HomeMy WebLinkAboutChange Order # 006 for Colvos Construction DocuSign Envelope ID: E6F9B89F-FD54-44A4-9FDD-91 F25C488C87
coRvosPCCO #006
Colvos Construction Project; - 20-031 Mason County Courthouse
711 Court C 414 West Franklin St
Tacoma,Washington 98402 Shelton,Washington 98584
Phone: (253)279-7887
Prime Contract Change Order #006: Multiple PCO's (PCO #034,0361 037)
TO: Mason County FROM: Colvos Construction
411 North 5th St 711 Court C
Shelton,Washington 98584 Tacoma Washington 98402
DATE CREATED: 11/22/2020 CREATED BY: Casey Angeline(Colvos Construction)
REVISION: 0
INVOICED DATE: PAID DATE:
SCHEDULE IMPACT: 0 days EXECUTED: No
CONTRACT FOR: 1:20-031 Mason County Courthouse Prime TOTAL AMOUNT: $4,589.56
Contract
DESCRIPTION:
PCCO#06 encompasses all cost associated with the PCO's listed below.
1. PCO#034-Holiday Schedule
2. PCO#036-Phase 2 Wall Layout Coordination(Rev.4)
3. PCO#037-Revised Lighting Layout
ATTACHMENTS:
POTENTIAL CHANGE ORDERS IN THIS CHANGE ORDER:
PCO# Title Schedule Impact Amount
034 Holiday Schedule 11 days 0.00
036 Phase 2 Wall Layout Coordination(Revision#04) 0 days 4,017.12
037 Revised Lighting Layout 0 days 572.44
TOTAL: $4,589.56
CHANGE ORDER LINE ITEMS:
PCO#034:Holiday Schedule
# Cost Code Doec6ption Type Amount
1 $0.00
Subtotal: $0.00
Send:3.00^/Applies to all line Item types. 0.00
Liability Insurance:1.25%Applies to all line item types. 0.00
Contractor Fee:10.00%Applies to all line item types. 0.00
980 Tax:0.591/Applies to all lima item types. 0.00
Sales Tax:8.80%Applies to all line item types. 0.00
Grand Total: $0.00
Colvos Construction page 1 of 2 Printed On: 12/4/2020 12:27 PM
DocuSign Envelope ID: E6F9B89F-FD54-44A4-9FDD-91 F25C488C87
c oRvos
1-1-1 Pcco #006
PCQ#036:Phase 2 Wall Layout Coordination(Revision#04)
# Cost Code Description Ty
pe Amount
1 06-10.53-Rough Carpentry 32 Hours for Revised Layout and Demolition of Existing Courtroom Wall,Labor to Other $2,560.00
Install New Wail and Sheathing that was previously not shown.
Additional Lumber and Sheathing required to frame and sheath the New Areas
2 06-11.13-lumber Other $1,500.00
North of Room 137.
3 09-51-13-Acoustical Panel Ceilings Credit for Reducing ACT Scope Other ($480.00)
4 1 09-60.01-Flooring Credit for Reducing Flooring Scope Other ($380.00)
Subtotal: $3.200.00
Bond:3,00%Applies to all line item types. 96.00
Liability Insurance:1.25%Applies to all line item types. 41,20
Contractor Fee:10.00%Applies to all line item types. 333.72
B&O Tax:0.58%Applies to all line item types. 21.29
Sales Tax:8.80%Applies to all line item types. 324.91
Grand Total: $4,017.12
PCO#037:Revised Lighting Layout
# Cost Code Description Type Amount
1 26-20-13-Building Electrical Revised Lighting Layout Based on Drawings provided by Helix on 11/4/2020 Other $386.00
2 01-30-23-Project Engineer 1 Hr of PE Time Other $70.00
Subtotal: $456.00
Bond:3.00%Applies to all line item types. 13.68
Liability Insurance:1.25%Applies to all line item types. 5.87
Contractor Fee:10.00%Applies to all line item types. 47.56
B&O Tax:0.58%Applies to all line item types. 3.03
Sales Tax:8.90%Applies to all line item types. 46.30
Grand Total: $572.44
The original(Contract Sum) $2,216,218.00
Net change by previously authorized Change Orders $ 569,550.09
The contract sum prior to this Change Order was $2,785,768.09
The contract sum would be changed by this Change Order in the amount of $4,589.56
The new contract sum including this Change Order will be $2,790,357.65
The contract time will not be changed by this Change Order by 0 days
Bruce McKean(Helix Design Group) Mason County Coivos Construction
6021 12th St E,Suite 201 411 North 5th St 711 Court C EDS
Tacoma Washington 98424 Shelton Washington 98584 Tacoma Washington 98402
l DocuSigned by:
12/8/2020
SIGNATURE DATE SIGNATURE DATE SIGOWFURFOEM4112... DATE
Colvos Construction page 2 of 2 Printed On: 12/4/2020 12-27 PM