HomeMy WebLinkAboutSEP2003-00089 - SEP Determinations Stft o MASON COUNTY
�p c DEPARTMENT OF COMMUNITY DEVELOPMENT
O
4 MO
Planning Division
i N T L? P O Box 279,Shelton,WA 98584
�0J Y ao" (360)427--9670
1864
DETERMINATION OF NONSIGNIFICANCE
(WAC 197-11-340)
SEP2003-00089
Description of Proposal: Grading and recontouring of a 5-acre site. Filling and grading of
approximately 860 cubic yards.
Proponent: DAVE COOPER
Location of Proposal:
Parcel Number: 123217500050
Legal Description: LOT 5 OF OVERTON LARGE LOT SUBDIVISION
Directions to Site: SR 3 PAST BELFAIR, LEFT OF LOG YARD RD, DEEP TO
RIGHT FOR 3/10 MILE, PROPERTY ON RIGHT
Lead Agency: Mason County
The Lead Agency for this proposal has determined that it does not have a probable significant
adverse impact on the environment. An Environmental Impact Statement (EIS) is not required
under RCW 43.21 C.030(2)(c). This decision was made after review of a completed
Environmental Checklist and other information on file with the Lead Agency. This information is
available to the public upon request.
Please contact Rick Mraz at ext. 577 with any questions.
This DNS is issued under 197-11-340(2), the Lead Agency will not act on this proposal for 14
days from the date below. Comments must be submitted to Rick Mraz, C/O Mason County DCD,
Planning Divisi n, x 279, Shelton WA 98584 by 9/24/2003.
A ocal Govern nt Official Date
PLANNING
MASON COUNTY
ENVIRONMENTAL CHECKLIST
Purpose of Checklist:
The State Environmental Policy Act(SEPA),chapter 43.21C RCW,requires all governmental agencies to
consider the environmental impacts of a proposal before making decisions. An environmental impact
statement(EIS)must be prepared for all proposals with probable significant adverse impacts on the
quality of the environment. The purpose of this checklist is to provide information to help you and the
agency identify impacts from your proposal(and to reduce or avoid impacts from the proposal, if it can be
done)and to help the agency decide whether an EIS is required.
Instructions for Applicants:
This environmental checklist asks you to describe some basic information about your proposal.
Governmental agencies use this checklist to determine whether the environmental impacts of your
proposal are significant,requiring preparation of an EIS. Answer the questions briefly,with the most
precise information known,or give the best description you can.
You must answer each question accurately and carefully,to the best of your knowledge. In most cases,
you should be able to answer the questions from your own observations or project plans without the need
to hire experts. If you really do not know the answer,or if a question does not apply to your proposal,
write "do not know" or"does not apply". Complete answers to the questions now may avoid unnecessary
delays later.
Some questions ask about governmental regulations, such as zoning, shoreline,and landmark
designations. Answer these questions if you can. If you have problems,the governmental agencies can
assist you.
The checklist questions apply to all parts of your proposal,even if you plan to do them over a period of
time or on different parcels of land. Attach any additional information that will help describe your
proposal or its environmental effects. The agency to which you submit this checklist may ask you to
explain your answers or provide additional information reasonably related to determining if there may be
significant adverse impact.
Use of Checklist for Non-project Proposals:
Complete this checklist for non-project proposals,even though questions may be answered"does not
apply". IN ADDITION,complete the SUPPLEMENTAL ACTIONS(Part D).
There is a$T1 fee required for the processing of the checklist. Please make your check payable to
"Mason County Treasurer."
For non-project actions,the references in the checklist to the works "project", "applicant",and "property
or site" should be read as "proposal", "proposer",and"affected geographic area",respectively.
MASON COUNTY ENVIRONMENTAL CHECKLIST
Page 1
A. BACKGROUND:
1. Name of proposed project,if applicable:
Transfer station for Cooper's Fuel
2. Name of Applicant:
Dave Cooper
3. Address&phone number of applicant&contact person:
Dave Cooper, 3236 Wheaton Way, Bremerton, WA 98310, (360)377-4100, cell(360)340-1931
Contact person: Marley L. Young, Consulting Engineer, (360)426-7475
4. Date checklist prepared:
August 27, 2003
5. Agency requesting checklist:
Mason County--Dept. of Community Development
6. Proposed timing or schedule(including phasing,if applicable):
Phase I, Clearing-ASAP
Phase II—October, if weather permits
7. Do you have any plans for future expansion,or further activity related to or connected with this
proposal? If yes,explain.
No
8. List any environmental information you know that has been prepared,or will be prepared,
directly related to this proposal.
Do not know �r, ls�„�
9. Do you know whether applications are pending for governmental approvals of other proposals
directly affecting the property covered by your proposal? If yes,explain.
None
10. List any governmental approvals or permits that will be needed for your proposal,if known.
Mason County Land Modification Permit
11. Give a brief,complete description of your proposal,including the proposed uses and the size of
the project and site. There are several questions later in this checklist that ask you to describe
certain aspects of your proposal. You do not need to repeat those answers on this page. (Lead
agencies may modify this form to include additional specific information on project description.)
Dave Cooper provides a home heating oil delivery service and is proposing development
of a transfer site on a 5-acre lot. The entire lot will be recontoured, and approximately four
acres will be contoured so that stormwater will,flow to a retention pond. The remaining one acre
will be allowed to sheet,flow to the private road. The transfer site to be developed contains
approximately 1.6 acres.
The operation consists of receiving product by tanker truck and transferring that product
directly to the Cooper's Fuel delivery trucks. When the tanker truck is empty it leaves the site.
The site would not have any permanent storage for heating oil above or below ground.
The public would not be served at this site. A camp trailer will serve as a small office for
the drivers to complete paperwork There are no sanitary sewers or storm sewers in the area. A
portable toilet will be provided for sanitation facilities.
12. What is the location of the proposal? Give sufficient information for a person to understand the
precise location of your proposed project,including a street address,if any,and section,
township,and range,if known. If a proposal would occur over a range of area,provide the range
or boundaries of the site(s). Provide a legal description,site plan,vicinity map,and topographic
map,if reasonably available. While you should submit any plans required by the agency,you are
not required to duplicate maps or detailed plans submitted with any permit applications related to
this checklist.
The site is located on Log Yard Road NE, Beffiair, Washington, which is accessed from
SR 3. Legal Description: Lot 5 of Survey recorded under Auditor's File 1773853 Records of
Mason County Washington and being a portion of the NE'/.of the SE'/.of Section 21, Township
23 North, Range I West, W.M, Mason County, Washington.
Assessor's Parcel No. 1232175 00050
B. ENVIRONMENTAL ELEMENTS:
1. EARTH:
a. General description of the site(circle one): Flat,rolling,hilly,steep slopes,mountainous,
other
b. What is the steepest slope on the site(approximate percent slope)?
5 to 10%
C. What general types of soils are found on the site(for example,clay,sand,gravel,peat,muck)? If
you know the classification of agricultural soils,specify them and note any prime farmland.
The soils found on the site are classified as Alderwood gravelly sandy loam(Ab), 5-15 percent
Slopes
d. Are there surface indications or history of unstable soils in the immediate vicinity? If so,
describe.
No.
e. Describe the purpose,type,and approximate quantities of any filling or grading proposed.
Indicate source of fill.
Approximately 860 yards of grading and approx. 200 yards of filling(from the grading activity).
Purpose is to recontour the property and to build a stormwater retention infiltration pond and
construct the access road. Material is local on site.
f. Could erosion occur as a result of clearing,construction,or use? If so,generally describe.
No. Sediment control measures will be put in place to minimize the migration of silt and/or soil,
by the use of silt fencing filters or other measures as recommended.
2
g. About what percent of the site will be covered with impervious surfaces after project
constructions(for example,asphalt or buildings)?
40'x 80'Concrete pad
h. Proposed measures to reduce or control erosion,or other impacts to the earth,if any:
Erosion control measures such as silt control fences will be constructed as needed to control
erosion
2. AIR:
a. What types of emissions to the air would result from the proposal(i.e.,dust,automobile,odors,
industrial wood smoke)during construction and when the project is completed? If any,generally
describe and give approximate quantities,if known.
Dust and vehicle emissions during construction. After construction, minimal dust and vehicle
emissions generated by trucks during the exchange of oil from truck to truck during regular oil
transfer activity-
b. Are there any off-site sources of emissions or odor that may affect your proposal? If so,generally
describe.
No
C. Proposed measures to reduce or control emissions or other impacts to air,if any:
None
3. WATER:
a. Surface:
1) Is there any surface water body on or in the immediate vicinity of the site(including year-
round and seasonal streams,saltwater,lakes,ponds,wetlands)? If yes,describe type and provide
names. If appropriate,state what stream or river it flows into.
No
2) Will the project require any work over,in,or adjacent to(within 200 feet)of the described
waters? If yes,please describe and attach available plans.
No
3) Estimate the amount of fill and dredge material that would be placed in or removed from
surface water or wetlands and indicate the area of the site that would be affected. Indicate the
source of fill material.
None
4) Will the proposal require surface water withdrawals or diversions? Give general description,
purpose,and approximate quantities if known.
No
5) Does the proposal lie within a 100-year floodplain? If so,note location on the site plan.
No
6) Does the proposal involve any discharges of waste materials to surface waters? If so,describe
the type of waste and anticipated volume of discharge.
No
3
b. Ground:
1) Will ground water be withdrawn,or will water be discharged to ground water? Give general
description,purpose,and approximate quantities, if known.
No
2) Describe waste material that will be discharged into the ground from septic tanks or other
sources,if any(for example,Domestic sewage: Industrial,containing the general size of the
system,the number of such systems,the number of houses to be served(if applicable),or the
number of animals or humans the system(s)are expected to serve.
None
C. Water Runoff(including stormwater):
1) Describe the source of runoff(including storm water)and method of collection and disposal,
if any(include quantities,if known). Where will this water flow? Will this water flow into other
waters? If so,describe.
Stormwater Control Plan is designed to retain and detain runoff from the fill slope and all
surface discharge at rates that satisfy the streambank erosion control requirements.
Stormwater will notflow into other waters.
2) Could waste materials enter ground or surface waters? If so generally describe.
No—This project does not generate waste water.
d. Proposed measures to reduce or control surface,ground,and runoff water impacts,if any:
Erosion control features will be constructed as needed during site construction. Silt control
fences and check dams will be used to control impacts. A sediment pond will be constructed and
used during construction. Permanent retention pond, grassway swale and oilAvater separator
will be installed to collect and infiltrate any surface water runoff.
4. PLANTS:
a. Check or circle types of vegetation found on the site:
X deciduous tree: alder, maple,aspen,other
X evergreen tree: fir, cedar,Aine,other
_ shrubs
X Qrass
_ pasture
_ crop or grain
_ wet soil plants: cattail,buttercup,bulrush,skunk cabbage,others
_ water plants: water lily,eelgrass,milfoil,other
X other types of vegetation—salal:scotch broom
b. What kind and amount of vegetation will be removed or altered?
Most of the five-acre area is expected to be cleared of vegetation.
C. List threatened or endangered species known to be on or near the site.
None
d. Proposed landscaping,use of native plants,or other measures to preserve or enhance vegetation
on the site, if any:
Native vegetation(grass)will be allowed to return to the site
4
5. ANIMALS:
a. Circle any birds and animals which have been observed on or near the site or are known to be on
or near the site:
birds: hawk,heron,eagle,songbirds,other
mammals: deer; ar,elk,beaver,other squirrels,chipmunks
fish: bass,sa on,trout,herring,shellfish,other
b. List any threatened or endangered species known to be on or near the site.
None
C. Is the site part of a migration route? If so,explain.
Do not know
d. Proposed measures to preserve or enhance wildlife,if any:
None
6. ENERGY AND NATURAL RESOURCES:
a. What kinds of energy(electric,natural gas,oil,wood stove,solar)will be used to meet the
completed projects energy needs? Describe whether it will be used for heating,manufacturing,
etc.
Does not apply
b. Would your project affect the potential use of solar energy by adjacent properties? If so,
generally describe.
No
C. What kinds of energy conservation features are included in the plans of this proposal? List other
proposed measures to reduce or control energy impacts,if any:
None
7. ENVIRONMENTAL HEALTH:
a. Are there any environmental health hazards,including exposure to toxic chemicals,risk of fire
and explosion,spill,or hazardous waste,that could occur as a result of this proposal? If so,
describe.
Yes—Potential for heating oil spill
1) Describe special emergency services that might be required.
Fire Department
2) Proposed measures to reduce or control environmental health hazards, if any:
Spill control plan and the proposed spill containment plan attached to questionairre.
b: Noise:
1) What types of noise exist in the area which may affect your project(for example:traffic,
equipment operation,other)?
None
2) What types of levels of noise would be created by or associated with the project on a
short-term or a long-term basis(for example: traffic,construction,operation,other)?
Indicate what hours noise would come from the site.
5
Noise from construction sources can be anticipated during site development. Occasional
vehicle noise will occur during transfer of product.
3) Proposed measures to reduce or control noise impacts,if any:
None
8. LAND AND SHORELINE USE:
a. What is the current use of the site and adjacent properties?
The site is undeveloped and is in scrub and second growth trees. Adjacent properties are also
undeveloped and in scrub and second growth trees. The pr erty across Log Yard Road is
developed to industrial use. (`� cam UO.`c k E �� ���I
b. Has the site been used for agriculture? If so,describe.
No
C. Describe any structures on the site.
None
d. Will any structures be demolished? If so,what?
No
e. What is the current zoning classifiqation of the. ' ?
The site to be developed isI Type I,
MArl
a
f. What is the current comprehensive plan designation of the site?
The site is within the Urban Growth Area boundary of Belfair,Mason County.
g. If applicable,what is the current shoreline master program designation of the site?
Does not apply
h. Has any part of the site been classified as an "environmentally sensitive"area? If so,specify.
No
i. Approximately how many people would reside or work in the completed project?
Site would be manned intermittently and only during working hours. Two truck drivers would be
on site during product transfer only.
j. Approximately how many people would the completed project displace?
None
k. Proposed measures to avoid or reduce displacement impacts,if any:
Does not apply
1. Proposed measures to ensure the proposal is compatible with existing and projected land uses and
plans,if any:
Completion of Environmental Checklist.
6
9. HOUSING:
a. Approximately how many units,if any,would be provided? Indicate whether high,middle,or
low income housing.
Does not apply
b. Approximately how many units,if any,would be eliminated? Indicate whether high,middle,or
low income housing.
Does not apply
C. Proposed measures to reduce or control housing impacts,if any:
Does not apply
10. AESTHETICS:
a. What is the tallest height of any proposed structure(s),not including antennas;what is the
principal exterior building material(s)proposed?
No permanent structures will be constructed
b. What views in the immediate vicinity would be altered or obstructed?
None
C. Proposed measures to reduce or control aesthetic impacts,if any:
None
11. LIGHT AND GLARE
a. What type of light or glare will the proposal produce? What time of day would it mainly occur?
None
b. Could light or glare from the finished project be a safety hazard or interfere with view?
No
C. What existing off-site sources of light or glare may affect your proposal?
None
d. Proposed measures to reduce or control light and glare impacts, if any:
None
12. RECREATION:
a. What designated and informal recreational opportunities are in the immediate vicinity?
None
b. Would the proposed project displace any existing recreational uses? If so,describe.
No
C. Proposed measures to reduce or control impacts on recreation,including recreation opportunities
to be provided by the project or applicant,if any:
None.
7
13. HISTORIC AND CULTURAL PRESERVATION:
a. Are there any places or objects listed on,or proposed for,national,state,or local preservation
registers known to be on or next to the site? If so generally describe.
No
b. Generally describe any landmark or evidence of historic,archaeological,scientific,or cultural
importance known to be on or next to the site.
None
C. Proposed measures to reduce or control impacts,if any:
None
14. TRANSPORTATION:
a. Identify public streets and highways serving the site and describe proposed access to the existing
street system. Show on site plans,if any.
Log Yard Road, which is a private paved road
b. Is site currently served by public transit? If not,what is the approximate distance to the existing
street system. Show on site plans,if any.
Does not apply because the public will not use the site.
C. How many parking spaces would the completed project have? How many would the project
eliminate?
Does not apply
d. Will the proposal require any new roads or streets,or improvements to existing roads or streets,
not including driveways? If so,generally describe(indicate whether public or private).
No
e. Will the project use(or occur in the immediate vicinity of)water,rail,or air transportation? If so
generally describe.
No
f. How many vehicular trips per day would be generated by the completed project? If known,
indicate when peak volumes would occur.
Approximately 6 per day
g. Proposed measures to reduce or control transportation impacts, if any.
None
15. PUBLIC SERVICES:
a. Would the project result in an increased need for public service(for example:fire protection,
police protection,health care,schools,other)? If so generally describe.
No
b. Proposed measures to reduce or control direct impacts on public services,if any:
None
8
16. UTILITIES
a. Circle utilities currently available at the site: electricity,natural gas,water,refuse service,
telephone,sanitary sewer,septic system,cable television,other.
None
b. Describe the utilities that are proposed for the project,the utility providing the service,and the
general construction activities on the site or in the immediate vicinity which might be needed.
None
17. SIGNATURE:
The above answers are true and complete to the best of my knowledge. I understand that the lead
agency is relying on them to make its decision.
Signature:
(N e&Title/Company
Date Submitted: 03
9