Joint Aquatic Resources Permit
Agency reference#: ;
Application (JARPA) Form'�2 hel
USE BLACK OR BLUE INK TO ENTER ANSWERS IN THE WHITE SPACES BELOW. Tax Parcel#(s):
-----------------------------------
Part 1-Project Identification
1. Project Name (A name for your project that you create. Examples: Smith's Dock or Seabrook Lane Development) Ehel
Satsop Springs Salmon Rearing Facility Pond Divider Upgrade
Part 2-Applicant
The person and/or organization responsible for the project. heI
2a. Name (Last, First, Middle)
Crumley, Lonnie
2b. Organization (If applicable)
Chehalis Basin Fisheries Task Force-Regional Fisheries Enhancement Group-(RFEG)
2c. Mailing Address (Street or PO Box)
P.O. Box 72
2d. City, State, Zip
Montesano, WA 98563
2e. Phone(1) 2f. Phone(2) 2g. Fax 2h. E-mail
360-470-0347 Admin@CBFTF.com
'Additional forms may be required for the following permits:
• If your project may qualify for Department of the Army authorization through a Regional General Permit(RGP),contact the U.S.Army Corps of
Engineers for application information(206)764-3495.
• Not all cities and counties accept the JARPA for their local Shoreline permits.If you need a Shoreline permit,contact the appropriate city or county
government to make sure they accept the JARPA.
2To access an online JARPA form with[help]screens,go to
htti)://www.epermitting.wa.gov/site/alias resourcecenterharpa iarpa form/9984/iarpa form asox.
For other help,contact the Govemor's Office for Regulatory Innovation and Assistance at(800)917-0043 or helpeoria.wa.gov.
ORIA-revised 12/2023 Page 1 of 18
Part 3—Authorized Agent or Contact
Person authorized to represent the applicant about the project. (Note: Authorized agent(s) must sign 11 b of this
application.) LtLeM
3a. Name (Last, First, Middle)
Crumley, Lonnie
3b. Organization (if applicable)
CBFTF
3c. Mailing Address (Street or PO Box)
97 Bartell Road
3d. City, State, Zip
Oakville, WA 98568
3e. Phone(1) 3f. Phone(2) 3g. Fax 3h. E-mail
1-360-470-0347 lwcrumley@centurytel.net
Part 4—Property Owner(s)
Contact information for people or organizations owning the property(ies) where the project will occur. Consider both
upland and aquatic ownership because the upland owners may not own the adjacent aquatic land. nel
® Same as applicant. (Skip to Part 5.)
® Repair or maintenance activities on existing rights-of-way or easements. (Skip to Part 5.)
❑ There are multiple upland property owners. Complete the section below and fill out JARPA Attachment A for
each additional property owner.
❑ Your project is on Department of Natural Resources (DNR)-managed aquatic lands. If you don't know, contact
the DNR at (360) 902-1100 to determine aquatic land ownership. If yes, complete JARPA Attachment E to
apply for the Aquatic Use Authorization.
4a. Name (Last, First, Middle)
Joe Coutu
41b. Organization (If applicable)
Washington Department of Fish and Wildlife
4c. Mailing Address (Street or PO Box)
P.O. Box 43234
4d. City, State, Zip
Olympia, WA 98501-1091
4e. Phone(1) 4f. Phone(2) 4g. Fax 4h. E-mail
1-360-742-7620 Joseph.Coutu@dfw.wa.gov
ORIA-revised 12/2023 Page 2 of 18
Part 5-Project Location(s)
Identifying information about the property or properties where the project will occur. [heir,]
❑ There are multiple project locations (e.g. linear projects). Complete the section below and use JARPA
Attachment B for each additional project location.
5a. Indicate the type of ownership of the property. (Check all that apply.) [help]
❑ Private
❑ Federal
® Publicly owned (state owned)
❑ Tribal
❑ Department of Natural Resources (DNR) — managed aquatic lands (Complete JARPA Attachment E)
5b. Street Address (Cannot be a PO Box. If there is no address, provide other location information in 5p.) heI
2090 W. Beerbower Road
5c. City, State, Zip(If the project is not in a city or town, provide the name of the nearest city or town.) hel
Elma, WA 98541
5d. County [help]
Mason County
5e. Provide the section, township, and range for the project location. h[ eV
1/4 Section Section Township Range
SE 21 19N 6W
5f. Provide the latitude and longitude of the project location. [heipl
• Example:47.03922 N lat. /-122.89142 W long. (Use decimal degrees- NAD 83)
47.1132 -123.43652
5g. List the tax parcel number(s) for the project location. [hei
• The local county assessor's office can provide this information.
619210060010
5h. Contact information for all adjoining property owners. (If you need more space, use JARPA Attachment C.) [help]
Name Mailing Address Tax Parcel # (if known)
Green Diamond Resource Co. 8809 Lenox Pointe DR., Suite B 619210000000
......................................................................................................................................................
Charlotte, NC 28273 619280001000
_...........................................................................--.----..._................................................
.......................................................................................................................................................
ORIA-revised 1212023 Page 3 of 18
5i. List all wetlands on or adjacent to the project location. [ gi
None
5j. List all waterbodies (other than wetlands) on or adjacent to the project location. of eM
East Fork Satsop River
5k. Is any part of the project area within a 100-year floodplain? nei
❑ Yes ® No ❑ Don't know
51. Briefly describe the vegetation and habitat conditions on the property. rL
No vegetation: Area is surrounded by gravel access roads for pond maintenance and fish rearing. Lawn grass,
one large spruce tree next to fish rearing ponds.
5m. Describe how the property is currently used. nei
Satsop Springs is managed by the CBFTF in cooperation with the Washington Department of Fish and Wildlife.
At the facility we raise 450,000 coho annually, 250,000 chum and our egg take goal through brood stocking we
try to get 600,000 chinook eggs. In addition we raise 7000 rainbow trout to and average of 4.5-5 pounds in size
for the local lakes.
5n. Describe how the adjacent properties are currently used. [nei
Adjacent properties are commercial forest lands used for timber harvest.
5o. Describe the structures (above and below ground) on the property, including their purpose(s) and current
condition. [help]
One residential house that houses a family of 4 currently. Next to the house is an open car port for two vehicles
and a storage shed next to the car port. One maintenance shop where tools are stored, plus fish feed and
grounds maintenance equipment is stored. Attached to the shop is the Task Force office. In addition there is a
small shed used to store hip boots and rain gear plus water sampling equipment. We have another storage shed
used for net and vehicle storage. Then there is the holding pond and fish trap facility for spawning and
surplusing salmon with a cable lift apparatus for removing fish from the holding area for spawning and
surplusing. There are 5 ponds excavated for fish rearing for which we are replacing pass-through structures for
water control.
5p. Provide driving directions from the closest highway to the project location, and attach a map. n[ eIp]
ORIA-revised 12/2023 Page 4 of 18
From Hwy 12 take the Brady exit; go to stop sign and continue straight on Middle Fork Satsop Road to Schafer
Park Road on right. Take Schafer Park Road to West Beerbower Road. Turn left on W. Beerbower Road and
continue for 2.5 mile to Satsop Springs on the left at the large Satsop Springs sign.
Part 6-Project Description
6a. Briefly summarize the overall project. You can provide more detail in 6b. [Lei
Replacing two round steel culverts which have flow cutoff valves at separate sites. One is at the inlet of pond
2, the other is at the inlet of pond 5, which is the bypass channel that leads to the river. Both are outlets from
pond 4. All ponds will be dry during project construction. The two culverts are about 15 feet apart. We are
also removing an old concrete structure from the pond bottom at the valve locations . The old valves and
culverts are currently in danger of failing due to age and rusting.
6b. Describe the purpose of the project and why you want or need to perform it. n� eld
The old steel culverts currently being used are deteriorating and in danger of malfunctioning which could
endanger fish rearing capabilities. With the new concrete trench installations, water flows and water levels can
be managed better for ponds 4 and 5 plus water flows can be managed better in the bypass channel during
the chum rearing period. Five other steel culvert water controls have been replaced and these are the last
ones to complete which will make water controls much more manageable for all the ponds.
6c. Indicate the project category. (Check all that apply) n[ elgl
❑ Commercial ❑ Residential ® Institutional ❑ Transportation ❑ Recreational
❑ Maintenance ❑ Environmental Enhancement
6d. Indicate the major elements of your project. (check all that apply) [help]
❑ Aquaculture ❑x Culvert ❑ Float ❑ Retaining Wall
❑ Bank Stabilization ❑ Dam /Weir ❑ Floating Home (upland)
❑ Boat House ❑ Dike/ Levee/Jetty ❑ Geotechnical Survey ® Road
❑ Boat Launch ❑ Ditch ❑ Land Clearing ❑ Scientific
Measurement Device
❑ Boat Lift ❑ Dock / Pier ❑ Marina / Moorage ❑ Stairs
❑ Bridge ❑ Dredging ❑ Mining ❑ Stormwater facility
❑ Bulkhead ❑ Fence ❑ Outfall Structure
❑ Swimming Pool
❑ Buoy ❑ Ferry Terminal ❑ Piling/Dolphin ❑ Utility Line
❑ Channel Modification ® Fishway ❑ Raft
Z Other: Upgrade and maintenance for a fish rearing facility to replace failing water controls and improve
water level management and flows through the ponds in the facility.
ORIA-revised 12/2023 Page 5 of 18
6e. Describe how you plan to construct each project element checked in 6d. Include specific construction
methods and equipment to be used. [hem
• Identify where each element will occur in relation to the nearest waterbody.
• Indicate which activities are within the 100-year floodplain.
The nearest water body is over 300 ft. away, E. Fk. Satsop River. We are working in a fish rearing facility
bordering the river where the water flow through the ponds can be totally dried up. This work will take place in
late May when the ponds are dried up for maintenance and cleaning after our annual fish realease. We will
remove two existing steel culvert structures. One is at the inlet of pond 2, the other is at the inlet of pond 5,
which is a water bypass channel that leads to the river, roughly 300 ft. from the pond outlet. Both allow outlet
flows from pond 4. Two thirty-feet-long concrete box trenches will be installed between these ponds that are
6ft. 3in. wide and 7ft. 2in. high. They come in 10 ft. sections because of the heavy weight. An old concrete
structure currently on the bottom of the current outlet of pond 4 that no longer has any purpose will be
removed. Once the pipes are excavated and the concrete structures removed from the channel, each trench
structure base will be excavated with a track excavator and 5/8 minus gravel base installed to set them on.
Once they are placed backfill material will be compacted around each vault and an access maintenance road
will be constructed over the top. The trenches will each be 30 ft. long, constructed of two pieces, the U-
shaped trench and the top lid that will allow vehicle passage over the top of the trenches. The access road
over the trenches will allow access to salmon brood stocking locations on the river and to access both sides of
the ponds for maintenance. None of this is in the 100 year flood plain.
6f. What are the anticipated start and end dates for project construction? (Month/Year) [help]
• If the project will be constructed in phases or stages, use JARPA Attachment D to list the start and end dates of each phase
or stage.
Start Date: May 20, 2024 End Date: May 31, 2024 See JARPA Attachment D
6g. Fair market value of the project, including materials, labor, machine rentals, etc. hel
$150,000
6h. Will any portion of the project receive federal funding? Eqel
• If yes, list each agency providing funds.
_� Yes Z No ❑ Don't know
Part 7—Wetlands: Impacts and Mitigation
Check here if there are wetlands or wetland buffers on or adjacent to the project area.
(If there are none, skip to Part 8.) [help]
7a. Describe how the project has been designed to avoid and minimize adverse impacts to wetlands. hem
Z Not applicable
7b. Will the project impact wetlands? hem
ORIA-revised 12/2023 Page 6 of 18
Yes `XJ No ❑ Don't know
7c. Will the project impact wetland buffers? het
Yes Z No ❑ Don't know
7d. Has a wetland delineation report been prepared? hel
• If Yes, submit the report, including data sheets,with the JARPA package.
❑ Yes Z No
7e. Have the wetlands been rated using the Western Washington or Eastern Washington Wetland Rating
System? hel
• If Yes, submit the wetland rating forms and figures with the JARPA package.
❑ Yes ® No ❑ Don't know
7f. Have you prepared a mitigation plan to compensate for any adverse impacts to wetlands? [hel
• If Yes, submit the plan with the JARPA package and answer 7g.
• If No, or Not applicable, explain below why a mitigation plan should not be required.
❑ Yes ® No ❑ Don't know
7g. Summarize what the mitigation plan is meant to accomplish, and describe how a watershed approach was
used to design the plan. [help]
N/A
7h. Use the table below to list the type and rating of each wetland impacted, the extent and duration of the
impact, and the type and amount of mitigation proposed. Or if you are submitting a mitigation plan with a
similar table, you can state (below) where we can find this information in the plan. [help]
Activity (fill, Wetland Wetland Impact Duration Proposed Wetland
drain, excavate, Name' type and area (sq. of impact3 mitigation mitigation area
flood, etc.) rating ft. or type` (sq. ft. or
category' Acres) acres
N/A
If no official name for the wetland exists,create a unique name(such as"Wetland 1"). The name should be consistent with other project documents,
such as a wetland delineation report.
ORIA-revised 12/2023 Page 7 of 18
2 Ecology wetland category based on current Western Washington or Eastern Washington Wetland Rating System.Provide the wetland rating forms
with the JARPA package.
3Indicate the days,months or years the wetland will be measurably impacted by the activity. Enter"permanent'if applicable.
4Creation C , Re-establishment/Rehabilitation R ,Enhancement E , Preservation P ,Mitigation Bank/In-lieu fee B
Page number(s) for similar information in the mitigation plan, if available:
7i. For all filling activities identified in 7h, describe the source and nature of the fill material, the amount in
cubic yards that will be used, and how and where it will be placed into the wetland. heI
N/A
7j. For all excavating activities identified in 7h, describe the excavation method, type and amount of material in
cubic yards you will remove, and where the material will be disposed. h[ elp]
N/A
Part 8—Waterbodies (other than wetlands): Impacts and Mitigation
In Part 8, "waterbodies" refers to non-wetland waterbodies. (See Part 7 for information related to wetlands.) [ham]
® Check here if there are waterbodies on or adjacent to the project area. (If there are none, skip to Part 9.)
8a. Describe how the project is designed to avoid and minimize adverse impacts to the aquatic environment.
[hel
x Not applicable
Ponds where work will take place will be dried up during construction. Any water seepage with sediment will
be pumped into bordering forest floor next to ponds. The project will not occur in a waterbody, but in an
artificial watered pond managed for fish rearing.
8b. Will your project impact a waterbody or the area around a waterbody? hei
❑ Yes Z No
ORIA-revised 1212023 Page 8 of 18
8c. Have you prepared a mitigation plan to compensate for the project's adverse impacts to non-wetland
waterbodies? hf gM
• If Yes, submit the plan with the JARPA package and answer 8d.
• If No, or Not applicable,explain below why a mitigation plan should not be required.
❑ Yes ® No ❑ Don't know
There will be no impacts to bordering water bodies. We have completed 5 other similar pond crossing
structures under the old Salmon Culture HPA and none had any impacts on bordering water bodies. The new
Salmon Culture HPA does not cover this activity anymore according to WDFW, thus the reason for requesting
this HPA.
8d. Summarize what the mitigation plan is meant to accomplish. Describe how a watershed approach was
used to design the plan.
• If you already completed 7g you do not need to restate your answer here. [hel
Mitigation will not be required via an on-site pre-construction discussion we had with DFW area habitat
biologist Megan Tuttle.
8e. Summarize impact(s) to each waterbody in the table below. [heIIDJ
Activity (clear, Waterbody Impact Duration Amount of material Area (sq. ft. or
dredge, fill, pile name' location of impact' (cubic yards) to be linear ft.) of
drive, etc.) placed in or removed waterbody
from waterbody directlyaffected
N/A
If no official name for the waterbody exists,create a unique name(such as"Stream 1")The name should be consistent with other documents
provided.
2 Indicate whether the impact will occur in or adjacent to the waterbody. If adjacent, provide the distance between the impact and the waterbody and
indicate whether the impact will occur within the 100-year flood plain.
'Indicate the days,months or years the waterbody will be measurably impacted by the work. Enter"permanent"if applicable.
8f. For all activities identified in 8e, describe the source and nature of the fill material, amount (in cubic yards)
you will use, and how and where it will be placed into the waterbody. [hel
N/A No fill in water body. This is in a dried up fish rearing pond. The nearest water body is over 300 ft. away
from digging site. The fill will be the excavated materials removed to install the new trenches. It is native soils
from original pond development. Roughly two loads, 30 CYs of crushed rock will be hauled in from local rock
quarry to install road access over top of new trenches once in place.
ORIA-revised 12/2023 Page 9 of 18
8g. For all excavating or dredging activities identified in 8e, describe the method for excavating or dredging,
type and amount of material you will remove, and where the material will be disposed. n�e
The old steel culvert water controls will be excavated with a track excavator. The materials will be stockpiled
near excavation. Once the new concrete trenches are installed much of the excavated materials will be used
to backfill. Any remaining materials will be stockpiled about 500 feet from the excavation site near the county
road where there is no impact to any water bodies due to stormwater runoff. The excavation quantities for
both trenches are 145 cy. for removing old structures and concrete channels, 100 cy. structure excavation
for new trenches, and 120 cy. for shoring and cribbing and 10 cy. for pond channel excavation and cleaning.
8h. Have you prepared a Water Quality Monitoring Plan (WQMP) for all in-water work (below ordinary high
water), over water work or discharges to waters of the state?
-1 Yes M No
If NO describe the monitoring that you will be conducting including parameters, equipment and locations,
or explain why monitoring will not be necessary. [help]
No monitoring plan is needed. Once the new trenches are installed the ponds will be flooded to receive this
year's salmon and trout for rearing and release in 2025. The ponds will be filled once construction is done and
any turbidity which should be minimal will be allowed to dissipate gradually over time to not impact the ponds
or eventual water bodies. Once the water is totally clear the fish will be released into the ponds. The
anticipated time for any cloudy water to dissipate is measured in minutes.
Part 9-Additional Information
Any additional information you can provide helps the reviewer(s) understand your project. Complete as much of
this section as you can. It is ok if you cannot answer a question.
9a. If you have already worked with any government agencies on this project, list them below. Eneid
Agency Name Contact Name Phone Most Recent
Date of Contact
DFW Megan Tuttle 1-360-819-6451 2/28/2024
ORIA-revised 12/2023 Page 10 of 18
9b. Are any of the wetlands or waterbodies identified in Part 7 or Part 8 of this JARPA on the Washington
Department of Ecology's 303(d) List? [heipl
• If Yes, list the parameter(s) below.
• If you don't know, use Washington Department of Ecology's Water Quality Assessment tools at: https://ecology.wa.gov/Water-
Shorelines/Water-guality/Water-i m provement/Assessment-of-state-waters-303d.
❑ Yes ❑ No
N/A
9c. What U.S. Geological Survey Hydrological Unit Code (HUC) is the project in? [helpi
• Go to http://cfpub epa.gov/surf/locate/index.cfm to help identify the HUC.
9d. What Water Resource Inventory Area Number (WRIA#) is the project in? hel
• Go to https//ecologv wa gov/Water-Shorelines/Water-supply/Water-availabilitVNVatershed-look-up to find the WRIA#.
220360
9e. Will the in-water construction work comply with the State of Washington water quality standards for
turbidity? heI
• Go to https//ecologv wa govNVater-Shorelines/Water-quality/Freshwater/Surface-water-quality-standards/Criteria for the
standards.
Yes ❑ No Z Not applicable
9f. If the project is within the jurisdiction of the Shoreline Management Act, what is the local shoreline
environment designation? [hel
• If you don't know, contact the local planning department.
• For more information, go to: https//ecologv wa gov/\Nater-Shorelines/Shoreline-coastal-management/Shoreline-coastal:
planning/Shoreline-laws-rules-and-cases.
❑ Urban ❑ Natural ❑ Aquatic ❑ Conservancy ® Other: N/A
9g. What is the Washington Department of Natural Resources Water Type? h[ elpl
• Go to http://www.dnr.wa.gov/forest-practices-water-typing for the Forest Practices Water Typing System.
❑ Shoreline ❑ Fish ❑ Non-Fish Perennial X7 Non-Fish Seasonal
9h. Will this project be designed to meet the Washington Department of Ecology's most current stormwater
manual? [heipi
• If No, provide the name of the manual your project is designed to meet.
Z Yes ❑ No
Name of manual:
9i. Does the project site have known contaminated sediment? hel
• If Yes, please describe below.
❑ Yes Z No
ORIA-revised 12/2023 Page 11 of 18
The current Stormwater Management Manual for Western Washington.
9j. If you know what the property was used for in the past, describe below. hel
Historically it was forest lands. For the last 60 years it has been a fish rearing facility
9k. Is the project located in or adjacent to a designated state or federal contaminated site or clean-up site.
(e.g. MTCA or CERCLA)?
• If Yes, provide any additional details below.
Yes k No
91. Has a cultural resource (archaeological) survey been performed on the project area? [help]
• If Yes, attach it to your JARPA package.
Yes Z No
ORIA-revised 12/2023 Page 12 of 18
9m. Name each species listed under the federal Endangered Species Act that occurs in the vicinity of the
project area or might be affected by the proposed work. Lei
None
9n. Name each species or habitat on the Washington Department of Fish and Wildlife's Priority Habitats and
Species List that might be affected by the proposed work. LLB]
None
Part 10—SEPA Compliance and Permits
Use the resources and checklist below to identify the permits you are applying for.
• Online Project Questionnaire at http://apps.oria.wa.gov/opas/.
• Governor's Office for Regulatory Innovation and Assistance at (800) 917-0043 or help .oria.wa.gov.
• For a list of addresses to send your JARPA to, click on agency addresses for completed JARPA.
10a. Compliance with the State Environmental Policy Act (SEPA). (check all that apply.) [Lel
• For more information about SEPA, go to https://ecology.wa.gov/regulations-permits/SEPA-environmental-review.
❑ A copy of the SEPA determination or letter of exemption is included with this application.
❑ A SEPA determination is pending with (lead agency). The expected decision date
is
❑ I am applying for a Fish Habitat Enhancement Exemption. (Check the box below in yob.) L[�
❑ This project is exempt (choose type of exemption below).
❑ Categorical Exemption. Under what section of the SEPA administrative code (WAC) is it exempt?
® Other: State owned fish rearing facility managed and operated by the CBFTF
❑ SEPA is pre-empted by federal law.
ORIA-revised 12/2023 Page 13 of 18
10b. Indicate the permits you are applying for. (Check all that apply.) hel
LOCAL GOVERNMENT
Local Government Shoreline permits:
❑ Substantial Development ❑ Conditional Use ❑ Variance
® Shoreline Exemption Type (explain): Not in natural water way-Hatchery pond that is dewatered as needed
Other City/County permits:
❑ Floodplain Development Permit ❑ Critical Areas Ordinance ?
STATE GOVERNMENT
Washington Department of Fish and Wildlife:
® Hydraulic Project Approval (HPA) ❑ Fish Habitat Enhancement Exemption—Attach Exemption Form
Washington Department of Natural Resources:
❑ Aquatic Use Authorization
Complete JARPA Attachment E and submit a check for$25 payable to the Washington Department of Natural Resources.
Do not send cash.
Washington Department of Ecology:
® Section 401 Water Quality Certification
❑ Authorization to impact waters of the state, including wetlands (Check this box if the proposed impacts
are to waters not subject to the federal Clean Water Act)
FEDERAL AND TRIBAL GOVERNMENT
United States Department of the Army (U.S. Army Corps of Engineers):
❑ Section 404 (discharges into waters of the U.S.) ❑ Section 10 (work in navigable waters)
United States Coast Guard:
For projects or bridges over waters of the United States,contact the U.S. Coast Guard at:
❑ Bridge Permit: D13-SMB-D13-BRIDGES@uscg.mil
❑ Private Aids to Navigation (or other non-bridge permits): D13-SMB-D13-PATON@uscg.mil
United States Environmental Protection Agency:
❑ Section 401 Water Quality Certification (discharges into waters of the U.S.) on tribal lands where tribes do
not have treatment as a state (TAS)
Tribal Permits: (Check with the tribe to see if there are other tribal permits, e.g.,Tribal Environmental Protection Act, Shoreline
Permits, Hydraulic Project Permits, or other in addition to CWA Section 401 WQC)
❑ Section 401 Water Quality Certification (discharges into waters of the U.S.) where the tribe has treatment
as a state (TAS).
ORIA-revised 1212023 Page 14 of 18
Part 11—Authorizing Signatures
Signatures are required before submitting the JARPA package. The JARPA package includes the JARPA form,
project plans, photos, etc. [help]
11 a. Applicant Signature (required) h[m
I certify that to the best of my knowledge and belief, the information provided in this application is true, complete,
and accurate. I also certify that I have the authority to carry out the proposed activities, and I agree to start work
only after I have received all necessary permits.
I hereby auth9rize the agent named in Part 3 of this application to act on my behalf in matters related to this
application. _(initial)
By initialing here, I state that I have the authority to grant access to the property. I also give my consent to the
permitting agencies enterirg the property where the project is located to inspect the project site or any work
related to the project. (initial)
Applicant Printed Name Ap can Signature Date
11 b. Authorized Agent Signature hem
I certify that to the best of my knowledge and belief, the information provided in this application is true, complete,
and accurate. I also certify that I have the authority to carry out the proposed activities and I agree to start work
only after all necessary permits have been issued.
Lonnie Crumley
Authorized Agent Printed Name uthorized Agent Signa ure Me
11 c. Property Owner Signature (if not applicant) hel
Not required if project is on existing rights-of-way or easements (provide copy of easement with JARPA).
I consent to the permitting agencies entering the property where the project is located to inspect the project site
or any work. These inspections shall occur at reasonable times and, if practical, with prior notice to the
landowner.
Joe Coutu Z-62-4
Property Owner Printed Name Prop ner Signature Dat
18 U.S.0§1001 provides that:Whoever, in any manner within the jurisdiction of any department or agency of the United States knowingly
falsifies,conceals, or covers up by any trick, scheme,or device a material fact or makes any false,fictitious, or fraudulent statements or
representations or makes or uses any false writing or document knowing same to contain any false, fictitious, or fraudulent statement or
entry, shall be fined not more than$10,000 or imprisoned not more than 5 years or both.
If you require this document in another format, contact the Governor's Office for Regulatory Innovation and Assistance(ORIA)at(800)
917-0043. People with hearing loss can call 711 for Washington Relay Service. People with a speech disability can call (877)833-
6341. ORIA publication number: ORIA-16-011 rev. 09/2018
ORIA-revised 12/2023 Page 15 of 18
SATSOP SPRINGS REARING FACILITY LOCATION
Mason County WA GIS Web Map
tsf{�
Satsop Springs
Rearing Facilityi'
est Beerbower Road y
.o
i�
I
East Fork Satsop River ;!f
t'
n
.y
228t2024,33448 PM 1:12,310
0 0.1 02 O.t rtl
County Boundary 0 0.15 OJ ❑x Ym
No Filled
L Tax Parcels(Zoom in to 1:30,000)
m.cai nCDL.�In.i nrl�ne�anlP�In,cc.crn.'�•r..
ilA IF..NMA14 r=Zw CA r:aC ,NL 13d-Su,aY Cal
.��Rir I Cai�A IMa+G r:nr�t Ic10L>tr('.iia�l.4q mll a Jea,nC
IIf c G lbi[mnfl.lY
1.4s n CLII�Y W AC IS Y*ab Mp.�pblm
Cuaa.e'Lab Rblar�r,CapCaomCalnCCL,:amn,�r GULir C,VSGi,/ILA NA%lk CP.-,k."AI
SATSOP SPRINGS TRENCH INSTALLATION LOCATIONS
SATSOP SPRINGS REARING & BROODSTOCKI NG FACILITY
Il.,k%1,k 1
If bast.` pn1.111c
slq,ta.'I, i.i,"Id .
L trench installation
�Inrm IA pn., t hhma s 1&2
IWA,Nrrtrn P—d.4 IWhiWI WI Ni.k - 4�
t'ulven .hn
Tiix ti._n .
1.1.4.!kr.e.fbM a3 ('h l"A a J.
Rxrk 41f1„N
I.Ilnkl:IR:1 I � y
Nl.in R-k N1.lr('hi,-A
Y..er rwfla N.ln. I.,ir.l\rn LEGEND
� Nrr.hcr -
Inl.hr
p °"" .,.:'...::.'..., ... Concrete Bypass Channel
A �.....flood Bypass Culvert �rt.ls
® IF .....Habitat Bypass Culvert
I l:rtr.\ir Nlu rngc m ng P.— � e
Flabilat Side Valve
1 r+I �. „••�� ItesfAcnrc RV Intake Screen i
I I I'nrkina w
.....Leal•Net
rn.rr � .....Outlet Screen
1 rnMw
NVI'—lfreAerRN.MwKnWrl6"FuP
,,,r,,,,, I 1 �. ..PowerBreaker
sfi-g, N'NIC J'M I I rNq.x'linlr
r...dua r.ra I J .....Rack Alnlc Chinook Location
I I Stop Weir Bypass
I___———————I ...Storm Bypass Chute
ENTRANCE � --I\xmrwu �� ...Weir
3/rcrhnr..........I �--}—
0
X
D
a
m
a
w CULVERT REPLACEMENT
INLET & OUTLET STRUCTURES FOR PONDS 2, 4, & 5
CHEHALIS BASIN FISHERIES TASK FORCE
i 2090 W. BEERBOWER ROAD
OJE
R
'RCT
"ITT-; ELMA, WA 98541
Schafer
McCleary_,
INDEX
ake Sylvia 1. TITLE SHEET
rTl a 2. PLAN VIEW
Brady SatSO I p •� /� 3. CULVERT PROFILES
o
rk Malone
Montesa o__
VICINITY MAP ^
SCALE: NONE
6'-3'SPAN.T-r
RISE 10 STRUCTURAL
10't RECAST UOUTY I1Nt
6'R SURFACING--MIN
APPROXIMATE QUANTITIES (1+*MINUS CRUSHED ROCK)
12'GRAVEL waGlu
FOR PIPE ZONE BEDDING
ITEM QUANTITY ITEM - (s�-MINUS)ON SWES.
— —
01
2 EACH REMOVING EXISTING CULVERT —. .— —.-' -- --—
02 145 C.Y. REMOVING EXISTING CONCRETE CHANNEL BOTTOM AND SIDE SLOPE$ —
100 C.Y. STRUCTURE EXCAVATION FOR CULVERT INSTALLAIM)
120 SO.FT. SHORXVG AND CRIBBING BACKF1 L W1H • —.—_ '� __ -. tl
10 C.Y. CHANNEL EXCAVATION EXCAVATED — --
XCAVATE
�6 5 C.Y. STREAMBED ORAVTi. _ a.
/7 70 C.Y. LIGHT LOOSE WRAP — --
/6 6 LF. INSTALL UVAULT 6 AN,7- MTH SHORTEN U
S4 LF. 1107ALL UTILITY VAULT 6- AN, - RI N FULL
0 90 CY. GRAVEL BACKRU.FOR PIPE ZONE BEOOING 5 6'MINUS) 4•i
1 40 GY. ROCK SUR(ACING(1'MINUS CRUSHEO HOCK 4'GRAVEL BACKFILL FOR POPE 7
#12 1 LUMP SUM I EROSION CON/ROL ZONE SMONG(5/5-MINUS)
ra 1 JOC.Y QUARRY SPALLS I TRENCH BACKFILL DETAIL
SCALE NONE
Ko a n 1A10 OWNRLAM)o5NLT1: 6LSKA1L6 en CULVERT REPLACEMENT M° - --_
-- SATSOP SPRINGS REARING AND CHEHALIS BASIN FISHERIES BECKER ENGINEERING
BROODSTOCKING FACILITY TASK FORCE 722 W. SPRUCE STREET INLET & OUTLET STRUCTURES -
LAT 47.1136 LONG-123.4364 2090 W. BEERBOWER ROAD MONTESANO. WA. 98563 FOR PONDS 2, 4 & 5 _AS SHOWN
- - ELMA, WA. 98541 360-249-4258 TITLE SHEET _1_-,a 3
v
O
0
X
$Yw.isfi AN,7'-2'RtSE ID
3 LENGTH STRUCTURAL PRECAST
UTILITY VAULT
INLET ELEV-9.180'
OUTLET ELEV-93.20'
<z
- ROAD
6 �q REMOVE ALL EXISTING
— CEM
ONCRETE SLABS&STARS.
METAL RACKS&SCRECNS'PIPES&CULVERTS.
REMOVE CONCRETE SIDE
SLOPE,
100 SY. PLACE
LIGHT LOOSE RIPRAP,100 CY.
'RZ
REMOVE EXISTING CONCRETE CHANNEL
BOTTOM AND SIDE SLOPES.PLACE
wwm STREAM BED GRAVEL TO BUILD CHANNEL
BACK TO ELEVATION OF CONCRETE
CHANNEL.CONCRETE REMOVAL,45 SY.
--'-EXISTING
REMOVE EXISTING UENG AN,7-2-RISE ID,30'
INLET ELEV-9510'
CONCRETE SLAB1H STRUCTURAL PRECAST UTILITY VAULT.
A
% OUTLET ELLV-95.20'
1
.'--";IEMOVE EXISTING 36-CMP
.,
(FROM POND#4 TO POND 05)
EXCAVATE EXISTING
GRAVEL rORD
STREAM CROSSING
PLAN VIEW
SCALE: 1" = 20'
1p Far
Jl 1.
Nawaao -------- ec CULVERT REPLACEMENT FW"a
SATSOP SPRINGS REARING AND CHEHALIS BASIN FISHERIES BECKER ENGINEERING INLET & OUTLET STRUCTURES iEWiw-- ATA
------- FACILITY TASK FORCE 722 W. SPRUCE STREET FOR PONDS 2, 4 & 5
BEERBOWER ROAD
iLAI 47M36 LONG-123.4364 2090 W. AS SHONRI
ELMA, WA. 98541 MONTESANO, WA. 98563 PLAN VIEW OF-3
-4
a
Gs
O
A
D
AD
'A
0
a
N
N
O
N
W
INSTALL W-3'SPAN.7'-2'RISE ID.30'LENGTH
POND 4 STRUCTURAL PRECAST UTILITY VAULT. POND 2
110 _"_ SHORTEN THE LID 10"ON .... _ .- 110
EACH ENO OF CULVERT
WATER FOR SCREEN PLACEMENT
ELEV-94.4' I ROADWAY
E%ISPNG I PLACE LIGHT LOOSE
18' RIPRAP 2'TICK.35 CY
SURFACE GROUND ATCULVERT/1 100
100
WATER SURFACE
oor ELEV-93.4'
90 — — 90
INLET ELEV. CULVERT #1
93.80' -OUTLET ELEV-
93.20'
REMOVE EXISTING CONCRETE
CHANNEL BED AND SIDE SLOPES.
POND 4 PLACE STREAM GRAVEL TO BUILD INSTALL 8'-3"SPAN,7'-2"RISE ID,30' EXCAVATE EXISTING POND 5
CHANNEL BACK TO ELEVATION OF LENGTH STRUCTURAL PRECAST UTILITY VAULT AVE STREA
'6ACRE1E-CR7R]REL-- L FORD-- -
110 110
— tDROADv�iAr —
SHORTEN THE UO 18'ON WATER SURFACE
EACH END OF CULVERT PLACE LIGHT LOOSE ELEV-93.5'
FOR SCREEN PLACEMENT RIPRAP 2'THICK.35 CY
A7 CULVERT/2
EXISTING
100 WATER— WTR SURFACE , / ORIX ND -- 100
ELEV-94.4'
slow allow
----"'.LILY]=CIJ-L2IL�=LI1.L7
90 — — 90
INLET ELEV- OUTLET REV-
PROFILE 95.9G' CULVERT #2
95.20'
SCALE: 1" 10'
saga IN PERT n --_ _ u ----'-"14 ....40 tz
Rvaa� LOCATION' LAM Cr1AIE CULVERT REPLACEMENT _-
SATSOP SPRINGS REARING AND CHEHALIS BASIN FISHERIES BECKER ENGINEERING AMFV. N/A
BROODSTOCKING FACILITY TASK FORCE INLET & OUTLET STRUCTURES
LAT 47.T136 LONG -723.4364 2090 W. BEERBOWER ROAD 722 W. SPRUCE STREET FOR PONDS 2, 4 & 5 SAS SHOWN
- - ELMA, WA. 98541 MONTESANO, WA. 98563 CULVERT PROFILES aacc—T Ov 3
0)
m
0)
ao
0
ao
LIOYAiY
L io L t009LlVOZS�IO OlP 4Z/9tlZ 31V0 WAw(EU HUM wi� %�VW woNm00vdD1®BIA311 a
uLaeA �r �e wie
S3RI3HSId NISVB SIlVF13HO NOLLYOPMA Noj
03AOHddV
Nn rrry
mir3ava Larmu ua�j
TIIBId 1{JL�Ar A.flr}pA[ip181taL0'i
0-
HONML OLOB
.............�.\llrarlo
M.M 1..rl��r'li w.r.11110�4N YM CW�1�'lTY1NW0.L
,sl04in M�iYY I•
ANwIN1.Cv rrl�i bin�lr L•d01
aimmisa4ul spas-pip
S M31A V M31A
aawiu s3owul Lsmalcl3aerila
uao.vin�t- aawY)
r --- , ---- — 1------— — -----
I
I I II II I I II II �'
30W LL09Rm I II II II II i
I = I II II I I II II
I I i II II I I it II
�LaLaum ldnc $ Omu"IIdu"M adub) `
d4 !� uAo�ltl
axrnalu n.Lacutu NWUA&co am m Yoo'r�m�w
.10" o-manum aim (d 11V130101S �--
Aid M31A NVld
rwim3 Jdoim'do1wlN
s s • s voHowiinwL,
AU
1+L�x
ra-mmmmtrl
uwmm�oumoow �� m m I � m m $
.63lYIL'11411SA1lIL13L3lL7gJ L�YJ3tld , m m I m m m m
O�%MOf30.ItlR/f/01lY.kJ?]dB ONONLi.JiYJWIaV :83:f(Id3Yll9 / �
3QR3CW"CM1VM n jwooi L�
NLd3a l0A AJ 3IOBI 3EfNACJNIB Opl 3M P.04
aWIMRvMwa�3ures�eiaem�ndi3vaw
31B1 W 31YM 3IOBI 3tl11893tld lOC M BlV I'di3 P4 01
AlW1l307W wou
19W�108AZNMlBHIMR117id1A%OC &I10'WW JN IWOWIM" 1:4
9 UOVO'ID1N)CYWl9<410111BYY
Lw91 LU did 611011IBVOM Ol0'IOFOW
+ALLI1313KAAIO:UJV.f311d OJ10161B7J1 71Y19108R
N(U OJ0101IJY83a7VlJllalall3=v8ff vw.w i7 to
30ww"K.YMN 7,:Ml
a13L1YtlDM mum :!NAIL
m3OlUa1Al'VIIIW iXYl2
MOA7J•i1NlfN911A 316®YIDOAO■ iliPJW
sam,OAIL.Nm
SATSOP SPRINGS REARING FACILITY PROJECT PHOTOS
IT
{ ,
t,.
-
ry:
A'
Culvert Outlets from Pond 4 Pond 4 Outlet View from Road
,I
-y
` y1
Pond 2