HomeMy WebLinkAboutChange Order # 004 for Colvos Construction 'DocuSign-Envelope ID:79DBA666-0691-4528-97F6-B32958885DAD" colvos PCO #004 Colvos Construction Project: -20-031 Mason County Courthouse 711 Court C 414 West Franklin St Tacoma,Washington 98402 Shelton,Washington 98584 Phone:(253)279-7887 Prime Contract Potential Change Order #004: ASI #03 -ADA Refuge Area, City Plumbing Updates, Holding Cell Updates TO: Mason County FROM: Colvos Construction 411 North 5th St 711 Court C Shelton,Washington 98584 Tacoma,Washington 98402 PCO NUMBERIREVISION: 004/0 CONTRACT: 1-20-031 Mason County Courthouse Prime Contract REQUEST RECEIVED FROM: CREATED BY: Casey Angeline (Colvos Construction) STATUS: Pending-In Review CREATED DATE: 1017/2020 REFERENCE: PRIME CONTRACT None CHANGE ORDER: FIELD CHANGE: No LOCATION: ACCOUNTING Amount Based METHOD: SCHEDULE IMPACT: 3 days PAID IN FULL: No TOTAL AMOUNT: $56,209.43 POTENTIAL CHANGE ORDER TITLE:ASI#03-ADA Refuge Area,City Plumbing Updates,Holding Cell Updates CHANGE REASON:Design Development POTENTIAL CHANGE ORDER DESCRIPTION:(The Contract Is Changed As Follows) See attached ASI#03 for following changes to occur in order to meet the requirements of the Remodel Permit Set. Based.on ASI#03-Permit Revisions,the following cost includes the items listed below. 1. At the new Area of Refuge near Exit Door 120 the following Items were added: 1. Additional wood framing and 518"GWB with Level 4 Finish at the.1 HR rated walls. This Includes fire taping above ceiling space and fire caulking the top and bottom of walls/penetrations. 2. Door 120A and 120B(HM Doors and Frames with Hardware per Hardware Group 25) 3. (2)Fire Smoke Dampers(Sized per Plans) 4. (2)Rectangular Duct Adder Stub-In 5. Two-Way Comm.UL listed Analog System.per RFI#24 2. (2)SA12 Security Toilet Tissue Holders 3. (2)SA01 Security Mirrors 12"x16" 4. (2)SA7018"Security Grab Bars 5. (2)SA70 36"Security Grab Bars 6. (2)SA70 42"Security Grab Bars 7. (1)RectorSeal 4"Extendable Clean Checks Backwater valves at sewer line connections. This is with the assumption that the existing backwater valve can be replaced with the new one without having to tear into asphalt and patch back around the valve.Per RFI#29-the(2)shown backwater valves were not required. 8. (1)Backflow preventer to water service line-Zurn Model 376 9. The cost associated for the separate toilet and sink equaled the cost for a toilettsink combo unit Therefore no cost Is associated with these Items. Excludes: 1. Benches in Holding Cells 2. New Building Waste Tie-In to City Sewer per RFI#29 3. Any work that is not described within the ASI#03 Narrative by Helix. 4. Asphalt Patching and Sawcutfing for exterior work. ATTACHMENTS: Colvos Construction page 1 of 2 Printed On:10/15/2020 12:04 PM DocuSign Envelope ID:79DBA666-0691-4528-97F6-B32958885DAD ' Colvos PC® #004 Permit#C166-20 Mason Co Courts Remodel Bid Set Revision 1 090320.adf SA70 Series Security Grab Bars.pdf SA12 Security Recessed Toilet Tissue Roll kolder.pdf SA61 Security Framed Wall Mirror.Ddf Det-WC-Stiigie.adf _Det-Lay-Sinnle.Ddf _ASI#3:.Mason Co Permit Revisions.pdf. 275129 Two Way Emergency Communication Systems.pdf Commercial Wail Systems-ASI#03.pdf GPH-ASI#03 Plumbing.pdf 9-8 Mason Co Courthouse.odf Sunset Air ASI#03 Quote.pdf .West Valley ASI#03 UL Listed Analog System Quote, R1.adf CO#5 Add power and Fire Alarm to smoke Dampers.odf g Cost Code Description Type - Amount 1 10.28-13-Toilet Accessories Holding Cell Toilet Accessories other $957.00 2 09.2216-Non-structural Metal Framing Add➢onal GWB,Fire Taping,and Fire Caulk at T&B of Walls/Penetra➢ons Other $2,648.00 3 23.11-11-HVAC System Smoke Dampers,Rec.Duct Additional.Stub-Ins,Shop Labor.and Feld Labor Other $1,600.00 4 26.20-13-Building Electrical Two-Way Communication System Other $21,848.00 b 2240-01-Plumbing Backflow Preventer and(1)Backwater Valve Other $3.850,00 6 01-30-23-Project Engineer 24HoursofPE Time 0$701Hr for Processing. Other 51,880.OD 7 01-30-13-Project Superintendent 3 Days ofSupervisionforAddi➢onal Work Required Other S2,520.00 8 08-10.53=Rough Carpentry 16 Hours of CarpentarTime forTAC Install vidhin Holding Cells and Framing newwa➢for Other $1,280.00 Area of Refuge 9 08.11-16-Metal Doors and Frames Door 120A&1209 Other $3,982.00 10 08-11-a3-Installation Doors and frames Installation of Doors-120A&1208 Other $900.00 11 26.20-13-Building Electrical Power providedfor(2)SmokeDampers Other $2,150.00 12 01-3G-32-Fuel/Oil MalntI Parts: Fuel/M➢eage for 3Days Other, .$208.80 13 01-3049-ProiectManager 18 Hours ofPMTime - Other $1,840.00 14 01-30-26-PMectAdministration 4 Hours ofAdminTime Other $240.00 16 W41-13-Lumber LumberforAdd➢onal Walls at Area ofRefuge Other $320.00 16 0152-19-Sent Cans $10.84 Daily Rental Rate Other $31.92 17 01-74-19-.Dumpsfer $9.46 Dally Rental Rate Other $28.38 18 W-52-13-Temporary Feld Office $20.98 Daily Rental Rate Other $62.91 19 01-64 21-Man&Material Hoist $105 Daily Rental Rate Other $315.00 20 W-52-15-Storage $3 Daily Rental Rate Other $9.00 Subtotal: $46,369.01 - Bond:3.00%Applies to all line item types. $1.391.07 Liability Insurance:1.26%Applies to all line item types: $597.00 Contractor Fee:10.00%Applies to all line Item types. $4,635.71 B&O Tax:0.56 Applies to all line Item types. $308.52 Sales Tax:8.80%Applies to all line item types. $4,708.12 Grand Total: $56,209.43 Bruce McKean(Helix Design Group) . Mason County Colvos Construction 6021 12th St E.Suite 201 411 North 5th St 711 Court C Tacoma,Washington 98424 Shelton,Washington 98584 Tacoma,Washington 98402 " ..• DocuSigne�d�by. _ 11/19/2020 SIGNATURE DATE SIGNATURE DATE S DATE Colvos Construction page 2 of 2 Printed On:10/15/2020 12:04 PM coLvos PCO #004 Colvos Construction Project: -20-031 Mason County Courthouse 711 Court C 414 West Franklin St Tacoma,Washington 98402 Shelton,Washington 98584 Phone:(253)279-7887 Prime Contract Potential Change Order #004: ASI #03 - ADA Refuge Area, City Plumbing Updates, Holding Cell Updates TO: Mason County FROM: Colvos Construction 411 North 5th St 711 Court C Shelton,Washington 98584 Tacoma,Washington 98402 PCO NUMBERIREVISION: 004/0 CONTRACT: 1-20-031 Mason County Courthouse Prime Contract REQUEST RECEIVED FROM: CREATED BY: Casey Angeline (Colvos Construction) STATUS: Pending-In Review CREATED DATE: 10/7/2020 REFERENCE: PRIME CONTRACT None CHANGE ORDER: FIELD CHANGE: No LOCATION: ACCOUNTING Amount Based METHOD: SCHEDULE IMPACT: 3 days PAID IN FULL: No TOTAL AMOUNT $58,209.43 POTENTIAL CHANGE ORDER TITLE:ASI#03-ADA Refuge Area,City Plumbing Updates,Holding Cell Updates CHANGE REASON:Design Development POTENTIAL CHANGE ORDER DESCRIPTION:(The Contract Is Changed As Follows) See attached ASI#03 for following changes to occur in order to meet the requirements of the Remodel Permit Set. Based on ASI#03-Permit Revisions,the following cost includes the items listed below. 1. At the new Area of Refuge near Exit Door 120 the following items were added: 1. Additional wood framing and 5/8"GWB with Level 4 Finish at the 1 HR rated walls. This includes fire taping above ceiling space and fire caulking the top and bottom of walls/penetrations. 2. Door 120A and 120B(HM Doors and Frames with Hardware per Hardware Group 25) 3. (2)Fire Smoke Dampers(Sized per Plans) 4. (2)Rectangular Duct Adder Stub-In 5. Two-Way Comm.UL listed Analog System per RFI#24 2. (2)SA12 Security Toilet Tissue Holders 3. (2)SA01 Security Mirrors 12"x16" 4. (2)SA70 18"Security Grab Bars 5. (2)SA70 36"Security Grab Bars 6. (2)SA70 42"Security Grab Bars 7. (1)RectorSeal 4"Extendable Clean Checks Backwater valves at sewer line connections. This is with the assumption that the existing backwater valve can be replaced with the new one without having to tear into asphalt and patch back around the valve.Per RFI#29-the(2)shown backwater valves were not required. 8. (1)Backflow preventer to water service line-Zum Model 375 9. The cost associated for the separate toilet and sink equaled the cost for a toilettsink combo unit. Therefore no cost is associated with these items. Excludes: 1. Benches in Holding Cells 2. New Building Waste Tie-In to City Sewer per RFI#29 3. Any work that is not described within the ASI#03 Narrative by Helix. 4. Asphalt Patching and Sawcutting for exterior work. ATTACHMENTS: Colvos Construction page 1 of 2 Printed On:10/15/2020 12:04 PM coLvos PCO #004 Permit#C166-20 Mason Co Courts Remodel Bid Set Revision 1 090320.pdf SA70 Series Security Grab Bars.pdf SA12 Security Recessed Toilet Tissue Roll Holderpdf SA01 Security Framed Wall Mirror.i3df Det-WC-Sinole.pdf Det-Lay-Sinole.pdf ASI#3-Mason Co Permit Revisions.pdf 275129 Two Way Emergency Communication Systems.pdf Commercial Wall Systems-ASI#03.pdf GPH-ASI#03 Plumbina.pdf 9-8 Mason Co Courthouse.pdf Sunset Air ASI#03 Quote.pdf _West Valley ASI#03 UL Listed Analog System Quote R1.Ddf _CO#5 Add power and Fire Alarm to smoke Dampers.pdf # Cost Code Description Type Amount 1 10-28-13-Toilet Accessories Holding Cell Toilet Accessories Other $957.00 2 09-22-16-Non-structural Metal Framing Additional GWB,Fire Taping,and Fire Caulk at T&B of Walls/Penetrations Other $2,648.00 3 23-11-11-HVAC System Smoke Dampers,Rec.Duct Additional Stub-Ins,Shop Labor,and Field Labor Other $1,500.00 4 26-20-13-Building Electrical Two-Way Communication System Other $21,846.00 5 22.40-01-Plumbing Backflow Preventer and(1)Backwater Valve Other $3,850.00 6 01-30-23-Project Engineer 24 Hours of PE Time @$70/Hr for Processing Other $1,660.00 7 01-30-13-Project Superintendent 3 Days of Supervision for Additional Work Required Other $2.520.00 6 06-1M3-Rough Carpentry 16 Hours of Carpenter Time for TAG Install within Holding Cells and Framing new wall for Other $1,280.00 Area of Refuge 9 08-11-16-Metal Doors and Frames Door 120A&120B Other $3.982.00 10 08-11-83-Installation Doors and Frames Installation of Doors 120A&120B Other $900.00 11 26-20-13-Building Electrical Power provided for(2)Smoke Dampers Other $2,150.00 12 01-30-32-Fuel/Oil/Maint/Parts Fuel/Mileage for 3 Days Other $208.80 13 01-30-19-Project Manager 16 Hours of PM Time Other $1,840.00 14 01-30-26-Project Administration 4 Hours of Admin Time Other $240.00 15 06-11-13-Lumber Lumber for Additional Walls at Area of Refuge Other $320.00 16 01-52-19-San!Cans $10.64 Daily Rental Rate Other $31.92 17 01-74-19-Dumpster $9.46 Daily Rental Rate Other $28.38 18 01-52-13-Temporary Field Office $20.96 Daily Rental Rate Other $62.91 19 01-54-21-Man&Material Hoist $105 Daily Rental Rate Other $315.00 20 01-52-15-Storage $3 Daily Rental Rate Other $9.00 Subtotal: $46.369.01 Bond:3.00%Applies to all line item types. $1,391.07 Liability Insurance;1.25%Applies to all line item types. $597.00 Contractor Fee:10.00%Applies to all line item types. $4,835.71 B&O Tax:0.58%Applies to all line item types. $308.52 Sales Tax:8.80%Applies to all line item types. $4,703.12 Grand Total: $58,209.43 Bruce McKean(Helix Design Group) Mason County Colvos Construction 6021 12th St E,Suite 201 411 North 5th St 711 Court C Tacoma,Washington 98424 Shelton,Washington 98584 Tacoma,Washington 98402 SIGNATURE DATE '.SIGNATURE DATE SIGNATURE DATE Colvos Construction page 2 of 2 Printed On:10/15/2020 12:04 PM Colvos PCO #004 Colvos Construction Project: -20-031 Mason County Courthouse 711 Court C 414 West Franklin St Tacoma,Washington 98402 Shelton,Washington 98584 Phone:(253)279-7887 Prime Contract Potential Change Order #004: ASI #03 - ADA Refuge Area, City Plumbing Updates, Holding Cell Updates TO: Mason County FROM: Colvos Construction 411 North 5th St 711 Court C Shelton,Washington 98584 'Tacoma,Washington 98402 PCO NUMBERIREVISION: 004/0 CONTRACT: 1-20=031 Mason County Courthouse Prime Contract REQUEST RECEIVED FROM: CREATED BY: Casey Angeline (Colvos Construction) STATUS: Pending-In Review CREATED DATE: 10/7/2020 REFERENCE: PRIME CONTRACT None, CHANGE ORDER: FIELD CHANGE: No LOCATION: ACCOUNTING Amount Based METHOD: SCHEDULE IMPACT: 0 days PAID IN FULL: No Y-..-... TOTAL AMOUNT: $51,485.74 POTENTIAL CHANGE ORDER TITLE:ASI#03-ADA Refuge Area,City Plumbing Updates,Holding Cell Updates CHANGE REASON:Design Development POTENTIAL CHANGE ORDER DESCRIPTION:(The Contract Is Changed As Follows) See attached ASI#03 for following changes to occur in order to meet the requirements of the Remodel Permit Set. Based on ASI#03-Permit Revisions,the following cost includes the items listed below. -1. At the new Area of Refuge near Exit Door 120 the following items were added: 1. Additional wood framing and 5/8"GWB with Level 4 Finish at the 1 HR rated walls. This includes fire taping above ceiling space and fire caulking the top and bottom of walls/penetrations. 2. Door 120A and 120B(HM Doors and Frames with Hardware per Hardware Group 25) 3. (2)Fire Smoke Dampers(Sized per Plans) 4. (2)Rectangular Duct Adder Stub-In 5. Two-Way Comm.UL listed Analog,System per RFI#24 2. (2)SA12 Security Toilet Tissue Holders 3. (2)SA01 Security Mirrors 12"x16 4: (2)SA70 18"Security Grab Bars 5. (2)SA70 36"Security Grab Bars 6. (2)-SA70 42"Security Grab Bars 7. (1)RectorSeal 4"Extendable Clean Checks Backwater valves at sewer line connections. This is with the assumption that the existing backwater valve can be replaced with the new one without having to tear into asphalt and patch back around the valve.Per RFI#29-the(2)shown backwater valves were not required. 8. (1)Backflow preventer to water service line-Zum Model 375 9. The cost associated for the separate toilet and sink equaled the cost for a toilet/sink combo unit. Therefore no cost is associated with these items. Excludes: 1. Benches in Holding Cells 2. New Building Waste Tie-In to City Sewer per RFI#29 3. Any work that is not described within the ASI#03 Narrative by Helix. 4. Asphalt Patching and Sawcutting for exterior work. ATTACHMENTS: Colvos Construction- page 1 of 2 Printed On:10/30/2020 11:38 AM coLvos PC® ##004 Permit#C166-20 Mason Co Courts Remodel Bid Set Revision 1 090320.ndf _SA70_Series_Security_Grab_Bars.pdf SA12 Security Recessed Toilet Tissue Roll Holder odf SA01 Security_Framed Wall Mirror.odf Det-WC-Single.Ddf .Det-Lav-Single.odf ASI#3-Mason Co Permit Revisions.pdf 275129 Two Way Emergency Communication Systems.pdf Commercial Wall Systems-AS]#03.pdf. GPH-AS[#03 Plumbing.pdf 9-8 Mason Co Courthouse.Ddf _Sunset Air AS]#03 Quote.pdf West Valley AS]#03 UL Listed Analog System Quote R1.9df _CO#5 Add power and Fire Alarm to smoke Dampers.pdf # Cost Code Description Type _Amount 1 10-28-13-Toilet Accessories Holding Cell Toilet Accessories Other $957.00 2 09-22-16-Non-structural Metal Framing Additional GWB,Fire Taping,and Fire Caulk at T&B of Walls/Penetrations Other $2,648.00 3 23-11-11-HVAC System Smoke Dampers,Rec.Duct Additional Stub-Ins,Shop Labor,and Field Labor Other $1,500.00 4 26-20-13-Building Electrical Two-Way Communication System Other $21.846.00 5 2240-01-Plumbing Backilow Preventer and(1)Backwater Valve Other $3,850.00 6 01-30-23-Project Engineer 16 Hours of PE Time @$70/Hr for Processing Other $1,120.00 7 06-1053-Rough Carpentry 16 Hours of Carpenter Time for TAC Install within Holding Cells and Framing new wall for Other $1,280.00 Area of Refuge 8 08-11-16-Metal Doors and Frames Door 120A&120B - Other $3,982.00 9 08-11-83-Installation Doors and Frames Installation of Doors 120A&,120B Other $900.00 10 26-20-13-Building Electrical Power provided for(2)Smoke Dampers Other $2.150.00 11 01-30-19-Project Manager 4 Hours of PM Time Other $460.00 12 06-11-13-Lumber Lumber for Additional Walls at Area of Refuge Other $320.00 Subtotal: $41,013.00 Bond:3.00%Applies to all line item types. $1.230.39 Liability Insurance:1.25%Applies to all line Item types. $528.04 Contractor Fee:10.00%Applies to all line Item types. $4.277.14 B&O Tax:0,58%Applies to all line item types. $272.88 Sales Tax:8.80%Applies to all line item types. $4,164.29 Grand Total: $51,485.74 Bruce McKean(Helix Design Group) Mason County Colvos Construction 6021 12th St E,Suite 201 411 North 5th St 711 Court C Tacoma,Washington 98424 Shelton,Washington 98584 Tacoma,Washington 98402 l�v� �i l�' �•2� SIGNATU E DATE SIGNATURE DATE SIGNATURE DATE Colvos Construction page 2 of 2 Printed On: 10/30/2020 11:38 AM Colvos PCCO #004 Colvos Construction Project: - 20-031 Mason County Courthouse 711 Court C 414 West Franklin St Tacoma,Washington 98402 Shelton,Washington 98584 Phone: (253)279-7887 Prime Contract Change Order#004: Multiple PCO's (PCO #03004006,16917) TO: Mason.County FROM: Colvos Construction 411 North 5th St 711 Court C Shelton,Washington 98584 Tacoma Washington 98402 DATE CREATED: 1 0/26 12020 CREATED BY: . Casey Angeline(Colvos Construction) REVISION: 0 INVOICED DATE: PAID DATE: SCHEDULE IMPACT: A days ~ EXECUTED: No CONTRACT FOR: 1:20-031•Mason County Courthouse Prime TOTAL AMOUNT: $61,501.34 Contract DESCRIPTION: The following PCCO#04 encompasses all cost associated with PCCO#04 1. PCO#03-ASI#01-Mason Co.CH Service Revision :.2. PCO#04.-ASI#03-Permit Revisions 3. PCO#06-Main Electrical Gear Surge Protection 4. PCO#16-RFl#22:Seismic Will Upgrades at BOH and Restrooms 5. PCO#17-RFI#20:Wall to Arched Glulam Connection ATTACHMENTS: POTENTIAL CHANGE ORDERS IN THIS CHANGE ORDER: PCO# Title Schedule Impact _ Amount 003 ASI#01-Mason Co.CH Service Revision 0 days 3,534.21. . . 004 ASI#03-ADA Refuge Area,City Plumbing Updates,Holding Cell 0 days 51,485,74 Updates. 006 Main Electrical Gear Surge Protection Q days 2,301.07 , 016 RFI#22:Seismic Wall Upgrades at BOH and Restrooms 0 days 2,805.71" 017 RFI#20:Wall to Arched Glulam Connection 0 days 1,374.61 TOTAL $61,501.34 CHANGE ORDER LINE ITEMS: PCO#003:ASI#01=Mason Co.CH Service Revision # Cost Code Description Type Amount 1 26-20-13=Building Electrical Revisions to Electrical Services laborand material Other $2,776.00 2 01-30-23-Project Engineer (1)Hr of PE time @$70/Hr Other $70.00 Subtotal: $2,846.00 Bond:3.00%Applies to all line Item types. 85.38 Liability Insurance:1.25%Applies to all line hem types. 36.64 Contractor Fee:10.00%Applies to all line Item types. 296.80 B&O Tax:0.58%Applies to all line Item types. .18.94 Sales Tax:8.80%Applies to all line item types. 250.45 Grand Total: $3,534.21. Colvos Construction page 1 of 3 Printed On:11/4/2020 12:55 PM C®Lvos PCCO #004 PCO#004:ASI#0.3-ADA Refuge Area,City Plumbing Updates,Holding Cell Updates # Cost Code Description Type Amount 1 10-28-13-Toilet Accessones : Hot d(ng Cell Toilet Accessories Other $957.00 '2 09-22-16-Non-structural Metal Framing Additional GWB,Fire Taping,and Fire Caulk at T&B of Walls/Penetrations Other $2,648.00 3 23-11-11-HVAC System Smoke Dampers,Rec.Duct Additional Stub-Ins,Shop Labor,and Field Labor Other $1,500.00 4 26-20-13.Building Electrical Two-Way Communication System Other $21,846.00 5 22-40-01-Plumbing Baddiow Preventer and(1)Backwater Valve Other $3,850.00 6 01-30-23-Project Engineer 16 Hours of PE Time @$7011-ir for Processing Other $1,120.00 7 06 1053-Rough Carpentry 16 Hours of Carpenter Time The Install within Holding Cells and Framing new der 4 $1,260.00 wall far Area of Refuge 8 08-11-16-Metal Doors and Frames Door 120A&1209. Other - $3,982.00 9 08-11-83-Installation Doors and Frames Installation of Doors 120A&120B Other $900.00 10 26-20A3-Building Electrical Power provided for(2)Smoke Dampers Other $2,150.00 11 01-30-19-Project Manager 4 Hours of PM Time Other $460.00 12 06-11-13-Lumber Lumber for Additional Walls at Area of Refuge Other $320.00 Subtotal: $41,013.00 Bond:3.00%Applies to all line Item types. 1,230.39 Liability Insurance:US%Applies to all line Item types. 528.04 Contractor Fee:10.00%Applies to all line Item types. 4,277.14 9&0 Tax:0.58%Applies to all line item types. 272.88 Sales Tax:8.80%Applies to all line Item types. 4,164:29 Grand Total: $51,485:74 PCO#006:Main Electrical Gear Surge Protection #.. Cost Code Description Type Amount 1 26-20-13-Building Electrical Main Electrical Gear Surge Protection Other $1,833.00 . Subtotal: $1,833.00 • Bond,3.00%Applies to all line item types. 54.99 Liability Insurance:1.26%Applies to all line Item types. 23.60 Contractor Fee:10.00%Applies to all line Item types. 191.16 B&O Tax:0.58%Applies to all line Item types. 12.20 Sales Taxes:8.80%Apples to all line Item types. 186.12 Grand Total: $2,301.07 PCO#016:RFI#22t Seismic Wall Upgrades at BOH and Restrooms . #. Cost Code Description: Type Amount. 1 06-11-13 Lumber Additional Lumber for Seismic Wall behind Women's Restrooms - - Other $700.00 2 06-10-53-Rough Carpentry Labor to Install Seismic Wall behind Women's Restrocm Other $1.280.00 3 01-30-23-Project Engineer PE Time Other $140.00 4 01-30-19-Project Manager. PM Time Other $115.00 Subtotal: $2,235.00 Bond:3.00%Applies to all line item type''. 67.05 .Liability Insurance:1.25%Applies to all line item types. 28.78 Contractor Fee:10.00%Applies to all line item types. 233.08 B&O Tax:0." Applies to all line item types. 14.87 Sales Tax:8.80%Applies to all line item types. 226.93 Grand Total: $2,805.71 Colvos Construction page 2 of 3 Printed On:11/4/2620 12:55 PM