This checklist is intended to assist Staff in the review of a Stormwater Plan. The Stormwater Plan is
reviewed for completeness with respect to the 1992 Department of Ecology Manual. If an item is found to
be not applicable, the Plan should explain the basis for the conclusion.The Plan is also reviewed for
clarity and consistency. If the drawings, discussion, or recommendations are not understandable, they
should be clarified. If they do not appear internally consistent or consistent with the application or
observations on site, this needs to be corrected or explained. If resolution is not achieved with the author,
staff should refer the case to the Planning Manager or Director.
Applicant's Name: f rnCJ
Permit# Parcel# fr.:)Ita7 03V0® O
Date(s)of the Document(s) reviewed:
(1) Erosion and Sediment Control:All new development and redevelopment that includes land
disturbing activities of one acre or greater shall comply with erosion and sediment control
requirements 1-14, below. Compliance with the Erosion and Sediment Control Requirements
shall be demonstrated through implementation of a large parcel erosion and sediment control
plan.
All new development and redevelopment that includes land disturbing activities of less than one
acre shall comply with the small parcel minimum requirements found in Section 14.48.130,
Compliance with the small parcel requirements shall be demonstrated through implementation of
a small parcel erosion and sediment control plan.
(a) Erosion and Sediment Control Requirement 1: Stabilization and Sediment Trapping.
OK? L,*^ Comment:
(b) Erosion and Sediment Control Requirement#2: Delineate Clearing and Easement Limits.
OK? Comment:
(c) Erosion and Sediment Control Requirement#3: Protection of Adjacent Properties.
OK? ✓ Comment:
(d) Erosion and Sediment Control Requirement#4: Timing and Stabilization of Sediment
Trapping Measures.
OK? I,,- Comment:
(e) Erosion and Sediment Control Requirement#5: Cut and Fill Slopes.
OK? b-'- Comment:
(f) Erosion and Sediment Control Requirement#6: Controlling Off-Site Erosion.
OK? 1� Comment:
(g) Erosion and Sediment Control Requirement#7: Stabilization of Temporary Conveyance
Chang Is and Outlets.
� OK. y Comment:
(h) Erosion and Sediment Control Requirement#8: Storm Drain Inlet Protection.
OK?_J,,-' Comment:
(i) Erosion and Sediment Control Requirement#9: Underground Utility Construction.
OK? 1/ Comment:
0) Erosion and Sediment Control Requirement#10: Construction Access Routes.
OK?_ Comment:
(k) Erosio and Sediment Control Requirement#11: Removal of Temporary BMPs.
OK? Comment:
(1) Erosion and Sediment Control Requirement#12: Dewatering Construction Sites.
Page 1 of 3 Form Effective May 2009
OK? t"'_ Comment:
(m) Erosion and Sediment Control Requirement#13: Control of Pollutants Other than Sediment
on fpastruction Sites.
OK? Comment:
(n) Erosion and Sediment Control Requirement#14: Maintenance.
OK? V-�Comment:
(o) Erosion and Sediment Control Requirement#15: Financial Liability.
OK?_�/Comment:
(2) Preservation of Natural Drainage Systems. Natural drainage patterns shall be maintained, and
discharges fir m the site shall occur at the natural location to the maximum extent practicable. -
OK? L--� Comment:
(3) Source Control of Pollution. Source control BMPs shall be applied to all projects to the
maximum extent practicable. Source control BMPs shall be selected, designed, and maintained
according to an approved manual.
OK?__Z,,::f_C omment:
(4) Runoff Treatment BMPs. All projects shall provide treatment of stormwater. Treatment BMPs
shall be sized to capture and treat the water quality storm, defined as the six-month, twenty-four
hour storm.The first priority for treatment of stormwater shall be to infiltrate as much as possible
of the water quality design storm into the ground. Pretreatment of stormwater prior to infiltration
into the�Gnd may be required.
OK? Comment:
(5) Streambank Erosion Control: The requirement below applies only to situations where
stormwater runoff is discharged directly or indirectly to a stream, and must be met in addition to
meeting the quirements in minimum requirement#4, Runoff Treatment BMPs.
OK?omment:
(6) Wetlands: Stormwater discharges to wetlands shall maintain the wetland's natural hydroperiod
and flows to the extent needed to preserve or enhance its existing functions and values. Prior to
proposing discharge of higher volumes of stormwater to a wetland, alternative discharge,
detention, and infiltration practices located in areas outside the wetland shall be evaluated and
employ01"yComment:
the project engineer where feasible and practicable.
OK?
(7) Water Quality Sensitive Areas. Where the Mason County commissioners or their designee
determine that the minimum requirements do not provide adequate protection of water quality
sensitive areas, either on-site or within the basin, more stringent controls shall be required to
protect water quality. An adopted and implemented basin plan (minimum requirement#9) may be
used to develop requirements for water quality sensitive areas that are tailored to a specific basin.
OK? V Comment:
(8) Off-Site Analysis and Mitigation. Downstream analysis may trigger additional requirements.
The project engineer shall provide a detailed qualitative analysis of the flow path of the discharge
from the project site to the receiving water. This requirement shall apply to all projects where a
drainage and erosion control plan is prepared, including those proposing retention facilities. This
analysis shall include flow routing, and provide existing pipe and channel sizes and estimated
capacities. In addition, the project engineer shall discuss any known or expected downstream
erosion, flooding, or water quality problems, including those that may be caused by interflow from
the proposed retention facility. The director or designee shall have the discretion to specify the
distance and level of detail to be provided by the project engineer. In making this determination,
the director or designee shall consider such factors as the relative size of the new development,
availability of other hydrologic work for the drainage area, and the extent of which stormwater
genemto on the project site is to be infiltrated.
OK? V Comment:
Page 2 of 3 Form Effective May 2009
i
(9) Basin Platt in . Basin plan supersedes Manual.
OK? P' Comment:
(10) Operation and Maintenance. An operation and maintenance schedule shall be provided for all
proposed stormwater facilities and BMPs, and the party(or parties) responsible for maintenance
and operation shall be identified. An operation and maintenance(O&M)covenant will be required
to cover all privately owned and maintained stormwater facilities approved by the director. O&M
Covenant forms are available at the Mason County Public Works Office. A copy of the completed
instrument shall be recorded with the Mason County Auditor's Office by the proponent and a copy
of the recorded instrument is required to be submitted to the Public Works Department prior to
final appro of the completed permanent stormwater facilities.
OK? V Comment:
(11) Financial Liability. Performance bonding or other appropriate instruments shall be required for
all proj�ct,�fo ensure compliance with these standards.
OK? yy Comment:
Are the Documents signed and stamped?hO_.
Type and#of License:.
If not approved, what is the next action/recommendation for further action?
ed s�
Reviewed by
Time spent in review:
SE OND REVIEW/UPDA E:
5 o ,_
Reviewed by ' Y , on n L7
Time spent in second revi w:
THIRD REVIEW/UPDATE:
Reviewed by on
Time spent in third review:
Disclaimer: Mason County does not certify the quality of the work done in this Stormwater Plan.
Page 3 of 3 Form Effective May 2009
1
Masson County Stormwater Checklist
MD Project# : l
Project Name Algrn q Nrtr»n Cn w 20/! EJgiT'N �RT�)?l AL D/SFt7s�c}L SirE
Twnsp,Sec,Range Svc.. 27 T 24 tl R 3 w ua.Irv, .
Minimum Requirements of 1992 Stormwater Manual
The stormwater checklist identifies the minimum requirements of the 1992
Stormwater Manuat. The checklist is intended to identify the locations within the plan
that addresses the minimum requirements. Mason County wilt not perform a technical
evaluation of the submittal. Rather, the checklist provides a guide to allow Mason
County to review the submittat and determine if the applicant has addressed the
minimum features that make up a stormwater plan.
It is incumbent upon the applicant and his/her engineer to fulfill all the applicable
requirements of the 1992 Stormwater Plan as it relates to the proposed project.
Review by Mason County is intended to determine if the plan has addressed the
minimum requirements. Applicant's engineer shall be responsible for the technical
accuracy of the submitted Stormwater plan.
During construction of the project, the stormwater plan engineer of record or his/her
authorized representative shall inspect the site to ensure the stormwater plan is being
implemented as designed. Upon completion of the project, the engineer or his
authorized representative shall be required to certify that the stormwater plan has
been implemented as designed.
Failure to meet the minimum requirements could result in delay or rejection of the
application until the deficiencies are corrected.
#1: Erosion and Sediment Control.All new development and redevelopment that
includes land disturbing activities of one acre or greater shalt comply with erosion and
sediment control requirements 1 through 14, below. Compliance with the Erosion and
Sediment Control Requirements shalt be demonstrated through implementation of a
large parcel erosion and sediment control plan.
All new development and redevelopment that includes land disturbing activities of less
than one acre shall comply with the small parcel minimum requirements found in
Section 14.48.140, Compliance with the small parcel requirements shall be
demonstrated through implementation of a small parcel erosion and sediment control
plan.
Erosion and Sediment Control Requirement#1: Stabilization and Sediment
Trapping. S o�.-1 T---- A f
See rage/paragraph�C .� 5 �5• �'o U h'sn ! PQ
Erosion and Sediment Control Requirement#2: Delineate Clearing and
Easement Limits.
See Page/Paragraph et-4 54-F 5;: Column I ; aaaj e:&ph A
Stormwater Cheddist DOE 1992 Manual.doc i
Updated May 20,2009
I
Erosion and Sediment Control Requirement#3: Protection of Adjacent
Properties.
See page/paragraph .2me,4 5 e F 6 /umm f 15 Phaaa✓wi1 $-
Erosion and Sediment Control Requirement#4:Timing and Stabilization of
Sediment Trapping Measures.
See page/paragraph oaf s Colttvn n 1,: i70-4M,&rm A 4
61
Erosion and Sediment Control Requirement#5• Cut and Fill Slopes.
See page/paragraph 5--, Co/u rn n 1 ; P"as re 1, A 5'
Erosion and Sediment Control Requirement#6: Controlling Off-Site Erosion.
See page/paragraph 5h cc;�' 5 dF S; Q(t%vrn n 1 ; PG,vi,..a rsp 6 R•!o
Erosion and Sediment Control Requirement#7: Stabilization of Temporary
Conveyance Channels and Outlets.
See page/paragraph $hea+ 5 o�5 ; Co I u.nn l ; por•ea.,%v%Lip(i A7
Erosion and Sediment Control Requirement#8: Storm Drain Inlet Protection.
See page/paragraph Jh ae+ 17 v wu, 1 • Paso 4�[•a�v� /�8
Erosion and Sediment Control Requirement#9: Underground Utility
Construction.
See page/paragraph .5heek- r2 5 ;Cg(avy�n I ; py-n-!� 'r V% 9
Erosion and Sediment Control Requirement#10: Construction Access Routes.
See page/paragraph 5he-e-�- tj orr 7i Go(ta.Y.N e-1 A fO
Erosion and Sediment Control Requirement#11: Removal of Temporary BMPs.
See page/paragraph Shu�r S 0415 Co lyYr.%v, l; Va-^ma m Ipp-A It
Erosion and Sediment Control Requirement#12: Dewatering Construction Sites.
See page/paragraph 51nac- - 07c4 5., CtI c,.. nyl, l% Po-•�a �r O� ,A IZ
Erosion and Sediment Control Requirement#13: Control of Pollutants Other
than Sediment on Construction Sites.
See page/paragraph SheP—� ri 652' Lc,(c�r,n rX 1� a ro►g ra.►�
Erosion and Sediment Control Requirement#14: Maintenance.
See page/paragraph Sf,f-e-+fio•FS-;Cot(A vti,v� i: ?b4g4p j,4
Erosion and Sedim�r�eennt Control Requirement#15• Fin racial Liabilipy.
See page/paragraph S/x3e.-1- Sa•F 5 : fo/u�>7 !r /'ara►gys.,oh A l�
#2: Preservation of Natural Drainaae Systems. Natural drainage patterns shall be
maintained, and discharges from the site shall occur at the natural location to the
maximum extent practicable.
Seepage/paragraph. Co1 a trot &Ia rneh L3
Stormwater Cheddist DOE 1992 Manuat.doc 2
Updated May 20, 2009
El#3: Source Control of Pollution. Source control BMPs shall be applied to all
projects to the maximum extent practicable. Source control BMPs shalt be selected,
designed, and maintained acqxdHng to an approved manual.
See page/paragraph 5 he e-- 5 o.V.".n 2,: ?&Mo. ,r4L V'A, C
#4: Runoff Treatment BMPs. All projects shall provide treatment of stormwater.
Treatment BMPs shall be sized to capture and treat the water quality storm, defined
as the six-month, twenty-four hour storm. The first priority for treatment of
stormwater shalt be to infiltrate as much as possible of the water quality design storm
into the ground. Pretreatment of stormwater prior to infiltration into the ground may
be required. ����
See page/paragraph 15 0�7jr ( o I g.,r,rn
#5: Streambank Erosion Control.The requirement below applies only to situations
where stormwater runoff is discharged directly or indirectly to a stream, and must be
met in addition to meeting the requirements in minimum requirement#4, Runoff
Treatment BMP's.
See page/paragraph 04-5 • E�i�.�,.,� Po.�a-��Tti.
#6: Wetly Stormwater discharges to wetlands shalt maintain the wetland's
natural hydroperiod and flows to the extent needed to preserve or enhance its existing
functions and values. Prior to proposing discharge of higher volumes of stormwater to
a wetland, alternative discharge, detention, and infiltration practices located in areas
outside the wettand shalt be evaluated and employed by the project engineer where
feasible and practicable.
See page/paragraph-:5 4 �--' , off' co l"m v, Z : 94 M, F
#7: Water Quality Sensitive Areas. Where the Mason County commissioners or
their designee determine that the minimum requirements do not provide adequate
protection of water quality sensitive areas, either on-site or within the basin, more
stringent controls shall be required to protect water quality. An adopted and
implemented basin plan (minimum requirement#9) may be used to develop
requirements for water quality sensitive areas that are tailored to a specific basin.
See pall/paragraph `thee-k-- 15 %IQ 5 1; 5,_sh t y.v,,h Z : �o..«, a�k.6r
#8: Off-Site Analysis and MitbwtlOn. Downstream Analysis May Trigger Additional
Requirements.The project engineer shalt provide a detailed qualitative analysis of the
flow path of the discharge from the project site to the receiving water.This
requirement shalt apply to all projects where a drainage and erosion control plan is
prepared, including those proposing retention facilities. This analysis shall include flow
routing, and provide existing pipe and channel sizes and estimated capacities. In
addition, the project engineer shalt discuss any known or expected downstream
erosion, flooding, or water quality problems, including those that may be caused by
interim from the proposed retention facility.The Director of Public Works or
designee shall have the discretion to specify the distance and level of detail to be
provided by the project engineer. In making this determination, the Director of Public
Works or designee shalt consider such factors as the relative size of the new
development, availability of other hydrologic work for the drainage area, and the
extent to which stormwater generated on the project site is to be infiltrated.
Stormwater Cheddist DOE 1992 Manuat.doc 3
Updated May 20,2009
See page/paragraph :jlnc.eAr* S .4 S; Ca l
if9: Basin Planning. Basin plan supersedes Manual „
See page/paragraph -*k r-i.rrF2 CaX ..,Z Panes
a#10: Operation and Mair>tienance. An operation and maintenance schedule shall be
Provided for all proposed stormwater facilities and BMPs, and the party (or parties)
responsible for maintenance and operation shall be identified. An operation and
maintenance(OftM) Declaration of Covenant will be required to cover all privately
owned and maintained stormwater facilities. OB.M Declaration of Covenant forms are
available at the Mason County Permit Assistance Center,426 W. Cedar Street, Shelton,
WA 98584.The proponent shall record a copy of the completed Declaration with the
Mason County Auditors'office. A copy of the recorded document must be submitted
to the Permit Assistance Center tooethpr wIW this completed Cheddist.
See page/paragraph Sh cc--\- Cc&uv,,
i certify that the stormwater plan submitted for this project fulfills the applicable
Provisions of the 1992 Stormwater Manual.
- Zoi (
Engineer Date
7
Applicant Date
Place signed Stamp Here
14144 P�►
a � OS4@�W ��46JA1. Ec
Stwmwater Checklist DOE 1992 Manuat.doc 4
Updated May 20,2009
I