TEMP: 67 . 00 WEATHER: clear
NO. CYLINDERS CAST: 3 TIME SAMPLED: 1100 TRUCK NO: 012
DESIGN STRENGTH: 3000
CYL NO. LAB NO. DATE TESTED AGE PSI
13 6282 6/16/94 7 3400
14 6283 7/7/94 28 4290
15 6284 7/7/94 28 4400
2401 Bristol Court S.W. • P.O. Box 10267 • Olympia, WA 98502 • Phone (206) 357-7883 • FAX (206) 754-4240
Bradley-Noble Geotechnical Company
Geotechnical Consulting P.
Construction Testing and Inspecting Services
JUo � �> •1�r,f
CONCRETE INSPECTION AND TEST REPORT
aENERAL SERVICES
CLIENT: POE Construction DATE OF INSPECTION: 6/9/94
PROJECT: Aero Controls Addition REPORT NO: 4
CONTRACTOR: POE Construction PROJECT NO: 94 . 05-11
INSPECTOR: S. Bassett CONCRETE SUPPLIER: Miles Sand &
Gravel
FORKS INSPECTED: yes REBAR INSPECTED: yes
REMARKS: Resteel was per plans .
PLACEMENT METHOD: chute CONSOLIDATION METHOD: vibration
LOCATION OF PLACEMENT: north side of building footing from about center to
LOCATION SAMPLED: footing on north side of guilding
SLUMP: 4 .5" AIR: ---- % CUBIC YDS. PLACED: 20
CEMENT: 5.5 SK. TYPE: ---- MAX. SIZE AGGR: 7/8"
ADMIXTURES: none listed AMOUNT: -----
CONC TEMP: 73 . 70 AIR TEMP: 67 .00 WEATHER: clear
NO. CYLINDERS CAST: 3 TIME SAMPLED: 1100 TRUCK NO: 012
DESIGN STRENGTH: 3000
CYL NO. LAB NO. DATE TESTED AGE PSI
13 6282 6/16/94 7 3400
14 6283 7/7/94 28
15 6284 7/7/94 28
2401 Bristol Court S.W. • P.O. Box 10267 • Olympia, WA 98502 - Phone (206) 357-7883 • FAX (206) 754-4240
I
Bradley-Noble Geotechnical Com
Geotechnical Consulting M Ilk
Construction Testing and Inspecting Services 0
JUiv
CONCRETE INSPECTION AND TEST REPORT GENERAL SERVICES
CLIENT: POE Construction DATE OF INSPECTION: 6/8/94
PROJECT: AERO Controls Addition REPORT NO: 3
CONTRACTOR: POE Construction PROJECT NO: 94 . 05-11
INSPECTOR: D. Strong CONCRETE SUPPLIER: Miles Sand &
Gravel
FORMS 11:S111ECTED: yes PEBAR INSPECTED: yes
REMARKS: Mesh was pulled during plaacement; edges were vibrated.
PLACEMENT METHOD: chute CONSOLIDATION METHOD: vibrascree
LOCATION OF PLACEMENT: slabs on grade: 2 to 3 lines & 4 to 5 lines
LOCATION SAMPLED: Set 1 : 2 to 3, 0 to P; Set 2 : 4 to 5, N to 0
SLUMP: 4 "-4 . 5 " AIR: ---- % CUBIC YDS. PLACED: 350
CEMENT: 5 . 5 SK. TYPE: ---- MAX. SIZE AGGR: 7/8 "
ADMIXTURES: none listed AMOUNT: ----------
CONC TEMP: 70 . 10 AIR TEMP: 65 . 40 WEATHER: high thin clouds, light
71 . 9 74 . 2 breeze, sunshine
NO. CYLINDERS CAST: 3, 3 TIME SAMPLED: 1100 TRUCK NO: 48 (rental)
1320 019
DESIGN STRENGTH: 3000
CYL NO. LAB NO. DATE TESTED AGE PSI
7 6276 6/15/94 7 3780
8 6277 7/6/94 28
9 6278 7/6/94 28
10 6279 6/15/94 7 3610
11 6280 7/6/94 28
12 6281 7/6/94 28
2401 Bristol Court S.W. • P.O. Box 10267 • Olympia, WA 98502 • Phone (206) 357-7883 • FAX (206) 754-4240
Bradley-Noble Geotechnical Company
Geotechnical Consulting
TP
Construction Testing and Inspecting Service
� I
CONCRETE INSPECTION AND TEST REPORT
GENERAL ERWICES
CLIENT: POE Construction DATE OF INSPECTION: 6/8/94
PROJECT: AERO Controls Addition REPORT NO: 3
CONTRACTOR: POE Construction PROJECT NO: 94 . 05-11
INSPECTOR: D. Strong CONCRETE SUPPLIER: Miles Sand &
Gravel
FORMS INSPECTED: yes REBAR INSPECTED: yes
REMARKS: Mesh was pulled during plaacement; edges were vibrated.
PLACEMENT METHOD: chute CONSOLIDATION METHOD: vibrascree
LOCATION OF PLACEMENT: slabs on grade: 2 to 3 lines & 4 to 5 lines
LOCATION SAMPLED: Set 1: 2 to 3, 0 to P; Set 2 : 4 to 5, N to 0
SLUMP: 4 "-4 .5 " AIR: ---- % CUBIC YDS . PLACED: 350
CEMENT: 5 . 5 SK. TYPE: ---- MAX. SIZE AGGR: 7/8 "
ADMIXTURES: none listed AMOUNT: ----------
CONC TEMP: 70 . 10 AIR TEMP: 65 . 40 WEATHER: high thin clouds, light
71 . 9 74 . 2 breeze, sunshine
NO. CYLINDERS CAST: 3, 3 TIME SAMPLED: 1100 TRUCK NO: 48 (rental)
i 77n 0 9
DESIGN STRENGTH: 3000
CYL NO. LAB NO. DATE TESTED AGE PSI
7 6276 6/15/94 7 3780
8 6277 7/6/94 28 4660
9 6278 7/6/94 28 4400
10 6279 6/15/94 7 3610
11 6280 7/6/94 28 4310
12 6281 7/6/94 28 4530
2401 Bristol Court S.W. • P.O. Box 10267 • Olympia, WA 98502 • Phone (206) 357-7883 • FAX (206) 754-4240
I
Bradley-Noble Geotechnical Co
Geotechnical Consulting JUTA N -`
Construction Testing and Inspecting Services
-1 v1ALS'ERVICF
CONCRETE INSPECTION AND TEST REPORT
CLIENT: POE Construction DATE OF INSPECTION: 6/7/94
PROJECT: Aero Controls Addition REPORT NO: 2
CONTRACTOR: POE Construction PROJECT NO: 94 . 05-11
INSPECTOR: M. Robinson CONCRETE SUPPLIER: Miles Sand &
Gravel
FORMS i SPECTED: yes REBAR INSPECTED: yes
REMARKS: Resteel was per plans .
PLACEMENT METHOD: chute CONSOLIDATION METHOD: vibration
LOCATION OF PLACEMENT: grade beam, north side, A, 1 to 6 and part on B line;
three footings adjacent to existing building
LOCATION SAMPLED: west third of grade beam
SLUMP: 4 . 0" AIR: ---- % CUBIC YDS . PLACED: 20+
CEMENT: 5 . 5 SK. TYPE: ---- MAX. SIZE AGGR: 7/8 "
ADMIXTURES: none listed AMOUNT: ------
CONC TEMP: 710 AIR TEMP: 580 WEATHER: partly cloudy
NO. CYLINDERS CAST: 3 TIME SAMPLED: 0807 TRUCK 1'O: ?_49
DESIGN STRENGTH: 3000
CYL NO. LAB NO. DATE TESTED AGE PSI
4 6270 6/14/94 7 3580
5 6271 7/5/94 28
6 6272 7/5/94 28
2401 Bristol Court S.W. • P.O. Box 10267 • Olympia, WA 98502 • Phone (206) 357-7883 • FAX (206) 754-4240
Bradley-Noble Geotechnical Company
Geotechnical Consulting --
Construction Testing and Inspecting Services-'
ervices .5 °.
..4
CONCRETE INSPECTION AND TEST REPORT
•.- t e-ar'c-�;
t A
CLIENT: POE Construction DATE OF INSPECTION: 6/7/94
PROJECT: Aero Controls Addition REPORT NO: 2
CONTRACTOR: POE Construction PROJECT NO: 94 . 05-11
INSPECTOR: M. Robinson CONCRETE SUPPLIER: Miles Sand &
Gravel
FORMS INSPECTED: yes REBAR INSPECTED: yes
REMARKS: Resteel was per plans .
PLACEMENT METHOD: chute CONSOLIDATION METHOD: vibration
LOCATION OF PLACEMENT: grade beam, north side, A, 1 to 6 and part on B line;
three footings adjacent to existing building
LOCATION SAMPLED: west third of grade beam
SLUMP: 4 . 0 " AIR: ---- % CUBIC YDS. PLACED: 20+
CEMENT: 5 . 5 SK. TYPE: ---- MAX. SIZE AGGR: 7/8 "
ADMIXTURES: none listed AMOUNT: ------
CONC TEMP: 710 AIR TEMP: 580 WEATHER: partly cloudy
NO. CYLINDERS CAST: 3 TIME SAMPLED: 0807 TRUCK NO: 149
DESIGN STRENGTH: 3000
CYL NO. LAB NO. DATE TESTED AGE PSI
4 6270 6/14/94 7 3580
5 6271 7/5/94 28 4210
6 6272 7/5/94 28 4390
2401 Bristol Court S.W. • P.O. Box 10267 • Olympia, WA 98502 • Phone (206) 357-7883 - FAX (206) 754-4240
Bradley-Noble Geotechnical Company.,
Geotechnical Consulting {, ;
Construction Testing and Inspecting Services " 4
CONCRETE INSPECTION AND TEST REPORT '� �� ��! p-+�-htl Vp �J7,
ei��,
CLIENT: POE Construction DATE OF INSPECTION: 6/3/94
PROJECT: AERO Controls Addition REPORT NO: 1
CONTRACTOR: POE Construction PROJECT NO: 94 . 05-11
INSPECTOR: M. Robinson CONCRETE SUPPLIER: Miles Sand &
Gravel
FORMS INSPECTED: ves REBAR INSPECTED: yes
REMARKS: per plans
PLACEMENT METHOD: chute CONSOLIDATION METHOD: vibration
LOCATION Of' PLACEMENT: loading dock footings, 6 line, G to N and grade beam
along S line, 1 to 6
LOCATION SAMPLED: dock footings, south side
SLUMP: 4 " AIR: ---- % CUBIC YDS . PLACED: 40+
CEMENT: 5 . 5 SK. TYPE: ---- MAX. SIZE AGGR: 7/8 "
ADMIXTURES: none listed AMOUNT: -----
CONC TEMP: 750 AIR TEMP: 760 WEATHER: clear, sunshine
NO. CYLINDERS CAST: 3 TIME SAMPLED: 1215 TRUCK NO: 107
DESIGN STRENGTH: 3000
CYL NO. LAB NO. DATE TESTED AGE PSI
1 6264 6/10/94 7 3150
2 6265 7/1/94 28 4490
3 6266 7/1/94 28 4310
2401 Bristol Court S.W. • P.O. Box 10267 • Olympia, WA 98502 • Phone (206) 357-7883 • FAX (206) 754-4240
Bradley-Noble Geotechnical Company
Geotechnical Consulting
Construction Testing and Inspecting Services
CONCRETE INSPECTION AND TEST REPORT
CLIENT: POE Const
ruction DATE OF INSPECTION: 6/3/94
PROJECT: AERO Controls Addition REPORT NO: 1
CONTRACTOR: POE Construction PROJECT NO: 94 . 05-11
INSPECTOR: M. Robinson CONCRETE SUPPLIER: Miles Sand &
Gravel
FORMS INSPECTED: yes REBAR INSPECTED: yes
REMARKS: per plans
PLACEMENT METHOD: chute CONSOLIDATION METHOD: vibration
LOCATION OF PLACEMENT: loading dock footings, 6 line, G to N and grade beam
along S line, 1 to 6
LOCATION SAMPLED: dock footings, south side
SLUMP: 4 " AIR: ---- % CUBIC YDS . PLACED: 40+
CEMENT: 5 . 5 SK. TYPE: ---- MAX. SIZE AGGR: 7/8 "
ADMIXTURES : none listed AMOUNT: -----
CONC TEMP: 750 AIR TEMP: 760 WEATHER: clear, sunshine
NO. CYLINDERS CAST: 3 TIME SAMPLED: 1215 TRUCK NO: 107
DESIGN STRENGTH: 3000
CYL NO. LAB NO. DATE TESTED AGE PSI
1 6264 6/10/94 7 3150
2 6265 7/1/94 28
3 6266 7/1/94 28
2401 Bristol Court S.W. • P.O. Box 10267 • Olympia, WA 98502 • Phone (206) 357-7883 • FAX (206) 754-4240
Bradley Noble Geotechnical Compan _�E
Aor �' fl F r
Soils Engineers and Geologists SEP
Testing and Inspecting Services 091992
FIELD INSPECTION REPORT GEIVERAL SERVICE
CLIENT: POE Construction DATE OF INSPECTION: 24 August 92
PROJECT: AERO Controls, Shelton REPORT NO: 1
CONTRACTOR: POE Construction PROJECT NO: 92 . 07-03
Frame on E line was inspected on 10 August prior to covering with sheet
rock, see report 8 dated 10 August. Inspected balance of structural steel
frame. Conducted a visual inspection of all connections and found based on
the visual inspection that all A325 bolts had been installed per the plans .
a l_1_ ircwe to footi_nq connections were t ight . Control of bolting was by the
turn of the nut method. We understand that a 1-inch diameter air impact
wrench was used by the erection subcontractor to tighten the bolts . We
inspected about 10% of the connections at random locations . We found the
flats of the nuts indicating that in fact a impcat type of wrench had been
used. We found all connections inspected to be tight and we could not turn
the nut using a wrench. Based on our visual inspection, it is our opinion
that the connections of the steel frames meet the project requirments .
David C . Strong
Engineering Geologist
2401 Bristol Court S.W. • P.O. Box 10267 9 Olympia, WA 98502 9 Phone(206) 357-7883
JUL-09-1'F�2 l::4:-l5 Fr -T! NI-- J'�JUH-PED :I:C. TO `_3 P.Q_
MCSQUARED, INC. Structural and Foundation En irteem
121 1 EAST 4TH AVE.
SUITE 202
CLYMPIA. WA 9850f?
(206)754-9339
July 9 , 1992 r
Aero Controls Inc.
° f
Shelton, WA 98584 1-0
Attn: Bob Williams by
c
RE: Water Infiltration Rate
Dear Mr. Williams:
David Strong of Bradley Noble Inc. performed a falling head
percolation test on your work site on Tuesday July 7 , 1992 .
The purpose of this test was to establish a percolation rate
for stormwater drainage calculations.
A. falling head percolation test measures the time it takes for
an inch of water to drop one inch i.. a pipe. The pipe is
erbedded into the soil in which the Sto.= water will drain
into. The procedure calls for soaking the around in which the
test is to be performed. In sandy soils soaking the soil is
not required. The soil at your location consists of sands and
gravel approximately 150 feet deep.
The water in the test fell 5 inches in 10 seconds. This worms
out to a percolation rate of 0 . 0332 minutes per inch. By
factoring the test percolation rate to account for stormwater
fines to clog the drainage path over time, and using the
minimum percolation rate allowablra a usdabla percolation rate
is 5 minutes per inch. The rate does not need any further
adjustment.
The swale used for stormwater transmission should be
maintained regularly to remove the accumulated fines.
If you have any questions, or if I may be of further help,
please call me at (206) 754-9339 .
Sincerely yours, t
MC SQUARED, INC. �t. q►
MIKE S ZRAMEK P. E.
Senior Engineer
Ex�iaEs 07111/9"�