HomeMy WebLinkAboutChange Order # 001 for Colvos Construction DocuSign Envelope ID:77E29FEF-F1E7-4A17-9EC5-E74661714C37
colvos PCCO #001
:PaA TFusT6.f
Colvos Construction Project: - 20-031 Mason County Courthouse
711 Court C 414 West Franklin St
Tacoma,Washington 98402 Shelton,Washington 98584
Phone: (253)279-7887
Prime Contract Change Order #001: Asbestos Abatement
TO: Mason County FROM: Colvos Construction
411 North 5th St 711 Court C
Shelton,Washington 98584 Tacoma Washington 98402
DATE CREATED: 8/26/2020 CREATED BY: Scott Fletcher(Colvos Construction)
REVISION: 0
INVOICED DATE: PAID DATE:
. ... . ....
SCHEDULE IMPACT. 21 days EXECUTED: No
CONTRACT FOR: 1:20-031 Mason County Courthouse Prime TOTAL AMOUNT: $79,577.54
Contract
DESCRIPTION:
CE#001-Asbestos Abatement
Inclusions:
Below is the detailed cost for the additional abatement required per the Hazardous Building Material Survey completed on July 23rd.
The report was provided after the project bid date,the following work to remove and dispose is included:
1. (4)mobilizations for phased abatement during construction
2. (110)asbestos containing Y or 4"mudded pipe fittings
3. (95)asbestos containing 6"mudded pipe fitting and tees
4. (17,200 SF)of asbestos containing vinyl floor tile and black mastic
5. (32 LF)of asbestos containing window frame sealant
6. (960 SF)of asbestos roofing removal where new RTU units will be installed
7. (14)roof penetrations through asbestos containing roofing for gas lines and vent pipes as shown on M300 of the architectural plan set dated
7.17.2020
8. (24 LF)black duct sealant
9. (650 SF)asbestos containing cement board
10. (520)mercury containing florescent light tubes
11. (2Bo)PCB containing light fixtures
12. (5)exist signs
13, (6)smoke detectors
The fallowing additional items are required due to the abatement removal:
1. (21)Calendar day or,(15)working day schedule impact
2. (24)9'and(5)4'new LGT type strip fixtures that Is originally to be saved per DE201,and will need to be replaced with new
3. Insulate(7)roof drain piping
4. (15)working days or(21)calendars days of original site supervision,project management,laborer and associated costs
5. Add to complete demo 5 days sooner than the original 20 working day delay due to abatement
6. Mandatory asbestos awareness training
Exclusions:
1. Other hazardous material other than listed above is not included and will bean extra cost for removal if found during demolition.
2. WSST
ATTACHMENTS:
POTENTIAL CHANGE ORDERS IN THIS CHANGE ORDER:
PCO# Title Schedule Impact Amount
001 1 CE#001-Asbestos Abatement 121 days 79,577.54
TOTAL: $79,5T7.54
CHANGE ORDER LINE ITEMS:
Colvos Construction page 1 of Printed On:8131/2020 02:34 PM
DocuSign Envelope ID:77E29FEF-F1 E7-4A17-9EC5-E74661714C37
c lvos Pcco #001
PCO#001:CE#001-Asbestos Abatement
a Cost Code Description Type Amount
1 02.61-23.-Asbestos Abatement Hazardous Material Abatement ogler $68,32mou
2 01-30-13-Project Superintendent 15 Workng Days of site supervision during demolition Other $12,600.00
3 01-30-23-Project Engineer 8 Working Days of Project Engineer time Other $4,490,00
4 0130-19-Project Manager 5 Working Days of Project Manager time Other $4,600.00
5 01-74-13-Continuous Cleanup 5 days of additional Laborer time Other $2,800.00
6 0t-30-26-Project Administration 6 Days or Project Administrative Time Other $2.880,00
7 01-52-13-Temporary Field Office Rentals Dab trailer and sankans) Other $500.00
8 01-30.31-Truck IMileage Mileage and Fuel Other $2,000,00
9 22-4041-Plumbing Roof Drain Insulation Other $1,150.00
10 ZHO-01-Lighting New required lights due to disposal from asbestos report Other $01011,00
11 02-41-30-Demolition .Add to complete the demo/abatement 5 days sooner Other $9,951.00
12 01-52-17-Safety Supplies I Inspections Asbestos awarenosa training Other $2.500.00
13 'OZ-61-23-Asbestos Abatement Original abatement allowance, Other ($50,W0.00)
Subtotal: $68,969.0D
Bond:&0811.Applies to all line item types, 2,069,07
Uabiiity,Insurance:1.26%Applies to all tine item types. 687.98
Contractor Fee:11100°4 Applies to all line item types, 7,192.60
86O Tax:0.58%Applies to all line item types. 468,89
Grand Total: $79,577.54
The original(Contract Sum) $2,216,218.00
Net change by previously authorized Change Orders $ 0.00
The contract sum prior to this Change Order was $2,216,218.00
The contract sum Would be changed by this Change Order in the amount of $79,577.54
The new contract sum including this Change Order will be $2,295,795.54
The contract time will be increased by this Change Order by 21 days
Bruce McKean(Helix Design Group) Mason County Colvos Construction Ds
6021 12th St E,Suite 201 411 North 5th St 711 Court C S�
Tacoma Washington 98424 Shelton Washington 98584 Tacoma Washington 96402
DocuSigned by:
ram" c� �oZp 8/31/2020
SIGNATURE DATE NA3U DATE 6WA3+t R&4E2... DATE
Cobos Construction page 2 of 2 Printed On:8131/2020 02:34 PM
r