HomeMy WebLinkAbout25-02 - Res. County Road Project 1728 MASON COUNTY
COMMISSIONERS RESOLUTION NO. : 25 - 02
COUNTY ROAD PROJECT NO. : 1728
WHEREAS, on Mason County Road No . 10000 , known locally as the Cloguallum Road , and more specifically
located in Section 36 , Township 19 North, Range 6 West WM M.P . 18 . 77, work defined as 'construction " in the
BARS Manual, Page U-63 , et seq, is determined to be necessary and proper, and,
WHEREAS , this project is identified as # 4 on the officially adopted County Annual Road Program.
THEREFORE, BE IT RESOLVED BY THE BOARD OF COUNTY COMMISSIONERS that it is their
intention to :
Perform preliminary engineering and construction for bank stabilization on county road adjacent to
Cloquallum Creek.
SAID WORK is to be performed by contract in accordance with the Washington State Standard
(day labor/contract)
Specifications for Road and Bridge Construction as adopted by Mason County,
BE IT FURTHER RESOLVED that the above described County Road Project is necessary and proper, and the
estimated costs of said project are herewith set out as follows :
Preliminary. Engineering $ 300 . 00
Right-of--Way $ —
Road Construction $ 100 ,000 . 00
The County Road Project herein described is HEREBY DECLARED to be a public necessity, and the County Road
Engineer is HEREBY ORDERED AND AUTHORIZED to report and proceed thereon as by law, provided and in
accordance with WAC 13648 .
ADOPTED this 12h day of March , 2002 .
BOARD OF COUNTY COMMISSIONERS
MASON COUNTY, WASHINGTON
Chairperson
Commissioner
ATTEST : Absent 1 bs t 3 / 2 / 02
_ Commissioner