Purdy Cut-Off Road Detour Agreement
THIS AGREEMENT is made and entered into this 1 7-day of /7R y
pco7 between the STATE OF WASHINGTON,Department of T sanr portation,
hereinafter the"STATE," and Mason County, Department of Public Works, P.O. Box
1850, Shelton, Washington 98584, hereinafter the"COUNTY,"individually referred to
as"PARTY" and collectively as "PARTIES."
WHEREAS,the COUNTY is planning an improvement project to reconstruct the
pavement structure of the Purdy Cut-Off Road, hereafter the"PROJECT"; and
WHEREAS, each year the STATE must detour STATE traffic onto Purdy Cut-Off Road
when US 101 or State Route 106 are closed due to accidents, floods, landslides or other
emergency situations; and
WHEREAS, the STATE's detoured traffic would reduce the effective service life of the
COUNTY's Purdy Cut-Off Road; and
WHEREAS, the STATE wishes to contribute a one time, lump sum amount as a Fifteen
(15)Year Detour Equivalent Life Cost toward the COUNTY's PROJECT,
NOW,THEREFORE, pursuant to RCW 47.08.070 and in consideration of the terms,
conditions, and performances contained herein, and the attached Exhibits A and B which
are incorporated and made a part hereof, IT IS MUTUALLY AGREED AS FOLLOWS:
1. GENERAL
1.1 The COUNTY agrees to allow the STATE to use the Purdy Cut-Off Road as a
detour route between its intersection with US 101 and with SR 106, when US 101
and/or SR 106 are closed due to accidents, floods, landslides or other emergency
situations. The Purdy Cut-Off Road is shown by the shaded area on Exhibit A.
1.2 The STATE agrees to contribute a one time, lump sum amount of Sixty-five
Thousand Dollars($65,000.00) toward the PROJECT as a 15 Year Detour
Equivalent Life Cost as shown in Exhibit B.
1.3 The COUNTY shall notify the STATE of the completion of the COUNTY's
PROJECT within 30 days after PROJECT completion.
1.4 The STATE agrees that if single or multiple emergencies require the use of the
Purdy Cut-Off Road as a detour route for a continuous duration exceeding seven
(7) calendar days, the STATE shall pay the COUNTY Eight Hundred Seventy
Dollars ($870.00) for each additional day exceeding seven (7) continuous days
that the Purdy Cut-Off Road is used as a detour route.
GCA-5206
Page 1 of
1.5 Use of the Purdy Cut-Off Road as a detour route for non-emergencies, such as
STATE construction projects, is not covered by this AGREEMENT. However,
construction traffic, associated with the emergency repair of US 101 and/or SR
106 during the emergency detour period, will be permitted to use the Purdy Cut-
Off Road as provided in this AGREEMENT at no additional cost to the STATE.
1.6 The COUNTY will provide all maintenance and be responsible for all damages to
the Purdy Cut-Off Road resulting from emergency detour use under this
AGREEMENT at no cost to the STATE.
2. PAYMENT
2.1 The STATE agrees to pay the one time,lump sum amount of$65,000.00 to the
COUNTY upon execution of this AGREEMENT to be spent by the COUNTY
toward the PROJECT.
2.2 Should the COUNTY fail to complete the PROJECT within twenty-four(24)
months from the date of this AGREEMENT, the STATE may request, through
written notice to the COUNTY, return of the STATE's contribution paid to the
COUNTY. Should the STATE make such a request, the COUNTY agrees to
return said contribution within sixty(60) calendar days from the receipt of said
request.
2.3 The COUNTY may bill the STATE for additional detour use in accordance with
Section 1.4. The STATE agrees to pay for the additional detour use within thirty
(30) calendar days from the receipt of said billing.
3. AMENDMENT
3.1 This AGREEMENT may be amended by mutual agreement of the PARTIES.
Such amendments or modifications shall not be binding unless they are in writing
and signed by persons authorized to bind each of the PARTIES.
4. TERMINATION
4.1 The COUNTY may terminate this AGREEMENT with written concurrence of the
STATE.
4.2 The STATE may terminate this AGREEMENT, in whole or in part, immediately
upon written notice to the COUNTY, or at such later date as the STATE may
establish in such notice.
5. INDEPENDENT CONTRACTOR
5.1 The COUNTY shall be deemed an independent contractor for all purposes and the
employees of the COUNTY or any of its contractors, subcontractors, consultants,
GCA-5206
Page 2 of 4
and the employees thereof, shall not in any manner be deemed to be employees of
the STATE.
6. INDEMNITY
6.1 The COUNTY shall protect, defend, indemnify, and hold harmless the STATE,
its officers, officials, employees, and agents, while acting within the scope of their
employment as such, from any and all costs, claims,judgments, and/or awards of
damages (both to persons and property), arising out of, or in any way resulting
from the COUNTY's construction, operation and/or maintenance of the
PROJECT and the Purdy Cut-Off Road pursuant to the provisions of this
AGREEMENT. The COUNTY will not be required to indemnify, defend or save
harmless the STATE if the claim, suit, or action for injuries, death, or damages
(both to persons and property) is caused by the sole negligence of the STATE.
Where such claims, suits, or actions result from concurrent negligence of the
PARTIES, the indemnity provisions provided herein shall be valid and
enforceable only to the extent of the PARTY's own negligence.
6.2 The COUNTY remains solely responsible for third party damages to Purdy Cut-
Off Road facilities during emergency detour events.
6.3 This indemnification and/or waiver shall survive the termination of this
AGREEMENT.
7. DISPUTES
7.1 In the event that a dispute arises under this AGREEMENT, it shall be resolved as
follows: The STATE and the COUNTY shall each appoint a member to a
disputes board,these two members shall select a third member not affiliated with
either PARTY. The three-member board shall conduct a dispute resolution
hearing that shall be informal and unrecorded. An attempt at such dispute
resolution in compliance with aforesaid process shall be a prerequisite to the filing
of any litigation concerning the dispute. The PARTIES shall equally share in the
cost of the third disputes board member.
8. VENUE
8.1 In the event that a PARTY deems it necessary to institute legal action or
proceedings to enforce any right or obligation under this AGREEMENT, the
PARTIES hereto agree that any such action or proceedings shall be brought in
Thurston County Superior Court.
9. RECORDS
9.1 All records relative to payments made under Section 2 shall be maintained by the
COUNTY for a period of three (3) years from completion of the PROJECT. The
GCA-5206
Page 3 of 4
state and/or federal governments or their representatives shall have full access to
and right to examine said records during normal business hours and as often as it
deems necessary.
10. TERM OF AGREEMENT
10.1 Unless otherwise provided herein, the term of this AGREEMENT shall
commence as of the date this AGREEMENT is entered into and terminate fifteen
(15) years from completion ofthe COUNTY's PROJECT.
10.2 Should the COUNTY fail to complete the PROJECT,this AGREEMENT shall
terminate upon the return of the STATE's contribution(see Section 2.2).
IN WITNESS WHEREOF,the PARTIES hereto have executed this AGREEMENT as of
the day and year first above written.
MASON COUNTY STATE OF WASHIN ON
DEPARTMENT OF NSPORTATION
By: By:
Title: F Title:
Printed Name: ,C Kevin J. Dayton, Region Administrator
Date: Date:lwt`Z Za-,X
APPROVED FO f, APPROVED AS TO FORM
By:
ssist t Prosecuting Attorney ssistant Attorney General
Date: Q Date: _07
GCA-5206
Page 4 of 4
apt /1/
1 N Q O
Q
C �
SIa.M CJ[S] VI
yc mrlJ
ec rC
5
Jr> �a
aaq ppmL,r4 46ti
f
Cp 3 0
g a
s
3 Q i
v —
n�
�9
e=aploH OIO � _. •••.•.•y .•..
v
\ %.
' n nb��._ i I HS/gO� si
ELI
Vaa
?oo ns
- o
p
O�
rl fli sILLa r
,d t
... z
pp _
J a � ! � __. . ._.L. �................. SNP
p
�C
GCA-5206
Exhibit B
Purdy Cut-Off Road
Detour Route for US 101 and/or SR 106 Traffic
Estimate of Costs:
Average Use Per Year for Emergencies 5 Days
(Days)
Roadway Section after Overlay 3"HMA
2" 1992 Overlay
1"Misc. BST's
4"CSBC
Calculated Pavement Life (ESAL's) 410,000
SR 101 Traffic 6,500 ADT
9% Single Trucks
4% Double Trucks
1% Triples
Calculated ESAL's/Day 610
Paving Project Estimated Cost $575,000
15 Year Detour Equivalent Life Cost $64,162
STATE's one time, lump sum Cost $65,000
15 Years x Average Days/Year x ESAL's/Day x Project Cost/ESAL Life
GCA-5206
Exhibit B
Page l of I